HomeMy WebLinkAboutWPO201400029 Review Comments Erosion Control Plan 2014-07-29COMMONWEALTH of VIRGINIA DEPARTMENT OF ENVIRONMENTAL QUALITY VALLEY REGIONAL OFFICE David K. Paylor 4411 Early Road, P.O. Box 3000, Harrisonburg, Virginia 22801 Director Molly Joseph Ward (540) 574 -7800 Fax (540) 574 -7878 Amy Thatcher Owens Secretary of Natural Resources www.deq.virginia.gov Regional Director July 28, 2014 United Land Development SENT VIA E -MAIL c/o Ms. Nena Harrell, Vice President RECEIPT CONFIRMATION REQUESTED PO Box 5548 Charlottesville, VA 22905 Re: Virginia Water Protection (VWP) General Permit Authorization Number WP4 -08 -0835 Northtown Center, Albemarle County, Virginia Notice of Planned Change Approval Letter Dear Ms. Harrell: The Virginia Department of Environmental Quality (DEQ) has received your Notice of Planned Change request for the VWP General Permit Authorization Number WP4 -08 -0835. The authorization was issued on July 28, 2008 for the permanent impact of 0.02 acres Palustrine Emergent (PEM) wetlands, 0.081 acres Palustrine Forested (PFO) wetlands, 0.14 acres Palustrine Open Water (POW), and 433 linear feet of stream channel associated with an unnamed tributary to the South Fork Rivanna River. In the letter dated June 18, 2014, Scott Collins of Collins Engineering, on your behalf, requested additional permanent impacts to stream channel of 75 linear feet due to necessary maintenance of the existing retaining wall that suffered a partial failure. Total project impacts including the Notice of Planned Change are to 0.02 acres PEM wetlands, 0.081 acres PFO wetlands, 0.14 acres POW, and 508 linear feet of stream channel associated with an unnamed tributary to the South Fork Rivanna River. Compensation for the additional impacts will be provided through the purchase of 104 stream credits from the Willis River Mitigation Bank. In accordance with your request and pursuant to the VWP General Permit Regulation 9 VAC 25- 690 -80, DEQ approves the additional impacts for coverage under this authorization. The work authorized by this VWP general permit was also authorized under the Norfolk District, U.S. Army Corps of Engineers' (USACE) State Program General Permit (07- SPGP -01). The expiration date of the SPGP -01 authorization cannot be extended as this authorization was superseded and replaced by the Norfolk District, USACE's issuance of a modified State Program General Permit (12- SPGP -01). The work previously determined to satisfy the terms and conditions of 07- SPGP -01 is now authorized under 12- SPGP -01. You are required to adhere to all special conditions contained within the attached 12- SPGP -01 that are pertinent to your project. The 12- SPGP -01 authorization is effective as of the date of this letter and remains effective until May 31, 2017. United Land Group July 28, 2014 Page 2 of 2 Please note that this letter is an official component of the authorization and should be attached to the authorization in your files. If you have any questions, do not hesitate to contact Eric Millard at (540) 574 -7813 or eric.millard@deq.virginia.gov. Respectfully, B. Keith Fowler Deputy Regional Director Enclosures: Revised Cover Page, VWP General Permit Conditions, 12- SPGP -0 1 cc: Scott Collins, Collins Engineering — VIA EMAIL Vincent Pero, U.S. Army Corps of Engineers, Dumfries Field Office — VIA EMAIL COMMONWEALTH of VIRGINIA DEPARTMENT OF ENVIRONMENTAL QUALITY VWP General Permit No. WP4 VWP General Permit Authorization No. WP4 -08 -0835 Authorization Effective date: July 28, 2008 Notice of Planned Change date: July 28, 2014 Authorization Expiration date: July 27, 2015 VWP GENERAL PERMIT FOR IMPACTS FROM DEVELOPMENT AND CERTAIN MINING ACTIVITIES UNDER THE VIRGINIA WATER PROTECTION PERMIT AND THE VIRGINIA STATE WATER CONTROL LAW Based upon an examination of the information submitted by the applicant and in compliance with § 401 of the Clean Water Act as amended (33 USC 1341) and the State Water Control Law and regulations adopted pursuant thereto, the board has determined that there is a reasonable assurance that the activity authorized by this VWP general permit, if conducted in accordance with the conditions set forth herein, will protect instream beneficial uses and will not violate applicable water quality standards. The board finds that the effect of the impact, together with other existing or proposed impacts to wetlands, will not cause or contribute to a significant impairment of state waters or fish and wildlife resources. Subject to the provisions of the Clean Water Act, as amended, and pursuant to the State Water Control Law and regulations adopted pursuant to it, the permittee is authorized to permanently or temporarily impact up to two acres of nontidal wetlands or open water and up to 1,500 linear feet of nontidal stream bed. While this general permit authorized impacts up to two acres non tidal wetlands or open water and up to 1,500 linear feet of nontidal streambed, this coverage only authorizes impacts as presented in the Activity Description below. Permittee: Wendell Wood, United Land Development Address: PO Box 5548, Charlottesville, VA 22905 Activity Location: Route 29, north of Charlottesville Activity Description: The permittee proposes to build a commercial development known as Northtown Center, including necessary appurtenant features such as an entrance off of Route 29, parking, commercial structures, utilities and stormwater treatment facilities. The proposed project will impact approximately 0.02 acres Palustrine Emergent (PEM) wetlands, 0.081 acres Palustrine Forested (PFO) wetlands, 0.14 acres Palustrine Open Water (POW), and 508 linear feet of stream channel associated with an unnamed tributary to the South Fork Rivanna River. The stream compensation is based on the Unified Stream Methodology. The original 433 linear of stream impacts require 527 stream credits, and the additional 75 linear feet of stream impacts require 104 stream credits. The authorized impact areas are as denoted in the Joint Permit Application, dated April 2008, prepared by Williamsburg Environmental Group and received by DEQ on May 1, 2008, and the Notice of Planned Change (NOPC) request received on June 18, 2014. Authorization Note(s): • The permittee shall comply with the recommendations specified in the U.S. Fish and Wildlife Service's 7/21/08 email (copy enclosed). • Impacts will be compensated at the replacement to loss ratios of 1:1 for PEM wetlands (0.02 acres), 2:1 for PFO wetland impacts (0.16 acres), and 1:1 for POW impacts (0.14 acres), through the purchase of credits from the James River Mitigation Land Bank. The 527 stream compensation requirements will be achieved through the preservation of 577 stream compensation credits at the Central Meadows area. An additional 104 stream credits will be purchased at the Willis River Mitigation Bank due to the additional impacts associated with the NOPC. VWP General Permit No. WP4 -08 -0835 July 28, 2014 Page 2 of 2 The work authorized by this permit also satisfies the terms and conditions contained in the Norfolk District, U.S. Army Corps of Engineers' ( USACE) State Program General Permit (12- SPGP -01) and no additional authorization from the USACE is required. The permittee is responsible for following all special conditions contained within the 12- SPGP -01 (attached) that are pertinent to the project. The authorized activity shall be in accordance with this cover page, Part I - Special Conditions, Part 11— Compensation, Monitoring, and Reporting, and Part III - Conditions Applicable to All VWP General Permits, as set forth herein. Date: 7/28/2014 B. Keith Fowler, Deputy Regional Director VWP General Permit WP4 -08 -0835 Part I Page 1 of 16 PART I. SPECIAL CONDITIONS. A. Authorized activities. 1. This permit authorizes permanent or temporary impacts of up to two acres of nontidal wetlands or open water and up to 1,500 linear feet of nontidal stream bed according to the information provided in the approved and complete application. 2. Any changes to the authorized permanent impacts to surface waters associated with this project shall require either a notice of planned change in accordance with 9 VAC 25- 690 -80, or another VWP permit application. 3. Any changes to the authorized temporary impacts to surface waters associated with this project shall require written notification to DEQ and restoration to preexisting conditions in accordance with the conditions of this permit authorization. 4. Modification to compensation requirements may be approved at the request of the permittee when a decrease in the amount of authorized surface waters impacts occurs, provided that the adjusted compensation meets the initial authorization compensation goals. 