COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
Project: Crozet United Methodist Church
Plan preparer: Anhold Associates [danhold @hughes.net]
Owner or rep.: CUMC, c/o Michael Carmagnola [mjcarmagnola @gmail.com]
Plan received date: 19 Feb 2013
Date of comments: 11 Mar 2013
Reviewer: Glenn Brooks
Erosion Control Plan (WP0201300012)
1. Provide easements for off -site work on neighboring parcels.
2. The offsite work for a "temporary parking area" would appear to require grading which is not shown
on the plan. The entrance to this area smust be easily accessible, and out of the way of construction.
The proposed location passes over a channel and through the construction area.
3. Please provide a plan sheet showing the existing conditions and installation of erosion control
measures. The plan is indecipherable when all the construction items and finished improvements are
shown together.
4. The plan appears to rely solely on silt fence and inlet protection. Inlet protection cannot be installed
until stormsewer and inlets are in place, and the site is graded to drain to them. Before that happens,
silt traps are typically necessary on a project this size. Please ensure all stages of construction are
adequately protected.
5. Please provide a more convenient construction entrance with access to the parking and staging area.
The current construction entrance cannot be used when the stormsewer and parking lot are under
construction.
6. Please provide a downstream channel analysis meeting MS -19 requirements.
7. This project appears to require stormwater management per sections 17 -314 to 317 of the county code.
Please provide a stormwater management plan. The pre - development condition will be the record at
the last site plan approval, or as shown on the county aerial topography, which can be viewed at
http:H,- isweb. albemarle .ora /GISWeb/Welcome.aspx. This indicates that the pre - development condition
cannot assume all the gravel lots were in place. It appears there was a small lot to the west, and one to
the south, but the area to the north was overflow in the field. This appears to have gradually become a
parking lot without plans. It is also noted that a pro -rata share to the Lickinghole Basin, a county
regional facility, will be required prior to final approval. This amount will be computed by the county
based on final plans.
8. The stream on the west side of the site requires a buffer according to 17 -317. This will change the
plan layout. Please see the subsequent code sections on development allowed within the buffer. It is
not clear where this stream originates, as so much of it has been piped, but it appears to be flowing
strongly at the outlet from the parking area, and has received much restorative work downstream with
the Jarman's Gap road project.
9. It appears some additional protection measure is needed at the culverts under Jarman's Gap road.
Information is needed on the extent of the drainage area, and how the disturbed area draining to it is to
be treated.
Any approval will be conditioned upon site plan approval, which will be required before a bond can be
posted and a grading permit can be issued. Site plan changes may necessitate changes to the WPO plans.
File: E1_ rp,esc,swm,fsp_GEB_template.doc