Loading...
HomeMy WebLinkAboutSUB201300058 Review Comments Bond Estimate 2013-08-26Dunlora Forest Subdivision Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer) Item Item No. Unit Unit Cost Cost Number installed % compete adjustment for inlle cost remaining Pebble Beach Court 4 road length 255.0 ft aggregate base 6.0 in of 255.0 ft L 40.0 ft W 357.0 ton $35.00 $12,495.00 0% $12,495.00 blotted or prime &double seal 255.0 ft L 40.0 ft W 1133.3 sy $0.00 $0.00 0% $0.00 asphalt base 2.5 in of 255.0 ft L 40.0 ft W 156.2 tons $100.00 $15,618.75 0% $15,618.75 asphalt surface 1.5 in of 255.0 ft L 40.0 ft W 93.7 tons $120.00 $11,245.50 0% $11,245.50 curb CG -2 0.0 ft $13.00 $0.00 0% $0.00 curb CG -6 500.0 ft $15.00 $7,500.00 0% $7,500.00 sidewalk, concrete (6) 0.0 ft $17.00 $0.00 0% $0.00 ramp CG -12 Oft $350.00 $0.00 0% $0.00 street name sign 1 $200.00 $200.00 0% $200.00 traffic control sign 2 $200.00 $400.00 0% $400.00 Street Landscape 0 Each 0 $150.00 $0.00 0% $0.00 guardrail 4 ES @ 1500 60.0 ft $17.00 $7,020.00 0% $7,020.00 drop inlet or grate 5 $3,500.00 $17,500.00 0% $17,500.00 standard manhole frame top (not inlet) 4 $500.00 $2,000.00 0% $2,000.00 manhole structure (per ft. rise) 24 $450.00 $10,800.00 0% $10,800.00 pipe, rcp, cmp (15 to 48 ") 15.0 in d 0 ES -1,2 0 EC -1 280.0 ft $35.00 $9,800.00 0% $9,800.00 rip -rap, placed 1.0 it d 20.0 ft L 10.0 ft W 0.0 ton $60.00 $0.00 0% $0.00 clear and grub (for wooded sites) 0.0 ft L 0.0 ft W 0.0 acre $24,000.00 $0.00 0% $0.00 grading (per cy for out or import only) 8000.0 cy fill 0.0 cy cut 8000.0 cy $13.00 $104,000.00 0% $104,000.00 as -built drawings (1k+ price per 0.1 mi.) 255.0 ft 0.0483 mi. 1 $2,000.00 $3,000.00 0% $3,000.00 survey and layout (price per 0.1 mi.) 255.0 ft L 0.0483 mi. 1 $2,000.00 $3,000.00 0% $3,000.00 mobilization 1 $500.00 $500.00 0% $500.00 materials testing 255.0 ft L 0.51 inc of 500' 2 $200.00 $320.00 0% $320.00 compaction testing 255.0 ft L 0.51 inc of 500' 2 $200.00 $320.00 0% $320.00 CBR tests (1 every 0.1 mi. per road) 255.0 ft L 0.51 inc of 500' 2 $200.00 $320.00 0% $320.00 stone depth inspections 255.0 ft L 0.51 inc of 500' 2 $200.00 $320.00 0% $320.00 pavement inspections 255.0 ft L 0.51 inc of 500' 2 $200.00 $320.00 0% $320.00 pipe and drainage video inspections 280 ft $1.00 $280.00 0% $280.00 VDOT surety (1 lane) 255.0 ft L 0.0483 mi. 0 Lanes $2,000.00 $0.00 0% $0.00 VDOT maintenance fee (1 In rd, 1 yr) 255.0 ft L 0.0483 mi. 0 Lanes $150.00 $0.00 0% $0.00 VDOT admin. Cost recovery fee(1 lane) 255.0 ft L 0.0483 mi. 0 Lanes $100.00 $250.00 0% $250.00 cost sum $207,209.25 $207,209.25 proj mgmt $31,081.39 $31,081.39 contingency $23,829.06 $23,829.06 Total $262,120 $262,120 8/26/2013 Dunlora Forest Subdivision Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer) Item Item No. Unit Unit Cost Cost Number installed % compete adjustment for inlle cost remaining Bethpage Court 4 road length 698.0 ft aggregate base 6.0 in of 698.0 ft L 20.0 ft W 488.6 ton $35.00 $17,101.00 0% $17,101.00 blotted or prime &double seal 698.0 ft L 20.0 ft W 1551.1 sy $0.00 $0.00 0% $0.00 asphalt base 2.5 in of 698.0 ft L 20.0 ft W 213.8 tons $100.00 $21,376.25 0% $21,376.25 asphalt surface 1.5 in of 698.0 ft L 20.0 ft W 128.3 tons $120.00 $15,390.90 0% $15,390.90 curb CG -2 0.0 ft $13.00 $0.00 0% $0.00 curb CG -6 1400.0 ft $15.00 $21,000.00 0% $21,000.00 sidewalk, concrete (6) 0.0 ft $17.00 $0.00 0% $0.00 ramp CG -12 Oft $350.00 $0.00 0% $0.00 street name sign 1 $200.00 $200.00 0% $200.00 traffic control sign 8 $200.00 $1,600.00 0% $1,600.00 Street Landscape 0 Each 3 $150.00 $450.00 0% $450.00 guardrail 2 ES @ 1500 280.0 ft $17.00 $7,760.00 0% $7,760.00 drop inlet or grate 14 $3,500.00 $49,000.00 0% $49,000.00 standard manhole frame top (not inlet) 2 $500.00 $1,000.00 0% $1,000.00 manhole structure (per ft. rise) 113 $450.00 $50,850.00 0% $50,850.00 pipe, mp, cmp (15 to 48 ") 15.0 in d 1 ES -1,2 1 EC -1 1470.0 ft $35.00 $52,450.00 0% $52,450.00 rip -rap, placed 1.0 it d 20.0 ft L 10.0 ft W 15.0 ton $60.00 $900.00 0% $900.00 clear and grub (for wooded sites) 0.0 ft L 0.0 ft W 0.0 acre $24,000.00 $0.00 0% $0.00 grading (per cy for out or import only) 1000.0 cy fill 740.0 cy cut 1246.7 cy $13.00 $25,826.67 0% $25,826.67 as -built drawings (1k+ price per 0.1 mi.) 698.0 ft 0.1322 mi. 2 $2,000.00 $5,000.00 0% $5,000.00 survey and layout (price per 0.1 mi.) 698.0 ft L 0.1322 mi. 2 $2,000.00 $5,000.00 0% $5,000.00 mobilization 1 $500.00 $500.00 0% $500.00 materials testing 698.0 ft L 1.396 inc of 500' 2 $200.00 $480.00 0% $480.00 compaction testing 698.0 ft L 1.396 inc of 500' 2 $200.00 $480.00 0% $480.00 CBR tests (1 every 0.1 mi. per road) 698.0 ft L 1.396 inc of 500' 2 $200.00 $480.00 0% $480.00 stone depth inspections 698.0 ft L 1.396 inc of 500' 2 $200.00 $480.00 0% $480.00 pavement inspections 698.0 ft L 1.396 inc of 500' 2 $200.00 $480.00 0% $480.00 pipe and drainage video inspections 1470 ft $1.00 $1,470.00 0% $1,470.00 VDOT surety (1 lane) 698.0 ft L 0.1322 mi. 0 Lanes $2,000.00 $0.00 0% $0.00 VDOT maintenance fee (1 In rd, 1 yr) 698.0 ft L 0.1322 mi. 0 Lanes $150.00 $0.00 0% $0.00 VDOT admin. Cost recovery fee(1 lane) 698.0 ft L 0.1322 mi. 0 Lanes $100.00 $250.00 0% $250.00 cost sum $279,524.82 $279,524.82 prof mgmt $41,928.72 $41,928.72 contingency $32,145.35 $32,145.35 Total $353,600 $353,600 8/26/2013