HomeMy WebLinkAboutSUB200500086 Review Comments Bond Estimate 2013-02-25Fray's Mill Subdivision Update 02 -26 -2013 Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer) Plan # SUB200500086 Item Item No. Unit Unit Cost Cost Number installed % compete adjustment for infl; cost remaining X Lane 0 +00 to 9 +50 road length 950.0 ft aggregate base 6.0 in d 950.0 ft L 18.0 ft W 598.5 ton $35.00 $20,947.50 0% $20,947.50 blotted or prime &double seal 950.0 ft L 0.0 ft W 0.0 sy $10.00 $0.00 0% $0.00 asphalt base 0.0 in d 950.0 ft L 0.0 ft W 0.0 tons $100.00 $0.00 0% $0.00 asphalt surface 2.0 in d 950.0 ft L 18.0 ft W 209.5 tons $120.00 $25,137.00 0% $25,137.00 curb CG -2 0.0 ft $13.00 $0.00 0% $0.00 curb CG -6 0.0 ft $15.00 $0.00 0% $0.00 sidewalk, concrete (6) 0.0 ft $17.00 $0.00 0% $0.00 ramp CG -12 0 ft $350.00 $0.00 0% $0.00 street name sign 1 each $200.00 $200.00 0% $200.00 traffic control sign 2 each $200.00 $400.00 0% $400.00 Street Landscape 0 Each 0 each $150.00 $0.00 0% $0.00 guardrail 0 ES @ 3000 0.0 ft $17.00 $0.00 0% $0.00 drop inlet or grate 0 each $3,500.00 $0.00 0% $0.00 standard manhole frame top (not inlet) 0 each $500.00 $0.00 0% $0.00 manhole structure (per ft. rise) 0 ft $450.00 $0.00 0% $0.00 pipe, rep, cmp (15 to 48 ") 18.0 in d 2 ES -1,2 2 EC -1 58.0 ft $40.00 $4,320.00 0% $4,320.00 rip -rap, placed 1.0 ft d 5.0 ft L 150.0 ft W 56.3 ton $60.00 $3,375.00 0% $3,375.00 clear and grub (for wooded sites) 0.0 ft L 0.0 ft W 0.0 acre $24,000.00 $0.00 0% $0.00 grading (per cy for cut or import only) 0.0 cy fill 0.0 cy out 0.0 cy $13.00 $0.00 0% $0.00 as -built drawings (ik+ price per 0.1 mi.) 950.0 ft L 0.17992 mi. 2 Isum $2,000.00 $5,000.00 0% $5,000.00 survey and layout (price per 0.1 mi.) 950.0 ft L 0.17992 mi. 2 Isum $2,000.00 $5,000.00 0% $5,000.00 mobilization 1 Isum $500.00 $500.00 0% $500.00 materials testing 950.0 ft L 1.9 inc of 500' 3 each $200.00 $580.00 0% $580.00 compaction testing 950.0 ft L 1.9 inc of 500' 3 each $200.00 $580.00 0% $580.00 CBR tests (1 every 0.1 mi. per road) 950.0 ft L 1.9 inc of 500' 3 each $200.00 $580.00 0% $580.00 stone depth inspections 950.0 ft L 1.9 inc of 500' 3 each $200.00 $580.00 0% $580.00 pavement inspections 950.0 ft L 1.9 inc of 500' 3 each $200.00 $580.00 0% $580.00 pipe and drainage video inspections 100 ft $1.00 $100.00 0% $100.00 VDOT surety (1 lane) 950.0 ft L 0.17992 mi. 2 Lanes $2,000.00 $7,196.97 0% $7,196.97 VDOT maintenance fee (1 In rd, 1 yr) 950.0 ft L 0.17992 mi. 2 Lanes $150.00 $539.77 0% $539.77 VDOT admin. Cost recovery fee(1 lane) 950.0 ft L 0.17992 mi. 2 Lanes $100.00 $609.85 0% $609.85 $76,226.09 cost sum $76,226.09 proj mgmt $11,433.91 $11,433.91 contingency $8,766.00 $8,766.00 Total $96,430 $96,430 \\ Cob- dts01 \CityViewLnk \Docs \2005 Applications \2005 SUBS \SUB200500086 \02 -26 -2013 Fray's Mill Road Bond Update.xls 3/29/2013