HomeMy WebLinkAboutSDP201200003 Review Comments Major Amendment, Final Site Plan 2012-04-05Philip Custer From: Philip Custer Sent: Thursday, April 05, 2012 6:01 PM To: Ali Daughtry Cc: Megan Yaniglos Subject: Engineering review of SDP - 2012 -00003 on I have reviewed the latest submittal of the site plan for the Kroger Fuel Center at Rio Hill (SDP- 2012 - 00003), received 30 March 2012. All technical engineering site plan comments from the last review have been addressed. Once I approve the ESC plan, I will have no objection to the approval of this site plan. I have begun the review of the ESC plan, but I noticed that no fee was provided with the resubmittal. Each review of an ESC plan requires a fee. In your case, because the disturbed area is under 1 acre, the fee is $150. Also, I'm tipping my hand a little bit on the ESC review, but the drainage area to the inlet sediment trap is close to an acre (during the first few weeks before the trench drains are installed) and to allow an undersized trap (67 cy /acre) as I mentioned in my last comment letter, we'll need to process a variation. This will require another fee of $150 and a brief letter outlining the request. Otherwise, you'll need to almost double the trap in a later submittal and this design likely be more of an issue to the contractor. Please let me know if you have any questions. Thanks, Phil 296 -5832 x3072