HomeMy WebLinkAboutSUB201100063 Review Comments Bond Estimate 2012-02-03Old Trail Block 13B Subdivision Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer) Item Item No. Unit Unit Cost Cost Number installed % compete cost remaining Upland Drive 16 +31.06 to 18 +82.6 road length 251.6 ft 1 aggregate base 6.0 in d 251.6 ft L 25.0 ft W 116.5 cy $35.91 $4,183.35 0% $4,183.35 2 blotted or prime &double seal 0.0 ft L 0.0 ft W 0.0 sy $6.30 $0.00 0% $0.00 3 asphalt base 3.0 in d 251.6 ft L 20.0 ft W 70.5 tons $73.50 $5,178.55 0% $5,178.55 4 asphalt surface 1.5 in d 251.6 ft L 20.0 ft W 35.2 tons $81.90 $2,885.19 0% $2,885.19 6 curb CG -2 0.0 ft $8.40 $0.00 0% $0.00 7 curb CG -6 503.0 ft $13.83 $6,955.74 0% $6,955.74 8 sidewalk, asphalt 0.0 in d 0.0 ft L 0.0 ft W 0.0 tons $73.50 $0.00 0% $0.00 9 sidewalk, concrete 5' width (unit price is for 4' width so apply a factor) 503.0 ft $11.66 $7,328.08 0% $7,328.08 10 ramp CG -12 0 $315.00 $0.00 0% $0.00 11 street name sign 1 $65.00 $65.00 0% $65.00 12 traffic control sign 3 $49.35 $148.05 0% $148.05 13 Street Landscape 8 Each 8 $105.00 $840.00 0% $840.00 13 guardrail 0 ES @ $3700 0.0 ft $16.80 $0.00 0% $0.00 14 manhole or drop inlet 4 $1,365.00 $5,460.00 0% $5,460.00 16 pipe, rcp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 EC -1 $200 249.7 ft $23.10 $5,766.92 0% $5,766.92 17 pipe, rcp (15 to 48 ") 48.0 in d 0 ES -1,2 $250 0 EC-1 $200 0.0 ft $126.00 $0.00 0% $0.00 18 pipe, pvc (4 to 10 ") 8.0 in d 0.0 ft $6.30 $0.00 0% $0.00 19 pipe, cmp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 EC-1 $200 0.0 ft $23.10 $0.00 0% $0.00 20 pipe, cmp (54 to 72 ") 60.0 in d 0 ES -1,2 $250 0 EC-1 $200 0.0 ft $146.00 $0.00 0% $0.00 21 rip -rap, placed 0.0 ton $31.50 $0.00 0% $0.00 22 E &S fabric,EC -2,3 0 ft L O ft W 0.0 sy $10.50 $0.00 0% $0.00 23 clear and grub (for wooded sites) 0.0 ft L 0.0 ft W 0.0 acre $10,500.00 $0.00 0% $0.00 24 grading (per cy for cut or import only 178.0 cy f II 222.0 cy cut -44.0 cy bal $3.15 $699.30 0% $699.30 24 CBR tests (1 every 0.1 mi. per road) 251.6 ft L 0.503 inc of 500' 2 $157.50 $252.00 0% $252.00 25 as -built drawings (1k + price per 0.1 251.6 ft L 0.048 mi. 1 $1,050.00 $2,050.00 0% $2,050.00 26 survey and layout (price per 0.1 mi.) 251.6 ft L 0.048 mi. 1 $525.00 $1,525.00 0% $1,525.00 27 mobilization 1 $525.00 $525.00 0% $525.00 28 VDOT surety (1 lane) 251.6 ft L 0.048 mi. 2 Lanes $2,000.00 $1,906.29 0% $1,906.29 29 VDOT maintenance fee (1 In rd, 1 yr) 251.6 ft L 0.048 mi. 2 Lanes $150.00 $142.97 0% $142.97 30 VDOT admin. Cost recovery fee(1 lar 251.6 ft L 0.048 mi. 2 Lanes $100.00 $345.31 