Loading...
HomeMy WebLinkAboutSDP201300058 Review Comments Initial Site Plan 2013-12-19Maude Ginty Service Auth6rity TO: Ellie Ray FROM: Alexander J. Morrison, Civil Engineer DATE: 12/19/2013 RE: Site Plan Technical Review for: SDP201300058- Rolkin Road Retail Center TMP# 078000000075AO The below checked items apply to this site. ✓ 1. This site plan is within the Authority's jurisdictional area for: ✓ A. Water and sewer B. Water only C. Water only to existing structure D. Limited service ✓ 2. An 8 inch water line is located approximately on site distant. 3. Fire flow from, nearest public hydrant, located distant from this site plan, is Gpm + at 20 psi residual. ✓ 4. An 8 inch sewer line is located approximately 24' distant (4" stub -out on site). 5. An Industrial Waste Ordinance survey form must be completed. ✓ 6. No improvements or obstructions shall be placed within existing or future easements. 7. and plans are currently under review. 8. and plans have been received and approved. 9. No plans are required. ✓ 10. Final water plans are required for our review and approval prior to construction. 11. Final site plan may /may not be signed. 12. RWSA approval for water and /or sewer connections. 13. City of Charlottesville approval for sewer. ✓ Comments: • Submit 3 copies of the final site plan for an ACSA construction review and approval (specifically for water infrastructure). • The water main serving the proposed fire hydrant assembly must be a minimum diameter of 6 inches. • Provide the ACSA with fixture counts so the water meter can be sized. 168 Spotnap Road • Charlottesville • VA 22911 • Tel (434) 977 -4511 • Fax (434) 979 -0698 www.serviceauthority.org s COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902 -4596 Phone (434) 296 -5832 Fax (434) 972 -4126 MEMORANDUM TO: Ellie Ray FROM: Margaret Maliszewski RE: SDP - 2013 -58: Rolkin Road Retail Center DATE: December 16, 2013 At its meeting on December 16, 2013, the ARB took the following actions on the Rolkin Road Retail Center: ARB- 2013 -164 and SDP - 2013 -58: 1. The ARB forwarded the recommendations outlined in the staff report to the agent for the Site Review Committee, as follows: — Regarding requirements to satisfy the design guidelines as per § 18- 30.6.4(2), (3) and (5): o As per § 32.4.2.2(b)(3) and 30.6.4(c)(3) and EC Guidelines 35a, it is not clear that sufficient planting area is available along the north and west sides of the site to accommodate required trees and shrubs. Regarding recommendations on the plan as it relates to the guidelines: None. Regarding recommended conditions of initial plan approval: • A Certificate of Appropriateness is required prior to final site plan approval. The applicant shall submit an application for a Countywide Certificate of Appropriateness for a structure located behind a structure that fronts the EC. • Provide additional information to clarify the type and location of utilities existing and /or planned along Rolkin and Abbey Roads. Provide planting in these areas to meet EC requirements or alternate planting of comparable size and quantity. Options might include: Provide the largest tree species acceptable to the easement holders, along with documentation that the easement holders do not object to the planting. Or provide large shade trees, 2%2" caliper at planting, 40' on center, in planting areas free of easements along Rolkin and Abbey Roads. Or add three islands with trees along the Rolkin side and three along the Abbey Road side of the site to compensate for the perimeter trees. Coordinate the proposed planting with the retaining wall along Rolkin Road. Regarding conditions to be satisfied prior to issuance of a grading permit: None. 2. The ARB offered the following comments on the initial plan for the benefit of the applicant's next ARB submittal: 1. Coordinate the design of the drive -thru window with the overall architecture of the building. 2. Carefully consider the form, illumination and materials (including the type and amount of glass used) in the tower design. 3. The design of the building should be compatible with the existing buildings in the area. 4. Coordinate building materials with those used in existing buildings in the area. 5. Avoid a blank wall on the west elevation by incorporating sufficient design details. If blank areas are still anticipated after design details are included, revise the layout to include planting area along the wall. 6. Include information on the architectural plans and elevations to show that visibility of rooftop equipment will be eliminated. 