5. The activities authorized for coverage under this VWP general permit must commence and be completed within seven years of the date of this authorization. B. Continuation of coverage. Reapplication for continuation of coverage under this VWP general permit or a new VWP permit may be necessary if any portion of the authorized activities or any VWP general permit requirement (including compensation) has not been completed within seven years of the date of authorization. Notwithstanding any other provision, a request for continuation of coverage under a VWP general permit in order to complete monitoring requirements shall not be considered a new application, and no application fee will be charged. The request for continuation of coverage must be made no less than 60 days prior to the expiration date of this VWP general permit authorization, at which time the board will determine if continuation of the VWP general permit authorization is necessary. C. Overall project conditions. 1. The activities authorized by this VWP general permit shall be executed in a manner so as to minimize adverse impacts on instream beneficial uses as defined in § 62.1 -10 (b) of the Code of Virginia. 2. No activity may substantially disrupt the movement of aquatic life indigenous to the water body, including those species which normally migrate through the area, unless the primary purpose of the activity is to impound water. Culverts placed in streams must be installed to maintain low flow conditions. The requirement to countersink does no apply to extensions or maintenance of existing culverts that are not countersunk, floodplain culverts being placed above ordinary high water, culverts being placed on bedrock, or culverts required to be placed on slopes 5.0% or greater. No activity may cause more than minimal adverse effect on navigation. Furthermore the activity must not impede the passage of normal or expected high flows and the structure or discharge must withstand expected high flows. 3. Wet or uncured concrete shall be prohibited from entry into flowing surface waters. Excess or waste concrete shall not be disposed of in flowing surface waters or washed into flowing surface waters. 4. All fill material shall be clean and free of contaminants in toxic concentrations or amounts in accordance with all applicable laws and regulations. 5. Erosion and sedimentation controls shall be designed in accordance with the Virginia Erosion and Sediment Control Handbook, Third Edition, 1992, or for mining activities covered by this general permit, the standards issued by the Virginia Department of Mines, Minerals and Energy that are effective as those in the Virginia Erosion and Sediment Control Handbook, Third Edition, 1992. These controls shall be placed prior to clearing and grading and maintained in good working order to minimize impacts to state waters. These controls shall remain in place until the area is stabilized and shall then be removed. VWP General Permit WP4 -08 -0835 Part I Page 2 of 16 6. Exposed slopes and streambanks shall be stabilized immediately upon completion of work in each permitted impact area. All denuded areas shall be properly stabilized in accordance with the Virginia Erosion and Sediment Control Handbook, Third Edition, 1992. 7. All construction, construction access (e.g., cofferdams, sheetpiling, and causeways) and demolition activities associated with this project shall be accomplished in a manner that minimizes construction or waste materials from entering surface waters to the maximum extent practicable, unless authorized by this VWP general permit. 8. No machinery may enter flowing waters, unless authorized by this VWP general permit. 9. Heavy equipment in temporarily- impacted wetland areas shall be placed on mats, geotextile fabric, or other suitable material to minimize soil disturbance to the maximum extent practicable. Equipment and materials shall be removed immediately upon completion of work. 10. All nonimpacted surface waters and compensatory mitigation areas within 50 feet of permitted activities and within the project or right -of -way limits shall be clearly flagged or marked for the life of the construction activity at that location to preclude unauthorized disturbances to these surface waters and compensatory mitigation areas during construction. The permittee shall notify contractors that no activities are to occur in these marked surface waters. 11. Temporary disturbances to surface waters during construction shall be avoided and minimized to the maximum extent practicable. All temporarily disturbed wetland areas shall be restored to preexisting conditions within 30 days of completing work at each respective temporary impact area, which shall include reestablishing preconstruction contours, and planting or seeding with appropriate wetland vegetation according to cover type (emergent, scrub /shrub, or forested). The permittee shall take all appropriate measures to promote and maintain revegetation of temporarily disturbed wetland areas with wetland vegetation through the second year post - disturbance. All temporarily impacted streams and streambanks shall be restored to their original contours within 30 days following the construction at that stream segment, and the banks seeded or planted with the same vegetation cover type originally present along the streamsbanks, including supplemental erosion control grasses if necessary, except for invasive species identified on DCR's Invasive Alien Plant Species of Virginia list. 12. Materials (including fill, construction debris, and excavated and woody materials) temporarily stockpiled in wetlands shall be placed on mats or geotextile fabric, immediately stabilized to prevent entry into state waters, managed such that leachate does not enter state waters, and completely removed within 30 days following completion of that construction activity. Disturbed areas shall be returned to original contours, restored within 30 days following removal of the stockpile, and restored with the same vegetation cover type originally present, including supplemental erosion control grasses if necessary, except for invasive species identified on DCR's Invasive Alien Plant Species of Virginia list. 13. Continuous flow of perennial springs shall be maintained by the installation of spring boxes, french drains, or other similar structures. 14. The permittee shall employ measures to prevent spills of fuels or lubricants into state waters. 15. The permittee shall conduct activities in accordance with the time -of -year restrictions recommended by the Virginia Department of Game and Inland Fisheries, the Virginia Marine Resources Commission, or other interested and affected agencies and shall ensure that all contractors are aware of the time -of -year restrictions imposed. 16. Water quality standards shall not be violated as a result of the construction activities, unless allowed by this permit authorization. 17. If stream channelization or relocation is required, all work in surface waters shall be done in the dry, unless authorized by this VWP general permit, and all flows shall be diverted around the channelization or relocation area until the new channel is stabilized. This work shall be accomplished by leaving a plug at the inlet and outlet ends of the new channel during excavation. Once the new channel has been stabilized, flow shall be routed into the new channel by first removing the downstream plug and then the upstream plug. The rerouted stream flow must be fully established before construction activities in the old stream channel can begin. VWP General Permit WP4 -08 -0835 Part I Page 3 of 16 D. Road crossings. 1. Access roads and associated bridges or culverts shall be constructed to minimize the adverse effects on surface waters to the maximum extent practicable. Access roads constructed above preconstruction contours and elevations in surface waters must be bridged or culverted to maintain surface flows. 2. Installation of road crossings shall occur in the dry via the implementation of cofferdams, sheetpiling, stream diversions, or similar structures. E. Utility, lines. 1. All utility line work in surface waters shall be performed in a manner that minimizes disturbance, and the area must be returned to its original contours and restored within 30 days of completing work in the area, unless otherwise authorized by this VWP general permit. Restoration shall be the seeding of planting of the same vegetation cover type originally present, including supplemental erosion control grasses if necessary, except for invasive specifies identified on DCR's Invasive Alien Plant Species of Virginia list. 2. Material resulting from trench excavation may be temporarily sidecast into wetlands not to exceed a total of 90 days, provided the material is not placed in a manner such that it is dispersed by currents or other forces. 