HomeMy WebLinkAboutWPO201100012 Review Comments Bond Estimate 2011-11-02BOND ESTIMATE - EROSION CONTROL Spreadsheet last revised:12 -5 -01 PROJECT NAME: West Leigh Water Main Replacement - Phase 2 PROJECT NUMBER: WP0201 1 0001 2 DATE OF ESTIMATE: 06/23/11 ESTIMATE BY: MRG BASED ON: Approved plan WATER ITEM DESCRIPTION UNIT QUANTITY UNIT COST ITEM TOTAL SEED, FERTILIZE, MULCH ACRE 0.7 1500 1050 SILT FENCE LF 1200 5 6000 SAFETY FENCE LF 0 3 0 TEMPORARY FILL DIVERSION LF 0 3 0 DIVERSION DIKE LF 0 3 0 TEMPORARY SLOPE DRAIN LF 0 20 0 SEDIMENT TRAP 1 ACRES 0 1000 0 SEDIMENT BASIN 1 ACRES 0 1000 0 CULVERT INLET PROTECTION EA 0 500 0 INLET PROTECTION EA 0 200 0 OUTLET PROTECTION EA 0 200 0 UTILITY STREAM CROSSING EA 1 200 200 EC -2 & 3 DITCH PROTECTION LF 0 10 0 RIP -RAP LF 130 55 7150 CHECK DAMS SQ.YD. 14 30 420 PAVED CONSTRUCTION ENTRANCE EA 0 2000 0 subtotal 14820.00 project management 2223.00 subtotal 17043.00 CONTINGENCY LS 10% 1704.30 TOTAL 18747.30 BOND AMOUNT REQUIRED 18800.00