5/24/2012 BOND ESTIMATE - EROSION CONTROL Spreadsheet last revised:12 -5 -01 PROJECT NAME: Buck Mountain Compensatory Stream Mitigation Plan PROJECT NUMBER: WP02012 -00022 DATE OF ESTIMATE: 05/23/12 ESTIMATE BY: MAK BASED ON: plans submitted 4/17/2012 approved 5/9/2012 ITEM DESCRIPTION UNIT QUANTITY UNIT COST ITEM TOTAL SEED, FERTILIZE, MULCH ACRE 3.45 1500 5176.89 SILT FENCE LF 2448 5 12240 AGG. STONE CONSTRUCTION ROAC CYD 125 35.91 4488.75 RIP -RAP COFFERDAMS TON 327 58.87 19250.49 PAVED CONSTRUCTION ENTRANCE EA 1 2000 2000 subtotal 43156.13 project management 6473.42 subtotal 49629.55 CONTINGENCY LS 10% 4962.96 TOTAL 54592.51 BOND AMOUNT REQUIRED 54600.00 \\ Cob- dts01 \CityViewLnk \Docs \2012 \WPO \WPO201200022 - Buck Mountain Compensatory Stream Mitigation Plan \E1_ESC_MAK_ BE WP0201200022.xis