Subdivision Bond Inspection
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
Project: HTC Laurel Park Lane Phase 2
Number: WP0200500078
Date: 6 Jan 2014
Reviewer: Michelle Roberge Original Bond Amount: $56,470
Phone: (434) 296 -5832 Current Bond Amount: $96,680 (rz as mlaleot bond Girxaf )
Your bond inspection request has been processed. This list contains an update on the items
received and approved.
Received
Approved
Y
N
Y
N
N/A
r
p
Completed inspection request and fee
'M
❑
❑
0
❑
As -built plan, updated to current date, per As -built policy
❑
❑
Zr
❑
Copies of recorded plats for right -of -way, easements
❑
❑
❑
Z
VDOT approval AM -4.3, or partial completion via punchlist
❑
❑
❑
❑
X
Letter from P.E. certifying improvements are built to plan
❑
❑
❑
❑
21
Current certification form completed by owner /developer
❑
❑
❑
2T
❑
CBR test reports for each road
❑
,K
❑
❑
0
Stone depth and material inspection reports (or core tests)
❑
❑
❑
❑
0
Pavement depth and material inspection reports (or core tests)
❑
❑
❑
❑
RT
Compaction test reports for fill areas under road
❑
❑
❑
❑
Rr
Pipe trench inspection reports
❑
❑
❑
,H'
❑
Pipe interior inspections reports and video
❑
0(
❑
❑
Z
Concrete test reports for structural concrete, curbing, aprons, etc.
❑
❑
❑
❑
Z
Structural inspection reports for any bridges or box culverts
❑
❑
❑
Updated bond amount based on completed work: $96,680
Based on the new current pricing, the bond amount increased to $96,680. Unforetunately, this amount
cannot be reduced. Some items submitted for review are for the wrong phase. Please see below.
Please provide the following for the next inspection request:
a) Thews -built submitted is for Phase 1 and not Phase 2. Refer to As -built Road Plan policy for next submittal.
The plan was not to scale and missing info from the As -built Road Plan policy.
b) Recorded plat has been submitted, but I need correct as -built to compare easement locations.
c) CBR appears to be for Phase 1 and not Phase 2. Please submit CBR for Phase 2.
d) Pipe inspection video needs to be on a CD for our records. Also, the pipes for Phase 2 are not shown. Please
show pipes east of 2a.