WPO201100004 Review Comments 2011-03-08
BOND ESTIMATE - EROSION CONTROL PROJECT NAME: PROJECT NUMBER: DATE OF ESTIMATE ESTIMATE BY: BASED ON: The Covenant School W PO201 100011 03/03/11 MRG Approved plan WATER ITEM DESCRIPTION UNIT QUANTITY UNIT COST ITEM TOTAL SEED, FERTILIZE, MULCH ACRE 0.3 1500 450 SILT FENCE LF 100 5 500 SAFETY FENCE LF 0 3 0 TEMPORARY FILL DIVERSION LF 0 3 0 DIVERSION DIKE LF 0 3 0 TEMPORARY SLOPE DRAIN LF 0 20 0 SEDIMENT TRAP 1 ACRES 0 1000 0 SEDIMENT BASIN 1 ACRES 0 1000 0 CULVERT INLET PROTECTION EA 0 500 0 INLET PROTECTION EA 0 200 0 OUTLET PROTECTION EA 0 200 0 EC -2 & 3 DITCH PROTECTION LF 0 10 0 RIP -RAP LF 0 55 0 CHECK DAMS SQ.YD. 2 30 60 PAVED CONSTRUCTION ENTRANCE EA 1 2000 2000 subtotal 3010.00 project management 451.50 subtotal 3461.50 CONTINGENCY LS 10% 346.15 TOTAL 3807.65 BOND AMOUNT REQUIRED 3900.00 last revised:12 -5 -01