HomeMy WebLinkAboutSUB200900062 Review Comments Road Plan and Comps. 2011-03-17Philip Custer
From: DeNunzio, Joel D., P.E. [ Joel .DeNunzio @VDOT.virginia.gov]
Sent: Thursday, March 17, 2011 2:54 PM
To: Philip Custer
Cc: Frank Pohl
Subject: FW: Wickham Phase II WPO- 2007 -00017
Phil,
I have reviewed the referenced plan and have the following comments:
1. The proposed Filterra units will need to have a maintenance agreement between Albemarle County and VDOT to
permit the units within the right of way. A sample agreement can be found at the VDOT website under the SSAR
Regulations.
2. Pavement striping along the outside edge of Route 240 for the right turn lane needs to be added to the plan on both
sides of the proposed entrance.
A Land Use Permit issued by VDOT needs to be acquired prior to any construction within the Route 240 right of
way
Please let me know if you have any questions or comments.
Thanks
Joel
From: Denunzio, Joel D., P.E.
Sent: Wednesday, September 19, 2007 11:58 AM
To: 'Allan Schuck'
Subject: FW: Wickham Phase II WPO- 2007 -00017
Allan,
We have received the revised sheets and all of our comments have been addressed. A permit will be required for work
within the VDOT ROW and can be obtained from my office.
Thanks,
Joel
Joel DeNunzio, P.E.
Staff Engineer
434 - 293 -0011 Ext. 120
joel.denunzio @VirginiaDOT.org
From: Denunzio, Joel D., P.E.
Sent: Wednesday, July 18, 2007 9:08 AM
To: 'Allan Schuck'
Subject: Wickham Phase II WPO- 2007 -00017
Wickham Phase II WPO- 2007 -00017
Allan,
I reviewed the latest Wickham II plan and have a couple small items:
• In the June 15th reply, #9 says that Wickham Place station 10 +00 to 15 +00 and 22 +00 to the end are 25 mph.
The plans look like 22 +00 to the end is 20 mph and I think that 20 mph for this section is correct. Please verify these
speeds for me.
• The right turn lane east of the proposed entrance has the curb and gutter coming out to route 240 and making a
9 foot turn lane. Both the thru lane and the turn lane need to be 11 feet. It actually looks like we need a small amount of
pavement widening here for the lanes to be correct.
No changes are necessary for the first comment other than verifying the design speeds. The second comment only
applies to sheets 4, 6, 8, and 13. 1 don't need an entire new set of plans. These sheets can be revised and sent to me
and I will insert them into the plan set.
Thanks,
Joel
Joel DeNunzio, P.E.
Staff Engineer
434 - 293 -0011 Ext. 120
joel. den unzio @Virginia DOT. orq