Megan,
I have reviewed the subject minor amendment and have the following comments:
1. The entrance shown on Golf Drive to phase one of the development needs to meet the minimum VDOT
standards and include 25 foot effective radii.
2. Remove the bump out directly across from the entrance to allow for the effective radius.
3. This amendment needs to also show the two entrances along Claremont Lane to the site meeting the minimum
standards. Please see the below e-mail for information on the two entrances that will need to have 25 foot
effective radii and a minimum 24 foot entrance width.
4. The alignment shift does not meet the minimum standard radii for a 25 mph design. However, this alignment
change does meet the minimum alignment shift requirement for a 3 foot offset of the centerline of the road. I
recommend that the reverse curve be omitted from the plan and replaced with an alignment shift. This will not
require any changes to the construction of the road.
Joel DeNunzio, P.E.
VDOT Culpeper
Land Development
434 - 589 -5871
joel.denunzio @vdot.virginia.gov
From: Kirsten Munz [ mailto: kirsten (d)collins- engineering.com]
Sent: Thursday, February 02, 2012 12:52 PM
To: DeNunzio, Joel D., P.E.
Subject: FW: SUB2012 -003 Old Trail Block 2- Prelim Subdivision
Joel,
Thanks for your feedback. Please see the attached exhibit — red linework are the changes to address your comment. Is
this acceptable for this entrance (block 2, phase 2)? We're resubmitting on Monday.
Thanks.
Kirsten
(434)566 -3013
From: DeNunzio, Joel D., P.E. [ mailto: Joel .DeNunzio(aVDOT.virginia.govl
Sent: Monday, January 30, 2012 4:26 PM
To: Kirsten Munz
Cc: Megan Yaniglos; Seale, Dennis L.
Subject: RE: SUB2012 -003 Old Trail Block 2- Prelim Subdivision
Kirsten,
I visited the site on Friday and this section of Claremont and Brookley Dr. have not started construction yet. Since they
have not started construction on any of these entrances, they should all be constructed to the current standard at this
time as these site plans come in for review. If we need to revisit the road plan to get the entrances corrected we can re-
review the plan or just correct the entrances with the site plans.
Thanks
Joel
Joel DeNunzio, P.E.
VDOT Culpeper
Land Development
434 - 589 -5871
Joel. den unzioCcbvdot.virainia.gov
From: Kirsten Munz [ mailto: krsten (acollins- engineering.com]
Sent: Thursday, January 26, 2012 2:39 PM
To: DeNunzio, Joel D., P.E.
Subject: FW: SUB2012 -003 Old Trail Block 2- Prelim Subdivision
Joel,
We received the attached comments on the preliminary plat for block 2, phase 2. This entrance was built with
Claremont Lane, per the approved road plans (sheet S -2 is attached) which showed a 20' entrance and 15' curb radii.
We understand that the requirements have changed within the last year, but this entrance now exists based on the old
requirements. Please let us know if this will be a problem.
Thank you
Kirsten Munz
Collins Engineering
(434)566 -3013
From: Megan Yaniglos [ mailto :myaniglos'balbemarle.orgl
Sent: Tuesday, January 24, 2012 3:35 PM
To: Kirsten Munz
Subject: SUB2012 -003 Old Trail Block 2- Prelim Subdivision
Kirsten and Scott:
Attached are the comments for the above submittal for SRC this Thursday the 26th.
Let me know if you have questions.
Thanks.
Megan Yanlglos, ASL4
Senior Planner
Albemarle County Community Development Department
Planning Services
401 McIntire Road, North Wing
Charlottesville, Virginia 22902
ph: 434.296.5832 x. 3004
fax: 434.972.4126