3. The trench for a utility line cannot be constructed in a manner that drains wetlands (e.g., backfilling with extensive gravel layers creating a french drain effect.). For example, utility lines may be backfilled with clay blocks to ensure that the trench does not drain surface waters through which the utility line is installed. F. Stream modification and stream bank protection. 1. Riprap bank stabilization shall be of an appropriate size and design in accordance with the Virginia Erosion and Sediment Control Handbook, Third Edition, 1992. 2. Riprap apron for all outfalls shall be designed in accordance with the Virginia Erosion and Sediment Control Handbook, Third Edition, 1992. 3. For stream bank protection activities, the structure and backfill shall be placed as close to the stream bank as practicable. No material shall be placed in excess of the minimum necessary for erosion protection. 4. All stream bank protection structures shall be located to eliminate or minimize impacts to vegetated wetlands to the maximum extent practicable. 5. Asphalt and materials containing asphalt or other toxic substances shall not be used in the construction of submerged sills or breakwaters. 6. Redistribution of existing stream substrate for the purpose of erosion control is prohibited. 7. No material removed from the stream bottom shall be disposed of in surface waters, unless authorized by this permit. G. Dredging. 1. Dredging depths shall be determined and authorized according to the proposed use and controlling depths outside the area to be dredged. 2. Dredging shall be accomplished in a manner that minimizes disturbance of the bottom and minimizes turbidity levels in the water column. 3. If evidence of impaired water quality, such as a fish kill, is observed during the dredging, dredging operations shall cease and the DEQ shall be notified immediately. VWP General Permit WP4 -08 -0835 Part I Page 4 of 16 4. Barges used for the transportation of dredge material shall be filled in such a manner to prevent the overflow of dredged materials. 5. Double handling of dredged material in state waters shall not be permitted. 6. For navigation channels the following shall apply: a. A buffer of four times the depth of the dredge cut shall be maintained between the bottom edge of the design channel and the channelward limit of wetlands, or a buffer of 15 feet shall be maintained from the dredged cut and the channelward edge of wetlands, whichever is greater. This landward limit of buffer shall be flagged and inspected prior to construction. b. Side slope cuts of the dredging area shall not exceed a two - horizontal -to -one- vertical slope to prevent slumping of material into the dredged area. 7. A dredged material management plan for the designated upland disposal site shall be submitted and approved 30 days prior to initial dredging activity. 8. Pipeline outfalls and spillways shall be located at opposite ends of the dewatering area to allow for maximum retention and settling time. Filter fabric shall be used to line the dewatering area and to cover the outfall pipe to further reduce sedimentation to state waters. 9. The dredge material dewatering area shall be of adequate size to contain the dredge material and to allow for adequate dewatering and settling out of sediment prior to discharge back into state waters. 10. The dredge material dewatering area shall utilize an earthen berm or straw bales covered with filter fabric along the edge of the area to contain the dredged material, and shall be properly stabilized prior to placing the dredged material within the containment area. 11. Overtopping of the dredge material containment berms with dredge materials shall be strictly prohibited. H. Stormwater management facilities. 1. Stormwater management facilities shall be installed in accordance with best management practices and watershed protection techniques (e.g., vegetated buffers, siting considerations to minimize adverse effects to aquatic resources, bioengineering methods incorporated into the facility design to benefit water quality and minimize adverse effects to aquatic resources) that provide for long -term aquatic resources protection and enhancement, to the maximum extent practicable. 2. Compensation for unavoidable impacts shall not be allowed within maintenance areas of stormwater management facilities. 3. Maintenance activities within stormwater management facilities shall not require additional permit authorization or compensation, provided that the maintenance activities do not exceed the original contours of the facility, as approved and constructed, and is accomplished in designated maintenance areas as indicated in the facility maintenance or design plan. VWP General Permit WP4 -08 -0835 Part II Page 5 of 16 Part II. Construction and Compensation Requirements, Monitoring, and Reporting. A. Minimum compensation requirements. 1. The permittee shall provide appropriate and practicable compensation for all impacts meeting the conditions outlined in this VWP general permit. 2. Compensation options that may be considered under this VWP general permit shall meet the criteria in 9 VAC 25- 690 -70. 3. The site or sites depicted in the conceptual compensation plan submitted with the application shall constitute the compensation site for the approved project. A site change will require a modification to the authorization. 4. For compensation involving the purchase or use of mitigation bank credits or a contribution to an in -lieu fee fund, the permittee shall not initiate work in permitted impact areas until documentation of the mitigation bank credit purchase or usage or of the fund contribution has been submitted to and received by DEQ. 5. All aspects of the compensation plan shall be finalized, submitted, and approved by the board prior to a construction activity in permitted impact areas. The board shall review and provide written comments on the plan within 30 days of receipt or it shall be deemed approved. The final compensation plan as approved by the board shall be an enforceable requirement of this VWP general permit authorization. Deviations from the approved plan must be submitted and approved in advance by the board. 6. The final wetlands compensation plan shall include: a. The goals and objectives of the plan in terms of replacement of wetland acreage and functions, by wetland type; b. Location map, including latitude and longitude (to the nearest second) at the center of the site; c. Summary of the type and acreage of existing wetland impacts anticipated during the construction of the compensation site and proposed compensation for these impacts; d. Grading plan with existing and proposed elevations at one -foot or less contours; e. Schedule for compensation site construction, including sequence of events with estimated dates; f. Hydrologic analysis, including a water budget based on expected monthly inputs and outputs that will project water level elevations for a typical year, a wet year, and a dry year•, g. Groundwater elevation data for the site, or the location of groundwater monitoring wells to collect these data, and groundwater data for reference wetlands, if applicable; h. Design of water control structures; i. Planting scheme and schedule, indicating plant species, zonation, and acreage of each vegetation type proposed; j. An abatement and control plan covering all undesirable plant species, as listed on DCR's Invasive Alien Plant Species of Virginia list, that includes the proposed procedures for notifying DEQ of their presence, methods of removal, and the control of such species; k. Erosion and sedimentation control plan; 1. A soil preparation and amendments plan addressing both topsoil and subsoil conditions; m. A discussion of structures and features considered necessary for the success of the site; VWP General Permit WP4 -08 -0835 Part II Page 6 of 16 n. A monitoring plan, including success criteria, monitoring goals and methodologies, monitoring and reporting schedule, and the locations of photographic stations and monitoring wells, sampling points, and, if applicable, reference wetlands; o. Site access plan; p. The location and composition of any buffers; and q. The mechanism for protection of the compensation area(s). 