SDP201200049 - Church of Our Savior Preliminary
Chris,
RWSA has reviewed the preliminary site plan for Church of Our Savior as prepared by Pohl Consulting LLC and dated
8/13/2012 and has the following comments for the engineer:
1. On all sheets, please adjust draw order so that RWSA waterline and easement are visible across the entire
disturbed area.
2. Label RWSA waterline as '30" RWSA DIP Waterline'.
3. When a final site plan is developed, please note that for all utility crossings with the existing RWSA waterline,
there must be at least 18" of vertical separation. Test pits may be required to confirm depth of existing facilities.
4. RWSA would like to discuss the possibility of widening the existing easement, since it is undersized for a 30"
waterline. RWSA is proposing an additional 10' on the east side of the waterline for a total of 30'.
Please let me know if you have any questions or concerns, or if you'd like additional information on any of the items
above.
Have a nice holiday weekend,
Vicki