County of Albemarle
Department of Community Development
Memorandum
To:
Megan Yaniglos, Senior Planner
From:
Phil Custer, Engineering Review
Date:
February 8, 2011
Subject:
SUB - 2011 -00006 Old Trail Block 23 Final Plat
The Final Plat for Old Trail Block 23 (SUB- 2010 - 00006), received 18 January 2011, has been reviewed.
Engineering can recommend approval to the plat after the following comments have been addressed.
1. All bonds (water + sewer, ESC, and Road) must be paid prior to the signing of this plat. In most
cases where the lots are for a multifamily development, an approved final site plan doubles as a
road plan (assuming the Chief of Current Development approves the private street with the Zoning
Ordinance standards). At this time, no final site or ESC plan has been provided and the plat
doesn't match the approved preliminary plat. For these reasons, additional comments may be
necessary as the final site plan is submitted and reviewed by all agencies. To receive a bond
amount, the applicant must provide a Bond Estimate Request to the County Engineer when all
plans have been approved. [14- 302.A.3, 14 -233, 14- 234,14- 303.E, 14 -412, 14 -435]
2. The private street must be authorized. To have this private street authorized please follow the
procedure outlined in 14 -234. If waivers of road standards are needed for the subdivision, they
should be requested at that time. [14 -234, 14- 412.B]
3. The plat referenced by the deedbook and page number for Golf Drive does not appear to actually
dedicate the ROW to public use. It seems to designate the road as an easement. Was there a latter
plat or other document that dedicated this ROW? If not, a deed of dedication may be necessary
prior to the approval of this subdivision plat for Block 23.
4. There is a drainage easement on Lot 13 that was platted with DB 3442 PG 188 that needs to be
vacated with this document, assuming the construction documents relocate this drainage system.
[14- 302.A.5]
5. Show the sidewalk and utility easement on the front of the property that was recorded with 3442
PG 188. [14- 302.A, 14- 303.E]
6. It is anticipated that sight distance easements on Lots 1 and 13 will be needed based on where the
existing easement/ROW line has been platted. The site plan assumed the ROW line to be lft off
of the sidewalk, where it is normally placed. [14- 303.L]
7. The private street statement of 14 -303.N needs to be included on the plat.
8. The payment of the Lickinghole Basin fee for this block must be paid prior to the approval of a
subdivision plat or final site plan.
9. The stream buffer statement of 14- 302.B.10 needs to be included on the plat. Please also show the
location of the pond water surface elevation so the accuracy of the buffer line can be verified.
E1_fpt_PBC_SUB- 20 1 1 -00006 Old Trail Block 23 Final Plat.doc