From: Christopher Perez
Sent: Wednesday, March 13, 2013 5:51 PM
To: 'Trey Steigman'
Cc: Michelle Roberge; Rebecca Ragsdale
Subject: RE: Haden Place Bond Estimate
T rey,
Michelle spoke correctly, while we received VDOT approval of the road plans this week, at this time we are awaiting Fire
and Rescue to finalize their review. Thus at this time the road plan is not approved. We hope to have something
definitive for you very soon, notably I'll be meeting with the Fire and Rescue Dept late tomorrow and hope to have
something finite by meetings end.
Aside from that, as you know we received County Attorney re- approval of the HOA /maintenance docs today, so that
item appears good to go.
Also, I have completed my review of the final subdivision plat which was submitted on March 5th... everything looks
good from my end, aside from the road bonds being posted which are contingent on the road plan being approved... etc.
However, per discussions with the Subdivision Agent it appears that the wording of note #20 on the plat is
inadequate for enforcement purposes and needs to be revised per the proffers and the code of development.
Revise note #20 to state: "Upon the request of Albemarle County, a fifty (50) foot wide portion of the
open space area shown as "Open Space B ", shall be dedicated to public use, as a necessary, for future
realignment of Killdeer Lane."
The above revision of note #20 can be reviewed via PDF through email, assure the plat to be approved has the revised
note.
Other than the above, I'll get back to you as soon I know the status of the road plan.
Christopher P. Perez I Senior Planner
Department of Community Development ICounty of Albemarle, Virginia
401 McIntire Road I Charlottesville, VA 22902
434.296.5832 ext. 3443
From: Trey Steigman [ mailto :tsteigman(aOmsc- rents.com]
Sent: Wednesday, March 13, 2013 5:19 PM
To: Michelle Roberge
Cc: Christopher Perez
Subject: RE: Haden Place Bond Estimate
Thanks Michelle — I will review this bond estimate and let you know if any questions, but please let me know in regards
to your comment that the road plan has not been approved? Engineering and VDOT have approved the Road Plan.
Who or what else needs to provide approval of these plans that hasn't done so since the submission on Tuesday,
February 26`" (i.e. two weeks ago)?
Thanks for your help!
Trey Steigman
Vice President, Development
Management Services Corporation
102 South 1st Street, Suite 301
P.O. Box 5306
Charlottesville, VA 22905
(P) 434/977 -4181 ext. 105
(M) 434/960 -2165
(F) 434/295 -8025
(E) tsteigman(amsc- rents.com
(W) www.msc - rents.com
J_�% T Management Seri ces Co -rporatian
NA FkbW Y Mn^moga . oe•axpmr and 6rokS
One of The Caton Companies www.catoncomr)anies.com
Licensed Virginia Real Estate Salesperson
PRIVILEGED, CONFIDENTIAL AND PROPRIETARY: This email communication and attachment files may contain legally
privileged, confidential and proprietary information for the sole use of the intended recipient. Any unauthorized review, copying,
distribution or other use is strictly prohibited.
If you are not the intended recipient, please notify the sender and delete the contents of this communication and any attachment
files from your system.
From: Michelle Roberge [ mailto :mroberge(abalbemarle.ora]
Sent: Wednesday, March 13, 2013 5:09 PM
To: Trey Steigman
Cc: Christopher Perez
Subject: Haden Place Bond Estimate
Hello Trey,
Here is the bond estimate. Please keep in mind that the road plan has not been approved. Also, please submit a
schedule of completion to Ana Kilmer once the road plan has been approved.
Thanks!
- Michelle Roberge
Michelle Roberge County E ngi neer