7. The final stream compensation plan shall include: a. The goals and objectives of the compensation plan in terms of replacement of stream functions and water quality benefits; b. A location map, including latitude and longitude (to the nearest second) at the center of the site; c. An evaluation, discussion, and plan sketches of existing conditions on the proposed compensation stream, including the identification of functional and physical deficiencies for which the measures are proposed, and summary of geomorphologic measurements (e.g., stream width, entrenchment ratio, width - depth ratio, sinuosity, slope, substrate, etc.); d. The identification of existing geomorphological stream type being impacted and proposed geomorphological stream type for compensation purposes; e. Detailed design information for the proposed restorative measures, including geomorphological measurements and reference reach information as appropriate; f. Riparian buffer plantings, including planting scheme, species, buffer width; g. Livestock access limiting measures, to the greatest extent possible; h. A site access plan; i. An erosion and sedimentation control plan, if appropriate; j. An abatement and control plan covering all undesirable plant species, listed on DCR's Invasive Alien Plant Species of Virginia list, that includes the proposed procedures for notifying DEQ of their presence, methods for removal, and the control of such species; k. A schedule for compensation site construction including projected start date, sequence of events with projected dates, and projected completion date; 1. A monitoring plan, including a monitoring and reporting schedule; monitoring design and methodologies to evaluate the success of the proposed compensation measures, allowing comparison from year to year; proposed success criteria for appropriate compensation measures; location of all monitoring stations including photo stations, vegetation sampling points, survey points, bank pins, scour chains, and reference streams; m. The mechanism for protection of the compensation area; and n. Plan view sketch depicting the pattern and all compensation measures being employed, a profile sketch, and cross - section sketches of the proposed compensation stream. 8. For final wetland or stream compensation plans, the vegetation used shall be native species common to the area, shall be suitable for growth in local wetland or riparian conditions, and shall be from areas within the same or adjacent USDA Plant Hardiness Zone or NRCS Land Resource Region as that of the project site. VWP General Permit WP4 -08 -0835 Part II Page 7 of 16 9. The final wetland or stream compensation plan(s) shall include a mechanism for protection in perpetuity of the compensation sites(s) to include all state waters within the compensation site boundary or boundaries. Such protections shall be in place within 120 days of final compensation plan approval. The restrictions, protections, or preservations, or similar instrument, shall state that no activity will be performed on the property in any area designated as a compensation area with the exception of maintenance or corrective action measures authorized by the board. Unless specifically authorized by the board through the issuance of a VWP individual or general permit, or waiver thereof, this restriction applies to ditching, land clearing or the discharge of dredge or fill material. Such instrument shall contain the specific phrase "ditching, land clearing or discharge of dredge or fill material" in the limitations placed on the use of these areas. The protective instrument shall be recorded in the chain of title to the property, or an equivalent instrument for government -owned lands. Proof of recordation shall be submitted within 120 days of final compensation plan approval. 10. All work in impact areas shall cease if compensation site construction has not commenced within 180 days of commencement of project construction, unless otherwise authorized by the board. 11. DEQ shall be notified in writing at least 10 days prior to the initiation of construction activities at the compensation site(s). 12. Planting of woody plants shall occur when vegetation is normally dormant unless otherwise approved in the final wetlands or stream compensation plan(s). 13. Point sources of stormwater runoff shall be prohibited from entering a wetland compensation site prior to treatment by appropriate best management practices. Appropriate best management practices may include sediment traps, grassed waterways, vegetated filter strips, debris screens, oil and grease separators, or forebays. 14. The success of the compensation shall be based on meeting the success criteria established in the approved final compensation plan. 15. Wetland hydrology shall be considered established if depths to the seasonal high water table are equal to or less than 12 inches below ground surface for at least 12.5% of the region's killing frost -free growing season, as defined in the soil survey for the locality of the compensation site or the NRCS WETS table, measured in consecutive days under typical precipitation conditions, and as defined in the water budget of the final compensation plan. For the purpose of this regulation, the growing season is defined as the period in which temperatures are expected to be above 28 degrees Fahrenheit in five out of 10 years, or the period during which the soil temperature in a wetland compensation site is greater than biological zero (five degrees Celsius) at a depth of 50 centimeters (19.6 inches), if such data is available. 16. The wetland plant community shall be considered established according to the performance criteria specified in the final compensation plan and approved by the board. The proposed vegetation success criteria in the final compensation plan shall include the following: a. Species composition shall reflect the desired plant community types stated in the final wetland compensation plan by the end of the first growing season and shall be maintained through the last monitoring year. b. Species composition shall consist of greater than 50% facultative (FAC) or wetter (FACW or OBL) vegetation, as expressed by plant stem density or areal cover, by the end of the first growing season and shall be maintained through the last monitoring year. 17. Undesirable plant species shall be identified and controlled as described in the undesirable plant species control plan, such that they are not dominant species or do not change the desired community structure. The control plan shall include procedures to notify DEQ when undesirable plant species comprise greater than 5.0% of the vegetation by areal coverage on wetland or stream compensation sites. The notification shall include the methods of removal and control, and whether the methods are successful. 18. If the wetland or stream compensation area fails to meet the specified success criteria in a particular monitoring year, other than the final monitoring year, the reasons for this failure shall be determined, and a corrective action plan shall be submitted to DEQ for approval with or before that year's monitoring report. The corrective action plan VWP General Permit WP4 -08 -0835 Part II Page 8 of 16 shall contain at minimum the proposed actions, a schedule for those actions, and a monitoring plan, and shall be implemented by the permittee in accordance with the approved schedule. Should significant changes be necessary to ensure success, the required monitoring cycle shall begin again, with monitoring year one being the year that the changes are complete, as confirmed by DEQ. If the wetland or stream compensation area fails to meet the specified success criteria by the final monitoring year, or if the wetland or stream compensation area has not met the stated restoration goals, reasons for this failure shall be determined and a corrective action plan, including proposed actions, a schedule, and a monitoring plan, shall be submitted with the final year monitoring report for DEQ approval. Corrective action shall be implemented by the permittee in accordance with the approved schedule. Annual monitoring shall be required to continue until two sequential, annual reports indicate that all criteria have been successfully satisfied and the site has met the overall restoration goals (e.g., that corrective actions were successful). 19. The surveyed wetland boundary for the wetlands compensation site shall be based on the results of the hydrology, soils, and vegetation monitoring data and shall be shown on the site plan. Calculation of total wetland acreage shall be based on that boundary at the end of the monitoring cycle. Data shall be submitted by December 31 of the final monitoring year. 20. Herbicides or algicides shall not be used in or immediately adjacent to the wetlands or stream compensation site or sites without prior authorization by the board. All vegetation removal shall be done by manual means, unless authorized by DEQ in advance. B. Impact site construction monitoring. 