HomeMy WebLinkAboutWPO201200086 Review Comments Erosion Control Plan 2012-12-18i"
,. `IRGINZP
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
Project: THE PRESERVE AT GLENMORE WP0201200086
Plan preparer: Collins Engineering Scott @collins - engineering.com
Owner or rep.: Sansovich Development LLC
Plan received date: 5 December 2012
Date of comments: 18 December 2012
Reviewer: Max Greene
The WPO Plans (WP0201200086) submitted 5 December 2012 has received Engineering Review
and meets Albemarle County minimum checklist items for engineering approval. A SWM
agreement will need to be recorded prior to final WPO plan approval.
The following link is for the SWM agreement procedure:
http: // www .albemarle.org /upload/images/ forms_ center / departments / Communiiy Development/f
orms/En ine�eringandWPOForms/Plan Review-
_StormwaterManagementBMP Facilities_ Maintenance_ AgreementProcedures.pdf
The following link is for the SWM agreement form:
http:// www .albemarle.org /upload/images/ forms_ center / departments /Community Development/f
orms/En ine�eringand WPO Forms/Plan Review -
Stormwater_ Management BMP Facilities _ Maintenance Agreement.pdf
The forms and instructions to request the Water Protection Ordinance Bond amount can be found
on the Community Development Department Web site at
http:// www.albemarle.org/upload/images /forms_ center / departments / Communiiy Development/f
orms/ bondsBond Estimate—Request Form .pdf
The forms and instructions to post the Water Protection Ordinance Bond can be found on the
Community Development Department Web site on
http://www.albemarle.oriz/deptforms.asp?department=bonds
The road bonds can be requested at this time with the bond request form.
You may contact Ana Kilmer (Albemarle County Department of Community Development) at
ext. 3246 for further information on bonding procedures and Maintenance Agreements.
Once the E &SC bond has been posted, you may contact the Department of Community
Engineering Review Comments
Page 2 of 2
Development to arrange a pre - construction meeting with a County Erosion & Sediment Control
Inspector. Should the County Inspector find the limits of disturbance increased or the need for
additional control measures required to protect the site, additional fees will be required.
[17- 204.G] An approved erosion and sediment control plan shall be void if the owner fails to obtain a grading,
building, or other permit for activities involving land disturbing activities within one (1) year after the date of the
approval.
File: E &SC Approval letter.doc