7. Add the following note to the site and the architectural plans: "Visibility of all mechanical equipment from the Entrance Corridor shall be eliminated." 8. Provide additional information to clarify the type and location of utilities existing and/or planned along Rolkin and Abbey Roads. Provide planting in these areas to meet EC requirements or alternate planting of comparable size and quantity. Options might include: Provide the largest tree species acceptable to the easement holders, along with documentation that the easement holders do not object to the planting. Or provide large shade trees, 21/2" caliper at planting, 40' on center, in planting areas free of easements along Rolkin and Abbey Roads. Or add three islands with trees along the Rolkin side and three along the Abbey Road side of the site to compensate for the perimeter trees. Coordinate the proposed planting with the retaining wall along Rolkin Road. 9. Increase the size of interior parking lot trees to 21/2" caliper minimum at planting. Increase the size of shrubs to 24" high minimum at planting. Consider increasing the variety of proposed shrubs species to a minimum of four different species. 10. Add the following note to the landscape plan: "All site plantings of trees and shrubs shall be allowed to reach, and be maintained at, mature height; the topping of trees is prohibited. Shrubs and trees shall be pruned minimally and only to support the overall health of the plant." 11. Remove Lighting Note #2 from Sheet 2. Provide complete lighting information for review. Calculate photometrics using a light loss factor of 1.0 and note the light loss factor on the plan. 12. Add the following note to the site plan: "Each outdoor luminaire equipped with a lamp that emits 3,000 or more initial lumens shall be a full cutoff luminaire and shall be arranged or shielded to reflect light away from adjoining residential districts and away from adjacent roads. The spillover of lighting from luminaires onto public roads and property in residential or rural areas zoning districts shall not exceed one half footcandle." 13. Include a comprehensive sign proposal with the ARB site plan/building design application. � jRclti�� County of Albemarle Department of Community Development 401 McIntire Road, Charlottesville, VA, 22902 Phone 434 - 296 -5832 Memorandum To: Daniel Hines, P.E. (dhines(a)bohlereng.com) From: Ellie Ray, CLA, Senior Planner Division: Planning Date: December 13, 2013 Subject: SDP 201300058 Rolkin Road Retail Center - Initial Fax 434 - 972 -4126 The County of Albemarle Planning Division will recommend approval of the plan referenced above once the following comments have been satisfactorily addressed (The following comments are those that have been identified at this time. Additional comments or conditions may be added or eliminated based on further review.): [Each comment is preceded by the applicable reference, which is to the Subdivision /Zoning Ordinances unless otherwise specified.] 1. [32.5.2(a)] Provide the name of the property owner. 2. [32.5.2(a)] Reference the Zoning Map Amendment approved for this property with the associated application plan (ZMA199800020), as well as any proffers and applicable approved waivers. 3. [32.5.2(b)] Provide /clarify the maximum amount of impervious cover and the maximum amount of paved parking and vehicular circulation area; the numbers provided are presented in a different manner and the `interior parking' number doesn't match the number provided on the landscape plan. 4. [32.5.2(d)] Show the areas of the site where existing slopes are critical slopes. Additionally, it appears a critical slopes waiver will be required to develop the site as presented. 5. [32.5.2(1), 4.12.13(e), & 4.12.18(c)] The design of the loading space and dumpster pads creates awkward and potentially dangerous vehicular access through the site; the full length of both the loading space and the dumpster pads must be out of the travelway. Please revise or clarify the layout to demonstrate that safe circulation is provided. 