1. Construction activities authorized by this permit that are within impact areas shall be monitored and documented. The monitoring shall document the preexisting conditions, activities during construction, and post - construction conditions. Monitoring shall consist of one of the following options: a. Photographs shall be taken during construction at the end of the first, second, and third months after commencing construction, and then every six months thereafter for the remainder of the construction project. Photos are not required during periods of no activity within impact areas. b. An ortho - rectified photograph shall be taken by a firm specializing in ortho - rectified photography prior to construction, and then annually thereafter, until all impacts are taken. Photos shall clearly show the delineated surface waters and authorized impact areas. c. In lieu of photographs, and with prior approval from DEQ, the permittee may submit a written narrative that summarizes site construction activities in impact areas. The narrative shall be submitted at the end of the first, second, and third months after commencing construction, and then every six months thereafter, for the remainder of the construction activities. Narratives are not required during periods of no activity within the impact areas. 2. As part of construction monitoring, photographs taken at the photo stations or the narrative shall document site activities and conditions, which may include installation and maintenance of erosion and sediment controls; surface water discharges from the site; condition of adjacent nonimpact surface waters; flagged nonimpact surface waters; construction access and staging areas; filling, excavation, and dredging activities; culvert installation; dredge disposal; and site stabilization, grading, and associated restoration activities. With the exception of the preconstruction photographs, photographs at an individual impact site shall not be required until construction activities are initiated at that site. With the exception of the post - construction photographs, photographs at an individual impact site shall not be required once the site is stabilized following completion of construction at that site. 3. Each photograph shall be labeled to include the following information: permit number, impact area and photo station number, date and time of the photograph, name of the person taking the photograph, photograph orientation, and photograph subject description. 4. Monitoring of water quality parameters shall be conducted during permanent relocation of perennial streams through new channels in the manner noted below. The permittee shall report violations of water quality standards to DEQ in accordance with the procedures in Part II E. Corrective measures and additional monitoring may be required VWP General Permit WP4 -08 -0835 Part II Page 9 of 16 if water quality standards are not met. Reporting shall not be required if water quality standards are not violated. a. A sampling station shall be located upstream and immediately downstream of the relocated channel. b. Temperature, pH and dissolved oxygen (D.O.) measurements shall be taken every 30 minutes for at least two hours at each station prior to opening the new channels and immediately before opening new channels. c. Temperature, pH and D.O. readings shall be taken after opening the channels and every 30 minutes for at least three hours at each station. C. Wetland compensation site monitoring. 1. An as -built ground survey, or an aerial survey provided by a firm specializing in aerial surveys, shall be conducted for the entire compensation site or sites including invert elevations for all water elevation control structures and spot elevations throughout the site or sites. Aerial surveys shall include the variation from actual ground conditions, such as +/- 0.2 feet. Either type of survey shall be certified by a licensed surveyor or by a registered professional engineer to conform to the design plans. The survey shall be submitted within 60 days of completing compensation site construction. Changes or deviations in the as -built survey or aerial survey shall be shown on the survey and explained in writing. 2. Photographs shall be taken at the compensation site or sites from the permanent markers identified in the final compensation plan, and established to ensure that the same locations and view directions at the site or sites are monitored in each monitoring period. These photographs shall be taken after the initial planting and at a time specified in the final compensation plan during every monitoring year. 3. Compensation site monitoring shall begin on day one of the first complete growing season (monitoring year 1) after wetland compensation site construction activities, including planting, have been completed. Monitoring shall be required for monitoring years 1, 2, 3, and 5, unless otherwise approved by DEQ. In all cases if all success criteria have not been met in the final monitoring year, then monitoring shall be required for each consecutive year until two annual sequential reports indicate that all criteria have been successfully satisfied. 4. The establishment of wetland hydrology shall be measured during the growing season, with the location and number of monitoring wells, and frequency of monitoring for each site, set forth in the final monitoring plan. Hydrology monitoring well data shall be accompanied by precipitation data, including rainfall amounts either from on site or from the closest weather station. Once the wetland hydrology success criteria have been satisfied for a particular monitoring year, monitoring may be discontinued for the remainder of that monitoring year following DEQ approval. After a period of three monitoring years, the permittee may request that hydrology monitoring be discontinued, providing that adequate hydrology has been established and maintained. Hydrology monitoring shall not be discontinued without written approval from DEQ. 5. The presence of hydric soils or soils under hydric conditions shall be evaluated in accordance with the final compensation plan. 6. The establishment of wetland vegetation shall be in accordance with the final compensation plan. Monitoring shall take place in August, September, or October during the growing season of each monitoring year, unless otherwise authorized in the monitoring plan. 7. The presence of undesirable plant species shall be documented. 8. All wetland compensation monitoring reports shall be submitted in accordance with 9 VAC 25- 690 -100 Part II E 6. D. Stream compensation. restoration. and monitorine. 1. Riparian buffer restoration activities shall be detailed in the final compensation plan and shall include, as appropriate, the planting of a variety of native species currently growing in the site area, including appropriate seed mixtures and woody species that are bare root, balled, or burlapped. A minimum buffer width of 50 feet, measured from the top of the stream bank at bankfull elevation landward on both sides of the stream, shall be required where VWP General Permit WP4 -08 -0835 Part II Page 10 of 16 practical. 2. The installation of root wads, vanes, and other instream structures, shaping of the stream banks, and channel relocation shall be completed in the dry whenever practicable. 3. Livestock access to the stream and designated riparian buffer shall be limited to the greatest extent practicable. 4. Stream channel restoration activities shall be conducted in the dry or during low flow conditions. When site conditions prohibit access from the streambank, heavy equipment shall be authorized for use within the stream channel. 5. Photographs shall be taken at the compensation site from the vicinity of the permanent photo stations identified in the final compensation plan. The photograph orientation shall remain constant during all monitoring events. At a minimum, photographs shall be taken from the center of the stream, facing downstream, with a sufficient number of photographs to view the entire length of the restoration site. Photographs shall document the completed restoration conditions. Photographs shall be taken prior to site activities, during instream and riparian compensation construction activities, within one week of completion of activities, and during at least one day of each monitoring year to depict restored conditions. 6. An as -built ground survey, or an aerial survey provided by a firm specializing in aerial surveys, shall be conducted for the entire compensation site or sites. Aerial surveys shall include the variation from actual ground conditions, such as +/- 0.2 feet. The survey shall be certified by the licensed surveyor or by a registered, professional engineer to conform to the design plans. The survey shall be submitted within 60 days of completing compensation site construction. Changes or deviations from the final compensation plans in the as -built survey or aerial survey shall be shown on the survey and explained in writing. 7. Compensation site monitoring shall begin on day one of the first complete growing season (monitoring year 1) after stream compensation site construction activities, including planting, have been completed. Monitoring shall be required for monitoring years 1 and 2, unless otherwise determined by DEQ. In all cases, if all success criteria have not been met in the final monitoring year, then monitoring shall be required for each consecutive year until two annual sequential reports indicate that all criteria have been successfully satisfied. 