0% $345.31 subtotal $46,256.74 subtotal $46,256.74 Golf Drive 16 +25.35 to 19 +82.8 road length 357.5 ft 1 aggregate base 9.0 in d 357.5 ft L 37.0 ft W 367.4 cy $35.91 $13,194.43 0% $13,194.43 2 blotted or prime &double seal 0.0 ft L 0.0 ft W 0.0 sy $6.30 $0.00 0% $0.00 3 asphalt base 4.0 in d 357.5 ft L 32.0 ft W 213.5 tons $73.50 $15,695.68 0% $15,695.68 4 asphalt surface 1.5 in d 357.5 ft L 32.0 ft W 80.1 tons $81.90 $6,558.55 0% $6,558.55 6 curb CG -2 0.0 ft $8.40 $0.00 0% $0.00 7 curb CG -6 715.0 ft $13.83 $9,887.38 0% $9,887.38 8 sidewalk, asphalt 0.0 in d 0.0 ft L 0.0 ft W 0.0 tons $73.50 $0.00 0% $0.00 9 sidewalk, concrete 8' width (unit price is for 4' width so apply a factor) 715.0 ft $11.66 $16,666.65 0% $16,666.65 10 ramp CG -12 0 $315.00 $0.00 0% $0.00 11 street name sign 1 $65.00 $65.00 0% $65.00 12 traffic control sign 2 $49.35 $98.70 0% $98.70 13 Street Landscape 11 Each 11 $105.00 $1,155.00 0% $1,155.00 13 guardrail 0 ES @ $3700 0.0 ft $16.80 $0.00 0% $0.00 14 manhole or drop inlet 4 $1,365.00 $5,460.00 0% $5,460.00 16 pipe, rcp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 ECA $200 35.2 ft $23.10 $813.12 0% $813.12 17 pipe, rcp (15 to 48 ") 18.0 in d 0 ES -1,2 $250 0 ECA $200 141.8 ft $27.30 $3,870.59 0% $3,870.59 17A pipe, rcp (15 to 48 ") 24.0 in d 1 ES -1,2 $250 1 ECA $200 241.6 ft $39.90 $10,091.44 0% $10,091.44 18 pipe, pvc (4 to 10 ") 8.0 in d 0.0 ft $6.30 $0.00 0% $0.00 19 pipe, cmp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 ECA $200 0.0 ft $23.10 $0.00 0% $0.00 20 pipe, cmp (54 to 72 ") 60.0 in d 0 ES -1,2 $250 0 ECA $200 0.0 ft $146.00 $0.00 0% $0.00 21 rip -rap, placed 0.0 ton $31.50 $0.00 0% $0.00 22 E &S fabric,EC -2,3 536.25 ft L 4 ft W 0.0 sy $10.50 $0.00 0% $0.00 23 clear and grub (for wooded sites) 0.0 ft L 0.0 ft W 0.0 acre $10,500.00 $0.00 0% $0.00 24 grading (per cy for cut or import only 1551.0 cy fill 0.0 cy cut 1551.0 cy bal $3.15 $4,885.65 0% $4,885.65 24 CBR tests (1 every 0.1 mi. per road) 357.5 ft L 0.715 inc of 500' 2 $157.50 $283.50 0% $283.50 25 as -built drawings (1k + price per 0.1 357.5 ft L 0.068 mi. 1 $1,050.00 $2,050.00 0% $2,050.00 26 survey and layout (price per 0.1 mi.) 357.5 ft L 0.068 mi. 1 $525.00 $1,525.00 0% $1,525.00 27 mobilization 1 $525.00 $525.00 0% $525.00 28 VDOT surety (1 lane) 357.5 ft L 0.068 mi. 2 Lanes $2,000.00 $2,708.33 0% $2,708.33 29 VDOT maintenance fee (1 In rd, 1 yr) 357.5 ft L 0.068 mi. 2 Lanes $150.00 $203.13 0% $203.13 30 VDOT admin. Cost recovery fee(1 Iar 357.5 ft L 0.068 mi. 2 Lanes $100.00 $385.42 0% $385.42 subtotal $96,122.57 subtotal $96,122.57 Fielding