HomeMy WebLinkAboutARB201100020 Review Comments Final Site Plan and Comps. 2011-11-11Phone (434) 296 -5832 �'IRGI1`�ZP COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902 -4596 MEMORANDUM TO: Ron Lilley, Facilities Development FROM: Margaret Maliszewski, Principal Planner CC: John Reno, PHRA, 58 Kenmore St., Harrisonburg, VA 22801 Ellie Ray, Senior Planner RE: ARB- 2011 -20: Crozet Library Phase 2 DATE: November 11, 2011 Fax (434) 972 -4126 The ARB reviewed the Crozet Library Phase 2 project on April 4, 2011 and approved the proposal pending staff administrative approval of several conditions. The conditions of approval are listed below by number. Staff review comments based on the recent site plan resubmittal follow each condition. 1. Reposition the trees near the dumpster to avoid the utilities. Staff response: The trees at the north corners of the dumpster have been deleted. The loss of these trees is not expected to have a significant impact on the Entrance Corridor. No further comments. 2. Provide a complete landscape schedule for Phase 2 planting. Ensure that Phase 2 trees have a minimum planting size of 2112' caliper. Staff response: These items have been provided. No further comments. 3. Show all of the four Phase 1 trees located on the north side of the parking lot on the Phase 2 plan. Staff response: The perimeter parking lot trees required on the north side of the parking lot are shown on the plan, as Phase 1 trees. No further comments. 4. Include this note on the Phase 2 landscape plan: All site plantings of trees and shrubs shall be allowed to reach, and be maintained at, mature height; the topping of trees is prohibited. Shrubs and trees shall be pruned minimally and only to support the overall health of the plant. Staff response: The note has been added. No further comments. 5. Provide a complete lighting/photometric plan as part of the site plan. Include all exterior lighting, both site lights and wall lights. Staff response: A photometric plan has been provided but it is not complete. It does not include a luminaire schedule and cut sheets for all proposed fixtures were not included in the site plan. Revise the site plan to include a luminaire schedule that includes all proposed design features for all exterior lighting — both site and wall lights. Include manufacturer's cut sheets for each fixture in the site plan. Ensure that the cut sheets show that each fixture that emits 3000 lumens or more is a full cutoff fixture. Resubmittal required. 6. Coordinate all drawings to clearly distinguish Phase 1 and Phase 2 work. Staff response: The notes regarding Phase 1 landscaping need clarification. Revise note 1 on the demolition plan C3.1 to read as follows: "Preserve trees and shrubs in this area if possible. If unable to protect during construction, replace with same species and size." Revise all other similar notes throughout the plan, as well (for example, on sheet C2.0). Add the Phase 1 landscape schedule to the landscape plan C7.1 (to facilitate replacement of plants in the event that demolition occurs) and add a note referring back to the demolition plan. Also, the numbered list of notes on the demolition plan C3.1 does not correspond to numbered notes on that plan. Revise the C3.1 note list to coordinate with the plan. Resubmittal required. 7. Add shrubs at the west end of the transformer pad to screen the equipment from the Entrance Corridor. Staff response: The site plan shows five abelia added west and south of the transformer. The applicant's response memo indicates that shrubs can't be added in this location and a white vinyl fence is proposed. A white vinyl fence is not shown on the plan and it is not expected to have an appropriate appearance for the EC. The shrubs are appropriate. Please clarify the transformer screening situation. If a fence is proposed, provide for review an alternate material /color that will blend with the surroundings, and ensure that the site plan includes the corresponding fence detail. Resubmittal required. 8. Add this note to the site and architectural plans: Mechanical equipment shall not be visible from the Entrance Corridor. Staff response: The note has been added to the site plan but the architectural plans were not submitted. Provide the architectural plans for review. Include this note on the architectural plans: "Mechanical equipment shall not be visible from the Entrance Corridor." Resubmittal required. 9. Provide planting at the west end of the south elevation. Staff response: Seven ilex crenata and one sophora Japonica have been added at the west end of the south elevation. The three mature oak trees currently located in this area are now proposed to be removed. Provide updated architectural elevations (line drawings) so that a determination can be made regarding the need for replacement trees. Also in this area, the retaining wall at the southwest corner of the library has been revised since the last ARB review. Indicate on the plan the material proposed for the retaining wall and include a retaining wall detail in the site plan. Provide a material/color sample for review. Resubmittal required. 