6. [32.5.2(k)] Verify that all necessary easements for proposed water, sewer and drainage facilities have been shown on the plan. 7. [32.5.2(1)] Provide the location of any other existing or proposed utilities and utility easements including telephone, cable, electric and gas. 8. [32.5.2(m)] Show the distance to the centerline of the nearest existing street intersection from the proposed ingress and egress locations. 9. [32.5.2(n)] Dimension all walkways, fences (guardrail), walls, trash containers (pads), paved areas, travelways, entrances and loading areas. 10. [32.5.2(n) & 4.12.16(e)] All parking spaces that are next to a sidewalk that is less than 6' wide must have bumper blocks. 11. [32.5.2(n)] Provide the proposed paving material for all walks, parking lots and other paved areas. 12. [32.5.2(n)] Clarify if any outdoor lighting is proposed; lighting locations appear to be shown but no photometric plan or fixture information is provided. No lighting locations are approved until this information is provided. 13. [32.5.2(p) & ZMA Proffer] The landscape plan must be submitted to the Thomas Jefferson Foundation to make sure that the plan provides, to their satisfaction, screening of all buildings and parking areas visible from Monticello. 14. [32.5.2(p) & 32.7.9.4] The landscape notes provided appear to reference old Site Plan ordinance sections; please update with current references. 15. [32.5.2(p) & ZMA Proffer] The proffers for ZMA 1998 -00020 included a provision that street trees would be provide along both sides of Rolkin Road; all proffers must be satisfied, see next comment for additional information regarding street trees. 16. [32.5.2(p), 32.7.5.2(d) & 32.7.9.5(d)] Street trees are required along both Rolkin and Abbey Roads. The existence of utilities or utility easements does not preclude this requirement; see section 32.7.9.5(d) for location and spacing requirements. 17. [32.5.2(p) & 32.7.9.6(a)] As noted above, the `Area of Parking Lot' on the landscape plan does not match the `Interior Parking' number provided on Sheet 3; please clarify and verify that the required 5% interior landscaped area is provided. 18. [32.5.2(p), 32.7.9.7(a)3 & 32.7.9.7(a)5] Clarify if dumpster screening is provided; though perhaps not specifically required by the ordinance due to the adjacent private streets, this area should be screened from view of any public street and from Monticello. 19. [32.5.2(p)] Several of the proposed plantings appear to be within existing or proposed easements; please either move all landscaping outside of easements or provide proof of authorization from the easement holder. 20. [Comment] The Special Permit for the proposed drive -thru must be approved prior to Site Plan approval. 21. [Comment] ARB approval is required. 22. [Comment] If any off -site easements are required, they must be submitted for review and recorded prior to Site Plan approval. Please contact Ellie Ray in the Planning Division by using eray(d)albemarle.orp or 434 - 296 -5832 ext. 3432 for further information. COMMONWEALTH of VIRGINIA DEPARTMENT OF TRANSPORTATION 1601 Orange Road Culpeper, Virginia 22701 -3819 Gregory A. Whirley Commissioner of Highways December 12, 2013 Ms. Ellie Carter Ray Senior Planner County of Albemarle Department of Community Development 401 McIntire Road Charlottesville, VA 22902 Re: SDP2013 -00058 Rolkin Road Retail Center— Initial Site Plan Dear Ms. Ray: We have reviewed the initial site plan for Rolkin Road Retail Center located at the intersection of Rolkin Road and Abbey Road dated 10/28/13 as submitted by Bohler Engineering and offer the following comments: 1. The entrances for this site will access roads not in the State Highway System and will not be required by VDOT to be permitted with the State. 2. Ideally, the new entrance shown onto Abbey Road should be removed and the shared entrance on the property line with the adjacent parcel to the east would be utilized as access to Abbey Road. 3. The entrance onto Abbey Road does not appear to meet VDOT standards for throat length. 