TO: Ellie Carter Ray
FROM: Alexander J. Morrison, EIT, Civil Engineer
DATE: May 2, 2013
RE: Site Plan Technical Review for: SDP201200010- Contractor Yard (Final Touch Tree
Service) Final
TMP# 56 -86
The below checked items apply to
this site.
✓ 1. This site plan is within the Authority's jurisdictional area for:
✓
A. Water and sewer
B. Water only
C. Water only to existing structure
D. Limited service
✓
2.
An 6 inch water line is located approximately (ON PROPERTY) distant.
3.
Fire flow from, nearest public hydrant, located distant from this site plan, is
Gpm + at 20 psi residual.
✓
4.
A 8 inch sewer line is located approximately 190' distant.
5.
An Industrial Waste Ordinance survey form must be completed.
✓
6.
No improvements or obstructions shall be placed within existing or future
easements.
7.
and plans are currently under review.
8.
and plans have been received and approved.
9.
No plans are required.
10.
Final and plans are required for our review and approval prior to
granting tentative approval.
11.
Final site plan may /may not be signed.
12.
RWSA approval for water and /or sewer connections.
13.
City of Charlottesville approval for sewer.
✓
Comments:
• Show proposed sanitary sewer easement on Final Touch property and
label as "Sewer Easement Hereby Dedicated to ACSA."
• Sewer can be extended through easement on Mass Enterprise property at
applicant's expense. If this is done, construction plans need to be
submitted to the ACSA for construction review.
• Include coordination notes with ACSA inspector for any work being
completed in the vicinity of existing ACSA infrastructure.