HomeMy WebLinkAboutSDP201300009 Review Comments Major Amendment, Preliminary Plan 2013-06-10COMMONWEALTH of VIRGINIA
DEPARTMENT OF TRANSPORTATION
1601 Orange Road
Culpeper, Virginia 22701 -3819
Gregory A. Whirley
Commissioner of Highways
June 10, 2013
Ms. Ellie Carter Ray, PLA
Senior Planning
County of Albemarle
Community Development Department
401 McIntire Road
Charlottesville, VA
Re: SDP - 2013 -00009 Seminole Trail Fire Station
Dear Ms. Ray,
I reviewed the subject site plan dated February 1, 2013 and offer the following comments:
1. Approval of the AM -2 exception request for the spacing requirement between the two entrance
shown has been recommended. Please note that fonnal approval of the spacing exception is
given by the District Administrator.
2. Based on the Geotechnical Study dated September 12, 2012 as provided by Froehling &
Robertson, Inc., the entrance pavement design will be allowed.
3. Based on the Stormwater Calculations dated April 17, 2013 as provided by DJG, Inc., the storm
sewer system is found to be adequate.
4. Two complete sets of the 100% complete site plan need to be provided to this office so that the
inspector has the correct set of plans in the field.
If you need additional information concerning this project, please feel free to contact me.
Sincerely,
AA
Troy ustin, P.E.
Area Land Use Engineer
Culpeper District
VirginiaDOT.org