8. All stream compensation monitoring reports shall be submitted in accordance with 9 VAC 25- 690 -100 Part II E 6. E. Reporting. 1. Written communications required by this VWP general permit shall be submitted to the appropriate DEQ office. The VWP general permit authorization number shall be included on all correspondence. 2. DEQ shall be notified in writing at least 10 days prior to the start of construction activities at the first permitted site authorized by this VWP general permit authorization so that inspections of the project can be planned, if deemed necessary by DEQ. The notification shall include a projected schedule for initiation and completion of work at each permitted impact area. 3. Construction monitoring reports shall be submitted to DEQ no later than the 10th day of the month following the month in which the monitoring event specified in Part II B takes place, unless otherwise specified below. The reports shall include the following, as appropriate: a. For each permitted impact area, a written narrative stating whether work was performed during the monitoring period, and if work was performed, a description of the work performed, when the work was initiated, and the expected date of completion. b. Photographs labeled with the permit number, the photo station number, the photo orientation, the date and time of the photo, the name of the person taking the photograph, and a brief description of the construction activities. The first construction monitoring report shall include the photographs taken at each impact site prior to initiation of construction in a permitted impact area. Written notification and photographs demonstrating that all temporarily disturbed wetland and stream areas have been restored in compliance with the permit conditions shall be submitted within 30 days of restoration. The post- VWP General Permit WP4 -08 -0835 Part II Page 11 of 16 construction photographs shall be submitted within 30 days of documenting post - construction conditions. c. Summary of activities conducted to comply with the permit conditions. d. Summary of permit noncompliance events or problems encountered, subsequent notifications, and corrective actions. e. Summary of anticipated work to be completed during the next monitoring period, and an estimated date of construction completion at all impact areas. f. Labeled site map depicting all impact areas and photo stations. 4. DEQ shall be notified in writing within 30 days following the completion of all activities in all permitted impact areas authorized under this permit. 5. DEQ shall be notified in writing at least 10 days prior to the initiation of activities at the compensation site. The notification shall include a projected schedule of activities and construction completion. 6. All compensation monitoring reports shall be submitted annually by December 31, with the exception of the last year of authorization, in which case the report shall be submitted at least 60 days prior to expiration of authorization under the general permit. a. All wetland compensation monitoring reports shall include, as applicable, the following: (1) General description of the site including a site location map identifying photo stations, vegetative and soil monitoring stations, monitoring wells, and wetland zones. (2) Summary of activities completed during the monitoring year, including alterations or maintenance conducted at the site. (3) Description of monitoring methods. (4) Analysis of all hydrology information, including monitoring well data, precipitation data, and gauging data from streams or other open water areas, as set forth in the final compensation plan. (5) Evaluation of hydric soils or soils under hydric conditions, as appropriate. (6) Analysis of all vegetative community information, including woody and herbaceous species, both planted and volunteers, as set forth in the final compensation plan. (7) Photographs labeled with the permit number, the name of the compensation site, the photo station number, the photograph orientation, the date and time of the photograph, the name of the person taking the photograph, and a brief description of the photograph subject. This information shall be provided as a separate attachment to each photograph, if necessary. Photographs taken after the initial planting shall be included in the first monitoring report after planting is complete. (8) Discussion of wildlife or signs of wildlife observed at the compensation site. (9) Comparison of site conditions from the previous monitoring year and reference site. (10) Discussion of corrective measures or maintenance activities to control undesirable species, to repair damaged water control devices, or to replace damaged planted vegetation. (11) Corrective action plan, which includes proposed actions, a schedule, and monitoring plan. b. All stream compensation monitoring reports shall include, as applicable, the following: (1) General description of the site including a site location map identifying photo stations and VWP General Permit WP4 -08 -0835 Part II Page 12 of 16 monitoring stations. (2) Summary of activities completed during the monitoring year, including alterations or maintenance conducted at the site. (3) Description of monitoring methods. (4) An evaluation and discussion of the monitoring results in relation to the success criteria and overall goals of compensation. (5) Photographs shall be labeled with the permit number, the name of the compensation site, the photo station number, the photograph orientation, the date and time of the photograph, the name of the person taking the photograph, and a brief description of the photograph subject. Photographs taken prior to compensation site construction activities, during instream and riparian restoration activities, and within one week of completion of activities shall be included in the first monitoring report. (6) A discussion of alterations, maintenance, or major storm events resulting in significant change in stream profile or cross section, and corrective actions conducted at the stream compensation site. (7) Documentation of undesirable plant species and summary of abatement and control measures. (8) A summary of wildlife or signs of wildlife observed at the compensation site. (9) Comparison of site conditions from the previous monitoring year and reference site, and as- built survey, if applicable. (10) A corrective action plan, which includes proposed actions, a schedule and monitoring plan. (11) Additional submittals that were approved by DEQ in the final compensation plan. 7. The permittee shall notify DEQ in writing when unusual or potentially complex conditions are encountered which require debris removal or involve potentially toxic substance. Measures to remove the obstruction, material, or toxic substance or to change the location of a structure are prohibited until approved by DEQ. 8. The permittee shall report fish kills or spills of oil or fuel immediately upon discovery. If spills or fish kills occur between the hours of 8:15 a.m. to 5 p.m., Monday through Friday, the appropriate DEQ regional office shall be notified; otherwise, the Department of Emergency Management shall be notified at 1- 800 - 468 -8892. 9. Violations of state water quality standards shall be reported within 24 hours to the appropriate DEQ office. 