HomeMy WebLinkAboutSDP201200003 Review Comments Major Amendment, Final Site Plan 2012-04-05Philip Custer
From:
Philip Custer
Sent:
Thursday, April 05, 2012 6:01 PM
To:
Ali Daughtry
Cc:
Megan Yaniglos
Subject:
Engineering review of SDP - 2012 -00003
on
I have reviewed the latest submittal of the site plan for the Kroger Fuel Center at Rio Hill (SDP- 2012 - 00003), received 30
March 2012. All technical engineering site plan comments from the last review have been addressed. Once I approve
the ESC plan, I will have no objection to the approval of this site plan. I have begun the review of the ESC plan, but I
noticed that no fee was provided with the resubmittal. Each review of an ESC plan requires a fee. In your case, because
the disturbed area is under 1 acre, the fee is $150.
Also, I'm tipping my hand a little bit on the ESC review, but the drainage area to the inlet sediment trap is close to an
acre (during the first few weeks before the trench drains are installed) and to allow an undersized trap (67 cy /acre) as I
mentioned in my last comment letter, we'll need to process a variation. This will require another fee of $150 and a brief
letter outlining the request. Otherwise, you'll need to almost double the trap in a later submittal and this design likely
be more of an issue to the contractor.
Please let me know if you have any questions.
Thanks,
Phil
296 -5832 x3072