HomeMy WebLinkAboutWPO201100042 Review Comments Bond Estimate 2011-08-19PROJECT NAME:
Crown BMW Retail Parts & Service Building
FILE #:
WPO- 2011 -00042
DATE APPROVED:
Pending
Item
Unit
Amount
Unit Cost
Subtotal
Filterra 4x6
each
3
$8,100.00
$24,300
Filterra 4x12
each
1
$12,900.00
$12,900
Filterra 6x8
each
1
$11,700.00
$11,700
Filterra Installation
per project
5
$12,225
Stormfilter 1 (2 cartridges)
each
1.00
$9,020.00
$9,020.00
from engineer
Stormfilter 2 (3 cartridges)
each
1.00
$11,550.00
$11,550.00
from engineer
Stormfilter 3 (3 cartridges)
each
1.00
$11,550.00
$11,550.00
from engineer
Stormfilter Installation
per project
3
$8,030
CM underground detention
each
1.00
$68,000.00
$68,000
from engineer
detention installation
each
1.00
$34,000.00
$34,000
(50% of cost of facility)
subtotal
$203,M
project management
$30,491
subtotal
$233,766
10% Contingency
$23,377
TOTAL
$257,143
ROUNDED TOTAL
$257,200
min total after reduction
$515440