10. Submittals required by this VWP general permit shall contain the following signed certification statement: "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violation." VWP General Permit WP4 -08 -0835 Part III Page 13 of 16 Part III. Conditions Applicable to All VWP General Permits A. Dutv to comply. The permittee shall comply with all conditions of the VWP general permit. Nothing in this VWP general permit shall be construed to relieve the permittee of the duty to comply with all applicable federal and state statutes, regulations, and toxic standards and prohibitions. VWP general permit noncompliance is a violation of the Clean Water Act and State Water Control Law, and is grounds for enforcement action, VWP general permit authorization termination for cause, VWP general permit authorization revocation, or denial of a continuation of coverage request. B. Duty to mitigate. The permittee shall take all reasonable steps to minimize or prevent impacts in violation of the VWP general permit which may have a reasonable likelihood of adversely affecting human health or the environment. C. Reopener. This VWP general permit authorization may be reopened to modify its conditions when the circumstances on which the previous VWP general permit authorization was based have materially and substantially changed, or special studies conducted by the board or the permittee show material and substantial change since the time the VWP general permit authorization was issued and thereby constitute cause for VWP general permit authorization revocation and reissuance. D. Compliance with state and federal law. Compliance with this VWP general permit constitutes compliance with the VWP permit requirements of the State Water Control Law. Nothing in this VWP general permit shall be construed to preclude the institution of any legal action under or relieve the permittee from any responsibilities, liabilities, or other penalties established pursuant to any other state law or regulation or under the authority preserved by § 510 of the Clean Water Act. E. Property rights. The issuance of this VWP general permit does not convey property rights in either real or personal property, or exclusive privileges, nor does it authorize injury to private property or invasion of personal property rights, nor infringement of federal, state or local laws or regulations. F. Severability. The provisions of this VWP general permit authorization are severable. G. Right of entry. The permittee shall allow the board or its agents, upon the presentation of credentials, at reasonable times and under reasonable circumstances to enter the permittee's property, public or private, and have access to, inspect and copy records that must be kept as part of the VWP general permit conditions; to inspect facilities, operations or practices (including monitoring and control equipment) regulated or required under the VWP general permit; and to sample or monitor any substance, parameter or activity for the purpose of assuring compliance with the conditions of the VWP general permit or as otherwise authorized by law. For the purpose of this section, the time for inspection shall be deemed reasonable during regular business hours. Nothing contained herein shall make an inspection time unreasonable during an emergency. H. Transferability of VWP general permit authorization. This VWP general permit authorization may be transferred to another person by a permittee when all of the criteria listed below are met. On the date of the VWP general permit authorization transfer, the transferred VWP general permit authorization shall be as fully effective as if it had been issued directly to the new permittee. 1. The current permittee notifies the board of the transfer of the title to the facility or property. 2. The notice to the board includes a written agreement between the current and new permittees containing a specific VWP General Permit WP4 -08 -0835 Part III Page 14 of 16 date of transfer of VWP general permit authorization responsibility, coverage and liability to the new permittee, or that the current permittee will retain such responsibility, coverage or liability, including liability for compliance with the requirements of enforcement activities related to the permitted activity. 3. The board does not notify the current and new permittees of its intent to modify or revoke and reissue the VWP general permit authorization within 15 days. I. Notice of planned change. Authorization under the VWP general permit may be modified subsequent to issuance in one or more of the cases listed below. A notice of planned change is not required if the project results in additional temporary impacts to surface waters, provided that DEQ is notified in writing, the additional temporary impacts are restored to preexisting conditions in accordance with Part I C 11 of this general permit, and the additional temporary impacts do not exceed the general permit threshold for use. The permittee shall notify the board in advance of the planned change, and the planned change request will be reviewed according to all provisions of this regulation. 1. The permittee determines that additional permanent wetland, open water, or stream impacts are necessary, provided that the additional impacts are associated with the previously authorized activities in authorized locations within the same phase of development, the cumulative increase in acreage of wetland or open water impacts is not greater than 1/4 acre, the cumulative increase in stream bed impacts is not greater than 100 linear feet, and the additional impacts are fully compensated. 2. The project results in less wetland or stream impacts, in which case, compensation requirements may be modified in relation to the adjusted impacts at the request of the permittee, provided that the adjusted compensation meets the initial authorization compensation goals. 3. There is a change in the project plans that does not result in a change in project impacts. 4. There is a change in the mitigation bank at which credits are purchased or used, provided that the same amount of credits are purchased or used and all criteria for use are met, as detailed in 9 VAC 25- 210 -116 E. 5. Typographical errors need to be corrected. J. VWP general permit authorization termination for cause. This VWP general permit authorization is subject to termination for cause by the board after public notice and opportunity for a hearing. Reasons for termination for cause are as follows: 1. Noncompliance by the permittee with any condition of the VWP general permit authorization; 2. The permittee's failure in the application or during the VWP general permit authorization issuance process to disclose fully all relevant facts or the permittee's misrepresentation of any relevant facts at any time; 3. The permittee's violation of a special or judicial order; and 4. A determination that the permitted activity endangers human health or the environment and can be regulated to acceptable levels by a VWP general permit authorization planned change or termination for cause. K. VWP general permit authorization termination by consent. This VWP general permit authorization may be terminated by consent when all permitted activities requiring notification under 9 VAC 25- 690 -50 A and all compensatory mitigation have been completed or when the authorized impacts will not occur. The permittee shall submit a request for termination by consent within 30 days of project completion or project cancellation. When submitted for project completion, the termination by consent shall constitute a notice of completion in accordance with 9 VAC 25- 210 -130. The director may accept this termination of authorization on behalf of the board. The request for termination by consent shall contain the following information: 1. Name, mailing address and telephone number of the permittee; VWP General Permit WP4 -08 -0835 Part III Page 15 of 16 2. Name and location of the activity; 3. The VWP permit authorization number; and 4. One of the following certifications: a. For project completion: "I certify under penalty of law that all activities and any required compensatory mitigation authorized by a VWP general permit have been completed. I understand that by submitting this notice of termination I am no longer authorized to perform activities in surface waters in accordance with the VWP general permit, and that performing activities in surface waters is unlawful where the activity is not authorized by a VWP permit. I also understand that the submittal of this notice does not release me from liability for any violations of this VWP general permit authorization." b. For project cancellation: "I certify under penalty of law that the activities and any required compensatory mitigation authorized by this VWP general permit will not occur. I understand that by submitting this notice of termination I am no longer authorized to perform activities in surface waters in accordance with the VWP general permit, and that performing activities in surface waters is unlawful where the activity is not authorized by a VWP permit. I also understand that the submittal of this notice does not release me from liability for any violations of this VWP general permit authorization, nor does it allow me to resume the permitted activities without reapplication and reauthorization." c. For events beyond permittee control, the permittee shall provide a detailed explanation of the events, to be approved by DEQ, and the following certification statement: "I certify under penalty of law that the activities or the required compensatory mitigation authorized by a VWP general permit have changed as the result of events beyond my control (see attached). I understand that by submitting this notice of termination I am no longer authorized to perform activities in surface waters in accordance with the VWP general permit, and that performing activities in surface waters is unlawful where the activity is not authorized by a VWP permit. I also understand that the submittal of this notice does not release me from liability for any violations of this VWP general permit authorization, nor does it allow me to resume the permitted activities without reapplication and reauthorization." L. Civil and criminal liabilitv. Nothing in this VWP general permit shall be construed to relieve the permittee from civil and criminal penalties for noncompliance. M. Oil and hazardous substance liability. Nothing in this VWP general permit shall be construed to preclude the institution of legal action or relieve the permittee from any responsibilities, liabilities, or penalties to which the permittee is or may be subject under § 311 of the Clean Water Act or §§ 62.1- 44.34:14 through 62.1- 44.34:23 of the State Water Control Law. N. Duty to cease or confine activity. It shall not be a defense for a permittee in an enforcement action that it would have been necessary to halt or reduce the activity for which a VWP permit has been granted in order to maintain compliance with the conditions of the VWP permit. O. Duty to provide information. 