Run Drive 10 +00.00 to 21 +10.0 road length 1110.0 ft 1 aggregate base 6.0 in d 1110.0 ft L 37.0 ft W 760.6 cy $35.91 $27,311.55 0% $27,311.55 2 blotted or prime &double seal 0.0 ft L 0.0 ft W 0.0 sy $6.30 $0.00 0% $0.00 3 asphalt base 3.0 in d 1110.0 ft L 26.0 ft W 404.0 tons $73.50 $29,696.94 0% $29,696.94 2/3/2012 Old Trail Block 13B Subdivision Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer) Item Item No. Unit Unit Cost Cost Number installed % compete cost remaining 4 asphalt surface 1.5 in d 1110.0 ft L 26.0 ft W 202.0 tons $81.90 $16,545.44 0% $16,545.44 6 curb CG -2 0.0 ft $8.40 $0.00 0% $0.00 7 curb CG -6 2220.0 ft $13.83 $30,699.27 0% $30,699.27 8 sidewalk, asphalt 0.0 in d 0.0 ft L 0.0 ft W tons $73.50 $0.00 0% $0.00 9 sidewalk, concrete 5' width (unit price is for 4' width so apply a factor) 2220.0 ft $11.66 $32,342.63 0% $32,342.63 10 ramp CG -12 10 $315.00 $3,150.00 0% $3,150.00 11 street name sign 2 $65.00 $130.00 0% $130.00 12 traffic control sign 4 $49.35 $197.40 0% $197.40 13 Street Landscape 10 Each 10 $105.00 $1,050.00 0% $1,050.00 13 guardrail 0 ES @ $3700 0.0 ft $16.80 $0.00 0% $0.00 14 manhole or drop inlet 10 $1,365.00 $13,650.00 0% $13,650.00 16 pipe, rcp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 EC -1 $200 348.7 ft $23.10 $8,054.74 0% $8,054.74 17 pipe, rcp (15 to 48 ") 18.0 in d 0 ES -1,2 $250 0 EC -1 $200 133.6 ft $27.30 $3,647.28 0% $3,647.28 18 pipe, pvc (4 to 10 ") 8.0 in d 0.0 ft $6.30 $0.00 0% $0.00 19 pipe, cmp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $23.10 $0.00 0% $0.00 20 pipe, cmp (54 to 72 ") 60.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $146.00 $0.00 0% $0.00 21 rip -rap, placed 0.0 ton $31.50 $0.00 0% $0.00 22 E &S fabric,EC -2,3 0 ft L O ft W 0.0 sy $10.50 $0.00 0% $0.00 23 clear and grub (for wooded sites) 0.0 ft L 0.0 ft W 0.0 acre $10,500.00 $0.00 0% $0.00 24 grading (per cy for cut or import only 611.0 cy fill 9828.0 cy cut - 9217.0 cy bal $3.15 $30,958.20 0% $30,958.20 24 CBR tests (1 every 0.1 mi. per road) 1110.0 ft L 2.22 Inc of 500' 3 $157.50 $519.75 0% $519.75 25 as -built drawings (1k + price per 0.1 1110.0ftL 0.21 mi. 3 $1,050.00 $4,150.00 0% $4,150.00 26 survey and layout (price per 0.1 mi.) 1110.0 ft L 0.21 mi. 3 $525.00 $2,575.00 0% $2,575.00 27 mobilization 1 $525.00 $525.00 0% $525.00 28 VDOT surety (1 lane) 1110.0 ft L 0.21 mi. 2 Lanes $2,000.00 $8,409.09 0% $8,409.09 29 VDOT maintenance fee (1 In rd, 1 yr) 1110.0 ft L 0.21 mi. 2 Lanes $150.00 $630.68 0% $630.68 30 VDOT admin. Cost recovery fee(1 lar 1110.0 ft L 0.21 mi. 2 Lanes $100.00 $670.45 0% $670.45 