4. Detail for the proposed storm sewer connection to the existing structure located on Hickman Road needs to be provided for review. In addition, hydraulic calculations need to be provided so that the adequacy of the existing storm sewer can be verified. If you need additional information concerning this project, please feel free to contact me. Sincerely, Troy Austin, P.E. Area Land Use Engineer Culpeper District VirginiaDOT.org WE KEEP VIRGINIA MOVING *—&A County of Albemarle Department of Community Development Memorandum To: Ellie Ray, Current Development planning and zoning review From: Max Greene, Current Development engineering review Date: 8 January 2014 Subject: Rolkin Road Retail Center (SDP201300058) critical slope waiver request The critical slope waiver request has been reviewed. The engineering analysis of the request follows: Description of critical slope area and proposed disturbance: This is an infill lot for the Pantops Shopping Center. The adjacent site plans around the project show no critical slopes prior to 2001. Since that time critical slopes have been constructed, possibly with the construction of Hickman Road. Areas Acres Total site 1.67 acres approximately Critical slopes 0.25 ,of site Critical slopes disturbed 0.25 1 100% of critical slopes Exemptions to critical slopes waivers for driveways, roads and utilities without reasonable alternative locations: This disturbance is not exempt. Compliance with Zoning Ordinance 18 -4.2: "movement of soil and rock" Proper slope construction, control of drainage, and vegetative stabilization will prevent any movement of soil. "excessive stormwater runoff' Stormwater runoff will be reduced in this area, as the slopes will be eliminated. "siltation" Inspection and bonding by the County will ensure siltation control during construction. Proper stabilization and maintenance will ensure long term stability. "loss of aesthetic resource" This area is visible from the roads and houses in the neighborhood. Some of the slopes were created with the roads. "septic effluent" This neighborhood is serviced by public sewer. Based on the review above, there are no engineering concerns which prohibit the disturbance of the critical slopes as shown. file: EI_csw_GEB_teinplate.doc 168 Spotnap Road • Charlottesville • VA 22911 • Tel (434) 977-4511 • Fax (434) 979-0698 www.serviceauthority.org TO: Ellie Ray FROM: Alexander J. Morrison, Civil Engineer DATE: 12/19/2013 RE: Site Plan Technical Review for: The below checked items apply to this site.  Submit 3 copies of the final site plan for an ACSA construction review and approval (specifically for water infrastructure).  The water main serving the proposed fire hydrant assembly must be a minimum diameter of 6 inches.  Provide the ACSA with fixture counts so the water meter can be sized. SDP201300058- Rolkin Road Retail Center TMP# 078000000075A0  1. This site plan is within the Authority’s jurisdictional area for:  A. Water and sewer B. Water only C. Water only to existing structure D. Limited service  2. An 8 inch water line is located approximately (on site) distant. 3. Fire flow from, nearest public hydrant, located distant from this site plan, is Gpm + at 20 psi residual.  4. An 8 inch sewer line is located approximately 24’ distant (4” stub-out on site). 5. An Industrial Waste Ordinance survey form must be completed.  6. No improvements or obstructions shall be placed within existing or future easements. 7. and plans are currently under review. 8. and plans have been received and approved. 9. No plans are required.  10. Final water plans are required for our review and approval prior to construction. 11. Final site plan may/may not be signed. 12. RWSA approval for water and/or sewer connections. 13. City of Charlottesville approval for sewer.  Comments: COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 MEMORANDUM TO: Ellie Ray FROM: Margaret Maliszewski RE: SDP-2013-58: Rolkin Road Retail Center DATE: December 16, 2013 At its meeting on December 16, 2013, the ARB took the following actions on the Rolkin Road Retail Center: ARB-2013-164 and SDP-2013-58: 1. The ARB forwarded the recommendations outlined in the staff report to the agent for the Site Review Committee, as follows:  Regarding requirements to satisfy the design guidelines as per § 18-30.6.4(2), (3) and (5): o As per § 32.4.2.2(b)(3) and 30.6.4(c)(3) and EC Guidelines 35a, it is not clear that sufficient planting area is available along the north and west sides of the site to accommodate required trees and shrubs.  Regarding recommendations on the plan as it relates to the guidelines: None.  