Loading...
HomeMy WebLinkAboutWPO201000057 Review Comments Erosion Control Plan 2011-02-15� OF AL ,. vIRGI1`IZP COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902 -4596 Phone (434) 296 -5832 Fax (434) 972 -4126 Project: Avinity ESC Plan [WP0201000057] Plan preparer: Scott Collins [scott @collins- engineering.com] Owner or rep.: Avon Properties, LLC Plan received date: 9 September 2010 (Rev. 1) 29 November 2010 (Rev. 2) 27 January 2011 Date of comments: 24 October 2010 (Rev. 1) 11 January 2011 (Rev. 2) 15 February 2011 Reviewer: John P. Diez — Engineering Technician Phil Custer — Civil Engineer (Rev. 1) Phil Custer Engineering has reviewed the first revision to the ESC plan associated with the Avinity site plan (WPO- 2010- 00057), received 27 January 2011. The review of the site, road, and stormwater plans will be provided in a separate comment letter. 1. It appears that E &S measures are not within the limit of disturbance for Phases 2 and 3. (Rev. 1) Comment has been addressed. 2. The height of the embankment is acceptable as long as it designed to meet the dimensions of VSMH 3.01. 3. The invert out of the principal spillway barrel does not match the SB Details on Sheet ESC -4. Please revise. (Rev. 1) Please refer to comment 12.e. (Rev. 2) Comment has been addressed. 4. Please rotate the baffle 10 degrees clockwise in Phase III to lengthen the flow path. (Rev. 1) Comment has not been addressed. My original comment probably could have been clearer. Since the majority of the watershed in phase III will be entering the basin through the pipe from structure 12, lengthening the distance this discharge must travel is important. The baffle should be modified to provide a longer flow path by placing the northend of it between the riser and outlet of the pipe from structure 12. (Rev. 2) Comment has been addressed. Please add a construction entrance to the Phase III ESC sheet. The construction entrance should be placed on the east side of the crest in the entrance road so it can drain back to a sediment trapping measure. Show construction road stabilization from the west side of the crest to Avon Road and note that vehicle washoff will occur so runoff will drain to the sediment basin. (Rev. 1) Comment has been addressed. Engineering Review Comments Page 2 of 4 6. Avinity Court and Lots 87 -93 should not be constructed in Phase III. As proposed, there will not be enough area for the staging, stockpiling of soil, and parking to construct all of the work proposed in Phase IV. (Rev. I) This comment is being withdrawn only because the applicant has assured me that the property is roughly balanced with regard to the cut and fill at the end of Phase III. The county inspector has the ability to modify phasing lines if the cut and fill calculation was in err and a stockpile is necessary adjacent to the basin. 7. In order for the project to continue on to Phase III of the ESC plan, the upstream watershed must be stabilized. Therefore, in Phase IV, please reduce the limits of construction to the remaining portion of the site (east of lots 44 and 74 and between Avinity Loop). All ESC measures in the other sectors of the project should be removed (IP, CE, etc.). A construction entrance for the Phase IV work should be provided as well as a diversion on the north end of the limits of construction. (Rev. I) Comment has been addressed. 8. The ESC measures proposed to protect Phase IV construction (IP and SF) are not adequate for the watershed and the amount of work required in this phase. I recommend breaking Phase IV into two phases. In Phase IVA, Avinity Court, lots 87 -100, and the detention facility would be constructed. Below this work the sediment basin would be filled in and converted to a sediment trap sized for the upstream watershed (-2 acres). Once this area has been stabilized, the rest of the work to finish the site can be performed using silt fence and inlet protection for the smaller watershed. (Rev. I) This sheet is acceptable except that a CE is still required in phase V. (Rev. 2) Comment has been addressed. 9. Since this is presumably the final WPO application for Avinity, please remove the final sentence of the note at the top of sheet ESC -313 and step 13 in the construction sequence. (Rev. I) Comment has not been addressed. Please remove this note wherever it exists. (Rev. 2) Comment has been addressed. 10. In Phase III and Phase IV, please provide diversion dikes east of lots 56 and 86 directing runoff into the sediment basin and trap. (Rev. I) Comment has been addressed. 11. Please update the standard county ESC notes that can be found in the latest edition of the design manual, available online. (Rev. I) Comment has been addressed. 12. The county offers the following comments regarding the MS -19 analysis: a. The discharge numbers used in the MS -19 analysis are based on the hydrologic data of the drainage and SWM plans that will be reviewed at a later date. Whenever a necessary correction to these hydrologic assumptions or calculations is noticed during the review of the MS -19 analysis, it will be commented on. However, a more detailed review will be undertaken later for the site drainage and swm plans. If issues are discovered during the review of these plans that affect the MS -19 calculations, updates to these calculations will be needed and additional comments may be required. (Rev. I) Corrections to the SWM plan are still necessary. (Rev. 2) Comment has been addressed. b. If the area used for the time of concentration from post - development drainage area IA is excluded will a greater discharge be the result? If yes, please exclude this area from the analysis. (Rev. I) The flow path for the post- development scenario begins in a grass channel sloped at >l0 %, not sheet