Project: Ch'ville H.S. Stadium Turf Replacement ESC Plan [WP0201100046]
Plan preparer: Craig Kotarski [CRAIG.KOTARSKI @TIMMONS.COM]
Owner or rep.: City of Charlottesville
Plan received date: 18 July 2011
Rev 1: 28 July 2011
Date of comments: 22 July 2011
Rev 1: 10 August 2011
Reviewer: John P. Diez — Engineering Technician
Engineering has reviewed the E &S plan associated with the Ch'ville H.S. Stadium Turf Replacement
received 28 July 2011. The plan meets the minimum requirements of the County Ordinance.
A. Erosion and Sediment Control (WP0201100046)
i. It appears that there is some discrepancies with the plans and the GIS. Please provide date and
source of the topographic information: All topography should be at least visually field verified by
the designer within the last year.
(Rev. 1) Comment has been addressed.
B. Stormwater Management Plan (WP0201100046)
2. Please provide a drainage area map and topography for the proposed Filterras.
(Rev. 1) Comment has been addressed.
3. Additional comments may be forthcoming once the plans have been resubmitted.
(Rev. 1) Comment has been addressed.
The Erosion & Sediment Control and Stormwater Management Plans (WP0201100046)
submitted 28 July 2011 have received Engineering Review and meet Albemarle County minimum
checklist items for approval.
A completed copy of the Standard Stormwater Maintenance Agreement and fee for recordation for
the stormwater facilities is required prior to final approval.[17 -304E] The forms and instructions
can be found on the Community Development Department Web site on www.albemarle.org.
You may contact Ana Kilmer (Albemarle County Department of Community Development) at ext.
3246 for further information on bonding procedures and Maintenance Agreements.
Once the E &SC bond and the SWM bond have been posted, you may contact the Department of
Community Development to arrange a pre - construction meeting with a County Erosion &
Sediment Control Inspector. Should the County Inspector find the limits of disturbance increased
or the need for additional control measures required to protect the site, additional fees will be
required.