Regarding recommended conditions of initial plan approval: o A Certificate of Appropriateness is required prior to final site plan approval. The applicant shall submit an application for a Countywide Certificate of Appropriateness for a structure located behind a structure that fronts the EC. o Provide additional information to clarify the type and location of utilities existing and/or planned along Rolkin and Abbey Roads. Provide planting in these areas to meet EC requirements or alternate planting of comparable size and quantity. Options might include: Provide the largest tree species acceptable to the easement holders, along with documentation that the easement holders do not object to the planting. Or provide large shade trees, 2½” caliper at planting, 40’ on center, in planting areas free of easements along Rolkin and Abbey Roads. Or add three islands with trees along the Rolkin side and three along the Abbey Road side of the site to compensate for the perimeter trees. Coordinate the proposed planting with the retaining wall along Rolkin Road.  Regarding conditions to be satisfied prior to issuance of a grading permit: None. 2. The ARB offered the following comments on the initial plan for the benefit of the applicant’s next ARB submittal: 1. Coordinate the design of the drive-thru window with the overall architecture of the building. 2. Carefully consider the form, illumination and materials (including the type and amount of glass used) in the tower design. 3. The design of the building should be compatible with the existing buildings in the area. 4. Coordinate building materials with those used in existing buildings in the area. 5. Avoid a blank wall on the west elevation by incorporating sufficient design details. If blank areas are still anticipated after design details are included, revise the layout to include planting area along the wall. 6. Include information on the architectural plans and elevations to show that visibility of rooftop equipment will be eliminated. 7. Add the following note to the site and the architectural plans: “Visibility of all mechanical equipment from the Entrance Corridor shall be eliminated.” 8. Provide additional information to clarify the type and location of utilities existing and/or planned along Rolkin and Abbey Roads. Provide planting in these areas to meet EC requirements or alternate planting of comparable size and quantity. Options might include: Provide the largest tree species acceptable to the easement holders, along with documentation that the easement holders do not object to the planting. Or provide large shade trees, 2½” caliper at planting, 40’ on center, in planting areas free of easements along Rolkin and Abbey Roads. Or add three islands with trees along the Rolkin side and three along the Abbey Road side of the site to compensate for the perimeter trees. Coordinate the proposed planting with the retaining wall along Rolkin Road. 9. Increase the size of interior parking lot trees to 2½” caliper minimum at planting. Increase the size of shrubs to 24” high minimum at planting. Consider increasing the variety of proposed shrubs species to a minimum of four different species. 10. Add the following note to the landscape plan: “All site plantings of trees and shrubs shall be allowed to reach, and be maintained at, mature height; the topping of trees is prohibited. Shrubs and trees shall be pruned minimally and only to support the overall health of the plant.” 11. Remove Lighting Note #2 from Sheet 2. Provide complete lighting information for review. Calculate photometrics using a light loss factor of 1.0 and note the light loss factor on the plan. 12. Add the following note to the site plan: “Each outdoor luminaire equipped with a lamp that emits 3,000 or more initial lumens shall be a full cutoff luminaire and shall be arranged or shielded to reflect light away from adjoining residential districts and away from adjacent roads. The spillover of lighting from luminaires onto public roads and property in residential or rural areas zoning districts shall not exceed one half footcandle.” 13. Include a comprehensive sign proposal with the ARB site plan/building design application. 