WPO Plan Review
Project: Lochlyn Hill Phase IA& 1B
Number: WP0201300045
Date: _07 -24 -2013
Reviewer: Max Greene
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
Phone: 434 - 296 -5832 ext. 3283
This is an abbreviated review comment notice. County engineering staff is available every Thursday
afternoon to discuss details of review. To schedule, please call your reviewer for an appointment.
Erosion & Sediment Control:
(Code Chapter 17, Article II)
Y N
Adequate
x Not Adequate
State standards followed, and Design Standards Manual notes and details
Adequate limits and perimeter measures out of work areas
All stages protected adequately
Adequate channels
MS -19 needs to be adequately addressed. Erosion and sediment control
Basins are not on County property. Per Erosion and Sediment Control Law,
Title 10.1, Chapter 5, Article 4 (10.1- 563.A) of Virginia State Code as
found in Chapter 8 page 13 of VESCH the County requests the project be
submitted to the Department of Conservation and Recreation for review and
approval rather than to each jurisdiction concerned.
http: / /www.dcr.vir ig nia.gov/ other / deq / stormwater _management /documents/
Stormwater Management:
(Code Chapter 17, Article III)
Y N
Adequate
x Not Adequate
Enough capture and treatment for on -site areas
Enough detention storage for on -site areas
Sealed hydrologic and hydraulic computations provided
Per Erosion and Sediment Control Law, Title 10. 1, Chapter 5, Article 4
(10.1- 563.A) of Virginia State Code as found in Chapter 8 page 13 of
VESCH the County requests the project be submitted to the Department of
Conservation and Recreation for review and approval rather than to each
jurisdiction concerned.
http: / /www.dcr.virginia.gov /other /deq /stonnwater management/documents
Mitigation:
(Code Chapter 17, Article III) Adequate
Not Adequate
Y N
F-7 I Buffers and disturbed areas adequately shown
Adequate plantings at 2:1, or other mitigation provided
N/A
This review attempts to encompass the larger compliance questions. County staff does not assume
responsibility for any calculation or plan details, and cannot cover the intricacies of every plan submitted.
Each plan and calculation must have a professional seal and signature to assume these responsibilities.
This plan is
Approved (please see attached Approval Fact Sheet)
g Not Approved