subtotal $214,913.42 subtotal $214,913.42 Penny Well Drive (Alley) 10 +10.00 to 12 +00.0 road length 190.0 ft 1 aggregate base 8.0 in d 190.0 ft L 22.0 ft W 103.2 cy $35.91 $3,706.27 0% $3,706.27 2 blotted or prime &double seal 0.0 ft L 0.0 ft W 0.0 sy $6.30 $0.00 0% $0.00 3 asphalt base 0.0 in d 190.0 ft L 0.0 ft W 0.0 tons $73.50 $0.00 0% $0.00 4 asphalt surface 1.5 in d 190.0 ft L 20.0 ft W 26.6 tons $81.90 $2,178.54 0% $2,178.54 6 curb CG -2 0.0 ft $8.40 $0.00 0% $0.00 7 curb CG -6 0.0 ft $13.83 $0.00 0% $0.00 8 sidewalk, asphalt 0.0 in d 0.0 ft L 0.0 ft W 0.0 tons $73.50 $0.00 0% $0.00 9 sidewalk, concrete 4' width 0.0 ft $11.66 $0.00 0% $0.00 10 ramp CG -12 0 $315.00 $0.00 0% $0.00 11 street name sign 1 $65.00 $65.00 0% $65.00 12 traffic control sign 1 $49.35 $49.35 0% $49.35 13 Street Landscape 0 Each 0 $105.00 $0.00 0% $0.00 13 guardrail 0 ES @ $3700 0.0 ft $16.80 $0.00 0% $0.00 14 manhole or drop inlet 2 $1,365.00 $2,730.00 0% $2,730.00 16 pipe, rcp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 EC -1 $200 138.7 ft $23.10 $3,203.97 0% $3,203.97 17 pipe, rcp (15 to 48 ") 48.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $126.00 $0.00 0% $0.00 18 pipe, pvc (4 to 10 ") 8.0 in d 0.0 ft $6.30 $0.00 0% $0.00 19 pipe, cmp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $23.10 $0.00 0% $0.00 20 pipe, cmp (54 to 72 ") 60.0 in d 0 ES -1,2 $250 0 EC -1 $200 0.0 ft $146.00 $0.00 0% $0.00 21 rip -rap, placed 0.0 ton $31.50 $0.00 0% $0.00 22 E &S fabric,EC -2,3 0 ft L O ft W 0.0 sy $10.50 $0.00 0% $0.00 23 clear and grub (for wooded sites) 0.0 ft L 0.0 ft W 0.0 acre $10,500.00 $0.00 0% $0.00 24 grading (per cy for cut or import only 0.0 cy fill 844.0 cy cut -844.0 cy bal $3.15 $2,658.60 0% $2,658.60 24 CBR tests (1 every 0.1 mi. per road) 190.0 ft L 0.38 Inc of 500' 1 $157.50 $220.50 0% $220.50 25 as -built drawings (1k + price per 0.1 190.0 ft L 0.036 mi. 1 $1,050.00 $2,050.00 0% $2,050.00 26 survey and layout (price per 0.1 mi.) 190.0 ft L 0.036 mi. 1 $525.00 $1,525.00 0% $1,525.00 27 mobilization 1 $525.00 $525.00 0% $525.00 28 VDOT surety (1 lane) 190.0 ft L 0.036 mi. 0 Lanes $2,000.00 $0.00 0% $0.00 29 VDOT maintenance fee (1 In rd, 1 yr) 190.0 ft L 0.036 mi. 0 Lanes $150.00 $0.00 0% $0.00 30 VDOT admin. Cost recovery fee(1 lar 190.0 ft L 0.036 mi. 0 Lanes $100.00 $0.00 0% $0.00 subtotal $18,912.23 subtotal $18,912.23 Penny Well Lane (Alley) 15 +36.43 to 17 +65.1 road length 228.7 ft 1 aggregate base 6.0 in d 228.7 ft L 25.0 ft W 105.9 cy $35.91 $3,802.47 0% $3,802.47 2 blotted or prime &double seal 0.0 ft L 0.0 ft W 0.0 sy $6.30 $0.00 0% $0.00 