1 County of Albemarle Department of Community Development 401 McIntire Road, Charlottesville, VA, 22902 Phone 434-296-5832 Fax 434-972-4126 Memorandum To: Daniel Hines, P.E. (dhines@bohlereng.com) From: Ellie Ray, CLA, Senior Planner Division: Planning Date: December 13, 2013 Subject: SDP 201300058 Rolkin Road Retail Center - Initial The County of Albemarle Planning Division will recommend approval of the plan referenced above once the following comments have been satisfactorily addressed (The following comments are those that have been identified at this time. Additional comments or conditions may be added or eliminated based on further review.): [Each comment is preceded by the applicable reference, which is to the Subdivision/Zoning Ordinances unless otherwise specified.] 1. [32.5.2(a)] Provide the name of the property owner. 2. [32.5.2(a)] Reference the Zoning Map Amendment approved for this property with the associated application plan (ZMA199800020), as well as any proffers and applicable approved waivers. 3. [32.5.2(b)] Provide/clarify the maximum amount of impervious cover and the maximum amount of paved parking and vehicular circulation area; the numbers provided are presented in a different manner and the ‘interior parking’ number doesn’t match the number provided on the landscape plan. 4. [32.5.2(d)] Show the areas of the site where existing slopes are critical slopes. Additionally, it appears a critical slopes waiver will be required to develop the site as presented. 5. [32.5.2(i), 4.12.13(e), & 4.12.18(c)] The design of the loading space and dumpster pads creates awkward and potentially dangerous vehicular access through the site; the full length of both the loading space and the dumpster pads must be out of the travelway. Please revise or clarify the layout to demonstrate that safe circulation is provided. 6. [32.5.2(k)] Verify that all necessary easements for proposed water, sewer and drainage facilities have been shown on the plan. 7. [32.5.2(l)] Provide the location of any other existing or proposed utilities and utility easements including telephone, cable, electric and gas. 8. [32.5.2(m)] Show the distance to the centerline of the nearest existing street intersection from the proposed ingress and egress locations. 9. [32.5.2(n)] Dimension all walkways, fences (guardrail), walls, trash containers (pads), paved areas, travelways, entrances and loading areas. 10. [32.5.2(n) & 4.12.16(e)] All parking spaces that are next to a sidewalk that is less than 6’ wide must have bumper blocks. 11. [32.5.2(n)] Provide the proposed paving material for all walks, parking lots and other paved areas. 2 12. [32.5.2(n)] Clarify if any outdoor lighting is proposed; lighting locations appear to be shown but no photometric plan or fixture information is provided. No lighting locations are approved until this information is provided. 13. [32.5.2(p) & ZMA Proffer] The landscape plan must be submitted to the Thomas Jefferson Foundation to make sure that the plan provides, to their satisfaction, screening of all buildings and parking areas visible from Monticello. 14. [32.5.2(p) & 32.7.9.4] The landscape notes provided appear to reference old Site Plan ordinance sections; please update with current references. 15. [32.5.2(p) & ZMA Proffer] The proffers for ZMA 1998-00020 included a provision that street trees would be provide along both sides of Rolkin Road; all proffers must be satisfied, see next comment for additional information regarding street trees. 16. [32.5.2(p), 32.7.5.2(d) & 32.7.9.5(d)] Street trees are required along both Rolkin and Abbey Roads. The existence of utilities or utility easements does not preclude this requirement; see section 32.7.9.5(d) for location and spacing requirements. 17. [32.5.2(p) & 32.7.9.6(a)] As noted above, the ‘Area of Parking Lot’ on the landscape plan does not match the ‘Interior Parking’ number provided on Sheet 3; please clarify and verify that the required 5% interior landscaped area is provided. 18. [32.5.2(p), 32.7.9.7(a)3 & 32.7.9.7(a)5] Clarify if dumpster screening is provided; though perhaps not specifically required by the ordinance due to the adjacent private streets, this area should be screened from view of any public street and from Monticello. 19. [32.5.2(p)] Several of the proposed plantings appear to be within existing or proposed easements; please either move all landscaping outside of easements or provide proof of authorization from the easement holder. 20. [Comment] The Special Permit for the proposed drive-thru must be approved prior to Site Plan approval. 21. [Comment] ARB approval is required. 