HomeMy WebLinkAboutWPO200900061 Review Comments Mitigation Plan 2011-04-15� OF AL
,. vIRGI1`IZP
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
Project: North Pointe Stream Crossing [WPO- 2009 - 00061]
Plan preparer: Mr. James Fulcher; TEC Inc. and Field Works
Owner or rep.: Neighborhood Investments, NP, LLC
Developer: Charles Rotgin; North Pointe Charlottesville, LLC c/o Great Eastern Management
Company
Plan received date: (Rev. 2) 17 March 2011
(Rev. 1) 25 October 2010
7 December 2009
Date of comments: (Rev. 2) 15 April 2011
(Rev. 1) 23 November 2010
14 January 2010
Reviewer: Phil Custer
The second resubmittal of the Mitigation Plan for the North Pointe Stream Crossing project, submitted on
17 March 2011, has been reviewed. The following comments must be addressed before approval of the set
is given:
1. The current plan does not appear to consider all proposed impacts to the buffer according to the
latest ESC plan. Since the December 7`" submittal, a sediment trap and new channel have been
added within the buffer and must be accounted for. Also, please consider the encroachment of the
turn lane into the stream buffer in your calculation of buffer impacts. Use the limits of
disturbance from both ESC plans prepared by WW Associates to determine the total buffer
impacts for this portion of the North Pointe project.
(Rev. 1) Figure 5 does not match Figure 6 with regard to the stream buffer disturbance around
the culvert crossing. Figure 6 is correct. Also, the existing crossing should be excluded from the
disturbed buffer calculations. The "South" disturbance area does not need to be mitigated
because stormwater conveyance channels are permitted in the buffer with county approval per 17-
318.B.5 and 17- 318.C.6 Should "50,215sf" in Section 1.2 be "88,165sf "? This number would
have to be updated based on issues raised earlier in this comment.
(Rev. 2) Comment has been addressed. The plan shows the correct amount of linear
streambank work and buffer plantings, summarized in Table 2, to mitigate for the disturbances
proposed under ESC applications WPO- 2009 - 00061, WPO- 2009 - 00067, and WPO- 2010 - 00017.
2. The side slopes of the stream crossing cannot be counted towards the total mitigation area. [17-
320-D.5] Also, the ESC plan for this stream crossing has a proposed groundcover proposed for
the side slopes to meet county requirements. The engineering division of the Community
Development Department is concerned a proposed forested condition on the 2:1 slopes would
experience more erosion than a woody groundcover.
(Rev. 1) This area of the site has been removed from the proposed plan.
3. An Army Corps of Engineers permit will be required prior to construction for the stream
restoration plans. If the applicant feels they do not need a permit for the proposed work, please
provide confirmation from an Army Corps of Engineer representative after submitting this package
Albemarle County Community Development
Engineering Review Comments
Page 2 of 3
to them.
(Rev. 1) When it is received, please forward Army Corps approval of the streambank work as
described on page 31 of the report.
(Rev. 2) Army Corps approval for the streamwork has not yet been approved. The mitigation
plan cannot be completely approved by the county until the application to the Army Corps is
acceptable to them.
4. Please provide a table summarizing proposed buffer impacts and proposed mitigation areas
(including the stream restoration equivalency outlined in the design manual). Considering the
increased impacts as identified in comment 1 and the prohibition of using the road side slopes as
called out in comment 2, it is our estimation that the total opportunities on site for mitigation will
not be enough to meet the requirements. Engineering review will allow the plan to be approved
short of the required 2:1 ratio if it appears that the applicant is providing mitigation in all other
practicable areas. (However, if a County Mitigation bank is established before plan approval, the
applicant will be required to pay into this bank for the mitigation that could not be provided on
site.) Additional areas of possible mitigation include streamwork at the confluence of Flat Branch
and the unnamed tributary north of the crossing (and other possible eroded banks north of the
culvert), the removal of the pond embankment, and VDOT outlet stabilization along Flat Branch.
(Rev. 1) On page 30 of the Mitigation Narrative, the design manual states that "I' of restored
channel for every I00sf of disturbed area" is a mitigation option. This implies that every Ift
linear feet of channel restoration is equivalent to 200sf of required planting.
If the 12,000sf "North" section is not approved as part of the permanent stormwater management
facility, it must be replanted. This replanted area can be counted towards total mitigation
requirements.
The county currently does not have a mitigation bank set up and cannot accept any payment for
buffer disturbance. It appears as though the applicant has not exhausted all opportunities along
Flat Branch. As noted in the County's Stream Assessment performed in 2003 and shown on page
29 of the narrative, there are erosion downstream of the roadway culvert. I expect there are
ample opportunities from road culvert to the river. The county assessment notes bank erosion and
buffer issues.
The cross - sections on pages 33, 34, and 35 are not clear in Figure 23 and it is very difficult to
decipher where along the stream which cuts are proposed. Two of these sections do not show any
construction (streambank 2 and Streambank 3. If these designations correspond to Figure 23
then it appears that only 295ft of bank stream restoration is actually occurring.
(Rev. 2) Comment has been addressed. The plan shows the correct amount of linear
streambank work and buffer plantings, summarized in Table 2, to mitigate for the disturbances
proposed under ESC applications WPO- 2009 - 00061, WPO- 2009 - 00067, and WPO- 2010 - 00017.
Areas C and D appear to be isolated by steep slopes. Please detail how the areas are to be accessed
in order to be bushhogged. If grading or clearing of forest or trees is necessary, the work will need
to be included in the stream crossing ESC plan.
(Rev. 1) Comment has not been addressed.
(Rev. 2) It is still unclear how access to the planted areas (now A, B, and C) will be provided.
This concern has been increased since the last submittal because much more streamwork has
been added. The streamwork will require excess soil to be hauled away which will require new
access roads from the stream to areas of the site already covered by ESC plans. Either this
mitigation plan or the appropriate ESC plans should be modified to show how the necessary
equipment can access the more remote areas of the mitigation work. The plan (or plans) that
Albemarle County Community Development
Engineering Review Comments
Page 3 of 3
alleviates the access concerns should clearly state that existing buffer vegetation is to be
preserved (except in Areas A, B, and C) as much as possible and that all haul roads should be
protected with ESC measures where appropriate. If Area A is to be accessed from Area B, an
appropriately size Stream Crossing should be detailed in the plan. It looks as though the work
on the east side of the stream can be accessed by a graded roadbed that runs adjacent to the
diversion dike and fill diversion on WPO- 2010 - 00017, which means the stream work must be
performed before Phase II of this plan. The work on the west side of the stream appears to be
accessible from the south end of the turn lane work of WPO- 2009 - 00067.
6. Please show the ESC measures, limits of disturbance, and replanting plan for the construction
necessary to perform the stream channel restoration. For instance, how will the work within the
existing forest be performed without damaging trees that must remain? I suspect there will need to
be a temporary access road provided through the forest adjacent to the stream to haul away excess
sediment. How will this road be cleared, protected from erosion, and replanted?
(Rev. 1) Comment has not been addressed. Will the ESC plan be updated to include the
mitigation work?
(Rev. 2) Please refer to the previous comment.
7. The bond for the mitigation plantings will be computed at the time of plan approval.
(Rev. 1) Comment remains unchanged.
(Rev. 2) Comment remains unchanged.
8. (Rev. 2) Please provide the minimum specifications for the EC -2 matting to be used on the
streambank. Some variations of EC -2 matting used for general ESC purposes may not be
adequate for the stream bank stabilization.
E3_mp_PBC_North Pointe Stream Crossing_wpo200900061.doc