3 asphalt base 3.0 in d 228.7 ft L 20.0 ft W 64.0 tons $73.50 $4,707.06 0% $4,707.06 4 asphalt surface 1.5 in d 228.7 ft L 20.0 ft W 32.0 tons $81.90 $2,622.50 0% $2,622.50 6 curb CG -2 0.0 ft $8.40 $0.00 0% $0.00 7 curb CG -6 457.0 ft $13.83 $6,319.62 0% $6,319.62 8 sidewalk, asphalt 0.0 in d 0.0 ft L 0.0 ft W 0.0 tons $73.50 $0.00 0% $0.00 9 sidewalk, concrete 4' width 0.0 ft $11.66 $0.00 0% $0.00 2/3/2012 Old Trail Block 13B Subdivision Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer) Item Item $62,062.22 contingency No. Unit Unit Cost Number cost remaining $0.00 0% installed 10 ramp CG -12 $65.00 $49.35 0 $315.00 11 street name sign $0.00 $0.00 1 $65.00 12 traffic control sign $5,460.00 $4,353.43 1 $49.35 13 Street Landscape 0 Each $0.00 0 $105.00 13 guardrail 0 ES @ $3700 $0.00 0.0 ft $16.80 14 manhole or drop inlet $0.00 $0.00 4 $1,365.00 16 pipe, rcp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 EC -1 $200 188.5 ft $23.10 17 pipe, rcp (15 to 48 ") 48.0 in d 0 ES -1,2 $250 0 EC-1 $200 0.0 ft $126.00 18 pipe, pvc (4 to 10 ") 8.0 in d $1,525.00 $525.00 0.0 ft $6.30 19 pipe, cmp (15 to 48 ") 15.0 in d 0 ES -1,2 $250 0 EC-1 $200 0.0 ft $23.10 20 pipe, cmp (54 to 72 ") 60.0 in d 0 ES -1,2 $250 0 EC-1 $200 0.0 ft $146.00 21 rip -rap, placed 0.0 ton $31.50 22 E &S fabric,EC -2,3 0 ft L o ft w 0.0 sy $10.50 23 clear and grub (for wooded sites) 0.0 ft L 0.0 ft w 0.0 acre $10,500.00 24 grading (per cy for cut or import only 0.0 cy f II 1850.0 cy cut - 1850.0 cy bal $3.15 24 CBR tests (1 every 0.1 mi. per road) 228.7 ft L 0.457 inc of 500' 2 $157.50 25 as -built drawings (1k + price per 0.1 228.7 ft L 0.043 mi. 1 $1,050.00 26 survey and layout (price per 0.1 mi.) 228.7 ft L 0.043 mi. 1 $525.00 27 mobilization 1 $525.00 28 VDOT surety (1 lane) 228.7 ft L 0.043 mi. 0 Lanes $2,000.00 29 VDOT maintenance fee (1 In rd, 1 yr) 228.7 ft L 0.043 mi. 0 Lanes $150.00 30 VDOT admin. Cost recovery fee(1 lai 228.7 ft L 0.043 mi. 0 Lanes $100.00 subtotal Cost proj mgmt $62,062.22 contingency % compete Total $523,400 cost remaining $0.00 0% $0.00 $65.00 0% $65.00 $49.35 0% $49.35 $0.00 0% $0.00 $0.00 0% $0.00 $5,460.00 0% $5,460.00 $4,353.43 0% $4,353.43 $0.00 0% $0.00 $0.00 0% $0.00 $0.00 0% $0.00 $0.00 0% $0.00 $0.00 0% $0.00 $0.00 0% $0.00 $0.00 0% $0.00 $5,827.50 0% $5,827.50 $236.25 0% $236.25 $2,050.00 0% $2,050.00 $1,525.00 0% $1,525.00 $525.00 0% $525.00 $0.00 0% $0.00 $0.00 0% $0.00 $0.00 0% $0.00 $37,543.18 subtotal $37,543.18 cost sum $413,748.13 proj mgmt $62,062.22 contingency $47,581.04 Total $523,400 $413,748.13 $62,062.22 $47,581.04 $523,400 2/3/2012