22. [Comment] If any off-site easements are required, they must be submitted for review and recorded prior to Site Plan approval. Please contact Ellie Ray in the Planning Division by using eray@albemarle.org or 434-296-5832 ext. 3432 for further information. COMMONWEALTH of VIRGINIA DEPARTMENT OF TRANSPORTATION 1601 Orange Road Culpeper, Virginia 22701 -3819 Gregory A. Whirley Commissioner of Highways December 12, 2013 Ms. Ellie Carter Ray Senior Planner County of Albemarle Department of Community Development 401 McIntire Road Charlottesville, VA 22902 Re: SDP2013 -00058 Rolkin Road Retail Center — Initial Site Plan Dear Ms. Ray: We have reviewed the initial site plan for Rolkin Road Retail Center located at the intersection of Rolkin Road and Abbey Road dated 10/28113 as submitted by Bohler Engineering and offer the following comments: 1. The entrances for this site will access roads not in the State Highway System and will not be required by VDOT to be permitted with the State. 2. Ideally, the new entrance shown onto Abbey Road should be removed and the shared entrance on the property line with the adjacent parcel to the east would be utilized as access to Abbey Road. 3. The entrance onto Abbey Road does not appear to meet VDOT standards for throat length. 4. Detail for the proposed storm sewer connection to the existing structure located on Hickman Road needs to be provided for review. In addition, hydraulic calculations need to be provided so that the adequacy of the existing storm sewer can be verified. If you need additional information concerning this project, please feel free to contact me. Sincerely, --�;)6,t, Troy Austin, P.E. Area Land Use Engineer Culpeper District VirginiaDOT.org WE KEEP VIRGINIA MOVING Project Name: Date Completed: Reviewer: Department/Division/Agency: Reviews Comments: Review Status: Review Comments Rolkin Road Retail Center - Initial Wednesday, December 04, 2013 Jay Schlothauer Inspections Initial Site Plan Based on plans dated October 28, 2013. No comments or conditions. No Objection Project Name: Date Completed: Reviewer: Department/Division/Agency: Reviews Comments: Review Status: Review Comments Rolkin Road Retail Center - Initial Tuesday, December 03, 2013 Robbie Gilmer Fire Rescue Initial Site Plan Based on plans dated 10/25/13 1. If the building will have a sprinkler system the FDC shall be located on the address side of the building and within 50 ft of a fire hydrant. Requested Changes Project Name: Date Completed: Reviewer: Department/Division/Agency: Reviews Comments: Review Status: Review Comments Rolkin Road Retail Center - Initial Monday, November 25, 2013 Andrew Slack E911 Initial Site Plan Approved. Approved Project Name: Date Completed: Reviewer: Department/Division/Agency: Reviews Comments: Review Status: Review Comments Rolkin Road Retail Center - Initial Friday, November 15, 2013 Max Greene Engineering Initial Site Plan `Double entrance is a traffic/safety concern and should be limited to only the entrance across from the access way to route 250. `Rolkin Road and Abbey Road intersection is a traffic/safety concern and may require a traffic study. `Dumpster location does not appear to allow for single unit truck maneuvering to empty containers as shown. Recommend moving dumpster location or angle for truck access. `Left turn lane from Rolkin into site may be warranted with a traffic study of the ultimate build-out design of shopping center. `Light pole in center of North-east parking should be moved back from curb 2' to avoid damage/impact with vehicles. `Retaining wall type, material, and construction are very important information prior to initial site plan approval. Cast in place concrete walls have vertical faces verses dry stack walls that step back with each subsequent course and require more site space and a larger finished product foot print and may narrow travel way below required width. `The following will be required prior to final site plan approval: `Erosion control plan. `Stormwater drainage profiles and computations proving system adequacy to existing SWM basin. Existing drainage system on Hickman Road are not connected on the plan, if they are connected in the field please make the plan match for drainage system adequacy verification and calculations `Top of proposed wall will require VDOT grade guardrail due to proximity to travel way. Requested Changes