10. Provide a material schedule on the architectural elevation drawings. Staff response: Architectural drawings were not submitted. Provide the architectural drawings listed in the ARB final SDP checklist for review. Provide a material schedule on the architectural elevation drawings. Resubmittal required. 11. Indicate if additional wall signs will be proposed for the building. If so, provide complete information for review (type, location, size, color, material, etc.). Staff response: The applicant has indicated that no wall signs will be visible from the Entrance Corridor. The applicant should be aware that approved sign permits are required before signs can be installed on the building. No further comments. 12. Confirm that no grading will be required after Phase 1 is completed, or provide a Phase 2 grading plan. Staff response: A grading plan was submitted. No further comments. 13. Submit all final ARB review documents. Staff response: The submittal failed to include all the items listed in the ARB final SDP checklist. Provide the following items for review. D. Lighting plan showing the following (drawn to the scale of l " =20' or larger, clearly legible and folded): ❑ Lighting schedule identifying all proposed light fixtures, poles and brackets. ❑ Manufacturer's cut sheets illustrating proposed lighting fixtures and information on illumination type, intensity, style, shielding, color, finish, and installation height. E. Appearance of the building(s) (architectural elevations, color perspective sketches, site sections): ❑ Dimensioned architectural elevations of the proposed building(s). Elevations must be drawn to the scale of 1/8 " =F -0 ". Include a building materials schedule and key on the elevation drawings. ❑ One set of all building materials / colors. ❑ A floor plan adequate to show exterior walls, windows and doors. Resubmittal required. 14. Window glass reflectance off the outside pane shall be limited to 7 %. Staff response: The applicant indicated in a memo that glass reflectance shall be 7 %. The information must appear on an approved drawing. Provide the glass specifications for review and include the glass spec, including the 7% reflectance off the outside pane, in the materials schedule. Resubmittal required. Please provide: 1. One full set of revised drawings addressing each of the above comments where resubmittal is required. Include updated ARB revision dates on each drawing. 2. A memo including detailed responses indicating how each condition has been satisfied. If changes other than those requested have been made, identify those changes in the memo also. Highlighting the changes in the drawing with "clouding" or by other means will facilitate review and approval. 3. The attached "Revised Application Submittal" form. This form must be returned with your revisions to ensure proper tracking and distribution. When staffs review of this information indicates that all conditions of approval have been met, a Certificate of Appropriateness may be issued. If you have any questions, please do not hesitate to contact me. of �L� ,.i UrAG1N1�F_ COUNTY OF ALBEMARLE Department of Community Development REVISED APPLICATION SUBMITTAL This form must be returned with your revisions to ensure proper tracking and distribution. County staff has indicated below what they think will be required as a resubmission of revisions. If you need to submit additional information please explain on this form for the benefit of the intake staff. All plans must be collated and folded to fit into legal size files, in order to be accepted for submittal. TO: Margaret Maliszewski DATE: PROJECT NAME: ARB201100020 Crozet Library Phase II Submittal Type Requiring Revisions ( ) indicates Submittal Code County Project Number # Co ies Erosion & Sediment Control Plan (E &S) # Copies Distribute To: Mitigation Plan (MP) 1 Margaret Maliszewski Waiver Request (WR) Stormwater Management Plan (SWMP) Road Plan (RP) Private Road Request, with private /public comparison (PRR) Private Road Request — Development Area (PRR -DA) Preliminary Site Plan (PSP) Final Site Plan (or amendment) (FSP) Final Plat (FP) Preliminary Plat (PP) Easement Plat (EP) Boundary Adjustment Plat (BAP) Rezoning Plan (REZ) Special Use Permit Concept Plan (SP -CP) Reduced Concept Plan (R -CP) Proffers (P) Bond Estimate Request (BER) Draft Groundwater Management Plan (D -GWMP) Final Groundwater Management Plan (F -GWMP) Aquifer Testing Work Plan (ATWP) Groundwater Assessment Report (GWAR) Architectural Review Board (ARB) ARB2011 -20 1 Other: Please explain (For staff use only) Submittal Code # Copies Distribute To: Submittal Code # Copies Distribute To: ARB 1 Margaret Maliszewski