flow. It appears the minimum time of concentration of 6min should be used. (Rev. 2) Please disregard comments. Engineering Review Comments Page 3 of 4 c. The drainage area limits and flow path for the south end of drainage areas 2 and 3 do not appear to be realistic. Both of these lines should be drawn perpendicular to contour lines (DA limits on the ridge and the flow paths in the swales). But in many instances, these lines create acute angles with topography. Please correct and update the time of concentration calculations. (Rev. 1) Comment has been addressed. d. The calculations indicate that the existing culvert under Avon Street Extended may not be adequate to convey the 10 -year storm. This existing structure will not be acting as a culvert, but a drainage pipe as calculated on sheet DP -7. In these calculations, the hydraulic capacity of this pipe is — 22cfs. Also, the provided topography shows that the outlet to this culvert is around 559, not 554, which would significantly reduce the capacity of the pipe. It appears that the existing culvert and some of the other proposed pipes in this area must be increased in diameter. (Rev. 1) Comment has been addressed. However, please remove any reference to proposed work at the base of this culvert or provide proof of permission that this work is authorized. An existing utility easement to ACSA will not suffice. (Rev. 2) Comment has been addressed. e. The barrel for the sediment basin has been set with the mass grading plan and appears to be over a foot below the lowest elevation at the property line. Grading offsite will be necessary to achieve positive drainage. Please provide a detail of the proposed downstream channel. (Rev. 1) There cannot be a sump at the outlet of the sediment basinlswm facility. This will create a mosquito habitat that will negatively affect the public's health, safety, and wellness. Please remedy this condition with this plan. (Rev. 2) Comment has been addressed. Please provide an analysis between the stream and the property line at the outlet of the 24" pipe. There appears to be a very poorly- defined, shallow riprap channel that may not be able to convey the 10 -year storm within its banks. This channel terminates at a 30" tree —1 Oft from the stream. Where the riprap stops before the stream is a critical area and will likely erode with the increased volume of water due to development. The western portion of TMP 90 -35L appears to be filled in at some time since the survey. (Rev. 1) A riprapped channel has been installed by the contractor under WPO -2005- 00001. However, this channel stops at least 20ft short of the stream and is not indicative of the remainder of this reach. Please analyze the section between the stream and the end of the riprapped channel. When the SWM facility is modified per SWM comment 7, adequacy of the existing channel above its confluence with the stream will be easier to prove. Please also correct any reference to the riprap channel at this outlet to specify it as being existing, not proposed. (Rev. 2) Comment has been addressed. However, a temporary construction easement must be obtained for the offsite work. g. The existing condition in the field at the front of the site, specifically at the southwest corner, does not match the survey. (Rev. 1) Comment has been addressed. Engineering Review Comments Page 4 of 4 h. Cross - section 7 is not typical of the downstream condition of the outlet of the 15" VDOT culvert west of Avon Street Extended. There is no defined channel. (Rev. 1) The applicant has claimed that the volume and peak discharge is being reduced in the post- development situation and therefore MS -19 is no longer a requirement. I have checked the applicant's calculations comparing the pre and post - development hydrology to the west and confirmed that the post- development volume and discharge for the 2 and 10 year storm are lower than the pre- development, given the applicant's assumptions for these drainage areas. However, the grading at the front of the site does not concentrate any part of this area to the yard drains. Modifications to the grading plan to assure that the drainage area delineations of SWM -2 and DP -1 are established in the field are necessary. Please provide spot elevations throughout the area establishing a deep enough sump condition for each grate on the yard inlets and specify the type of inlet. VDOT will need to approve this private drainage system within their ROW The drainage areas shown by the applicant on sheet SWM -2 and DP -I does not match the drainage area shown on ESC -4. Also, please provide a profile of this system to confirm it can be constructed to structure 90. The front of lots 1 -10 differ between ESC -4 and S -1, S -2, etc. Please clarify. (Rev. 1) Comment has been acknowledged i. For both the pre - development and post - development drainage area sheets, please specify the acreage and hydrologic coefficient for the portion of drainage area 2 that is on site. Please send Phil updated pdfs of these drainage area sheets before addressing 12.h. (Rev. 1) Please see the previous comment. (Rev. 2) Comment has been acknowledged 13. The ESC bond will be computed at the time of plan approval. (Rev. 1) To receive an ESC bond estimate, please submit the Bond Estimate Request Form to the County Engineer after the ESC plan is approved. (Rev. 1) Comment has been acknowledged 14. (Rev. 1) ESC measures and limits will need to be adjusted based upon the requirement of constructing a paved walking trail to Cale Elementary School per Proffer 3, unless waived by the Albemarle County School Board. (Rev. 2) Comment has been addressed. \\ Cob- dts01 \cityviewlnk\Docs \2010 \WPO \WPO201000057 - Avinity - Final \CDE3- esc_PBC_Avinity WPO- 2010- 00057.doc