HomeMy WebLinkAboutSDP201100057 Review Comments Final Site Plan and Comps. 2012-01-09Philip Custer
From: Philip Custer
Sent: Monday, January 09, 2012 5:40 PM
To: 'Tom Gallagher'; 'Herbert F. White III, P.E.'; 'rum berger@wwassociates. net';
' droundtree @johnsondevelopment.net'
Cc: Bill Fritz; Ana Kilmer
Subject: Engineering Approval of The Haven at Stonefield
Good Evening,
I have reviewed the latest submittal of the ESC and site plans for The Haven at Stonefield (WPO- 2011 -00070 and SDP -
2011- 00057), received 22 December 2011. Except for the SWM facility maintenance agreement being recorded and the
Filterra approval letter, all previous engineering comments have been addressed. The ESC plan is hereby approved.
(The SWM plan was approved in December.) Engineering offers no objection to the approval of the site plan.
Please provide 3 additional copies of the plan and an updated Filterra approval letter to me so I can pass the file off to
the WPO inspectors. If the site plan is ready for signature, more copies will also be needed for the planner.
The ESC and SWM bonds amounts have been calculated. The ESC bond amount is $56,800. The SWM bond amount is
$75,200. To post these bonds, please contact Ana Kilmer at (434)296 -5832 x3246.
Before a grading permit can be issued, the site plan must be signed, the three extra WPO copies of the plan and updated
Filterra letter must be provided to me, the SWM facility maintenance agreement must be recorded, the WPO bonds (ESC
and SWM) must be posted, and the first year permit and inspection fee must be paid.
Please let me know if you have any questions.
Thanks,
Phil
(434)296 -5832 x3072