1. The permittee shall furnish to the board any information which the board may request to determine whether cause exists for modifying, revoking and reissuing and terminating the VWP permit authorization, or to determine compliance with the VWP permit authorization. The permittee shall also furnish to the board, upon request, copies of records required to be kept by the permittee. 2. Plans, maps, conceptual reports and other relevant information shall be submitted as required by the board prior to VWP General Permit WP4 -08 -0835 Part III Page 16 of 16 commencing construction. P. Monitoring and records requirements. 1. Monitoring of parameters, other than pollutants, shall be conducted according to approved analytical methods as specified in the VWP permit. Analysis of pollutants will be conducted according to 40 CFR Part 136 (2000), Guidelines Establishing Test Procedures for the Analysis of Pollutants. 2. Samples and measurements taken for the purpose of monitoring shall be representative of the monitored activity. 3. The permittee shall retain records of all monitoring information, including all calibration and maintenance records and all original strip chart or electronic recordings for continuous monitoring instrumentation, copies of all reports required by the VWP permit, and records of all data used to complete the application for the VWP permit, for a period of at least three years from the date of the expiration of a granted VWP permit. This period may be extended by request of the board at any time. 4. Records of monitoring information shall include, as appropriate: a. The date, exact place and time of sampling or measurements; b. The name of the individuals who performed the sampling or measurements; c. The date and time the analyses were performed; d. The name of the individuals who performed the analyses; e. The analytical techniques or methods supporting the information such as observations, readings, calculations and bench data used; f. The results of such analyses; and g. Chain of custody documentation. Q. Unauthorized discharge of pollutants. Except in compliance with this VWP general permit, it shall be unlawful for the permittee to: 1. Discharge into state waters sewage, industrial wastes, other wastes, or any noxious or deleterious substances; 2. Excavate in a wetland; 3. Otherwise alter the physical, chemical, or biological properties of state waters and make them detrimental to the public health, to animal or aquatic life, to the uses of such waters for domestic or industrial consumption, for recreation, or for other uses; or 4. On and after October 1, 2001, conduct the following activities in a wetland: a. New activities to cause draining that significantly alters or degrades existing wetland acreage or functions; b. Filling or dumping; c. Permanent flooding or impounding; or d. New activities that cause significant alteration or degradation of existing wetland acreage or functions. DEPARTMENT OF THE ARMY NORFOLK DISTRICT CORPS OF ENGINEERS - FORT NORFOLK GI FRONT STREET NORFOLK, VIRGINIA 23510 -1096 CENAO -WRR REGIONAL PROGRAMATIC GENERAL PERMIT 12- SPGP -01 Effective Date: May 31, 2012 Expiration Date: May 31, 2017 I. AUTHORITIES: 12- SPGP -01 authorizes the discharge of dredged or fill material in nontidal waters, of the United States, including wetlands, associated with certain residential, commercial, and institutional developments and linear transportation projects within the geographical limits of the Commonwealth of Virginia and under the regulatory jurisdiction of the U.S. Army Corps of Engineers, Norfolk District (Corps or Norfolk District). These projects must have no more than minimal individual and cumulative impacts and must meet all the terms and conditions outlined herein. The use of 12- SPGP -01 is restricted to those projects that have avoided and minimized impacts to waters of the U.S., including wetlands, to the maximum extent practicable. The people of the Commonwealth of Virginia (Virginia or "the Commonwealth ") are hereby authorized by the Secretary of the Army and the Chief of Engineers, pursuant to Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. § 403) and Section 404 of the CWA (33 U.S.C. § 1344), to perform the aforementioned work in nontidal waters and wetlands of the Commonwealth as described herein. The Corps' authority and guidance to develop general permits is contained in 33 U.S.C. § 1344(e) and 33 C.F.R. § 325.2(e)(2), 33 C.F.R. § 325.3(b), and Corps Regulatory Guidance Letter 83 -7. II. PROCEDURES: A. Delineation Confirmations: Prior to the submission of an application for any Residential, Commercial, or Institutional Development Activity or Linear Transportation Activity covered by 12- SPGP -01, a proponent must first obtain a confirmed delineation of all waters of the U.S., including wetlands, and Virginia state surface waters on the property. The applicant will contact the Corps to obtain a delineation confirmation. A confirmed delineation is not required for Virginia Department of Transportation (VDOT) linear transportation projects (these projects must adhere to separate, but similar, procedures). When appropriate a delineation confirmation may also be required from the Environmental Protection Agency (EPA). B. Application: Applicants must use the newest version of Joint Permit Applications (JPAs) and submit these applications to the Virginia Marine Resources Commission (VMRC). The applicable Virginia Water Protection (VWP) permit regulations define the information required for a complete VWP permit application (see 9 VAC 25- 210 -80, 9 VAC 25- 660 -50, 9 VAC 25- 670 -50, 9 VAC 25- 680 -50, and 9 VAC 25- 690 -50). This information, plus a confirmed delineation from the Corps with associated map(s) and data sheets, will be required to render an application complete for 12- SPGP -01 purposes. VDOT will submit the Inter- Agency Coordination Meeting JPA or the VDOT Reporting Only Spreadsheet. A joint permit application may be obtained through the following link: http:// www .nao.usace.army.mil/Reg-ulatoiy Branch/JPA.asp C. State Approvals: In order for 12- SPGP -01 to be valid, permittees must obtain the following state approvals prior to commencement of work in waters of the U.S.: 1. Virginia Department of Environmental Quality (VDEQ) VWP permit and 2. VMRC permit, when required For the purpose of resolving non - compliance and/or enforcement actions the 12- SPGP -01 may be issued or modified in conjunction with a VDEQ informal resolution, letter of agreement, executive compliance agreement or consent order. Authorizations under 12- SPGP -01 also require that permittees ensure that their projects are designed and constructed in a manner consistent with all state and local requirements pursuant to the Chesapeake Bay Preservation Act (Virginia Code 10.1 -2100 et seq.) and the Chesapeake Bay Preservation Area Designation and Management Regulations (9 VAC 10 -20 -10 et seq.), the Virginia Erosion and Sediment Control Regulations (4 VAC 30 -50 -10 et seq.), and the Virginia Stormwater Management Program (VSMP) Permit Regulation (4 VAC 50 -60 -10 et seq.). Authorizations under 12- SPGP -01 do not supersede state or local government authority or responsibilities pursuant to the Act. D. Defmitions: a. For purposes of 12- SPGP -01, "loss" of waters of the U.S., including wetlands, shall be defined as filling (including placement of pipes or other water conveyances in waters) and other permanent adverse effects, including mechanized landclearing, permanent conversion, excavation (including channelization), flooding, draining, etc. The acreage/linear footage of loss of waters of the U.S. is the threshold measurement of the impact to existing waters, including wetlands, for determining whether a project may qualify for 12- SPGP -01; it is not a net threshold that is calculated after considering compensatory mitigation that may be used to offset losses of aquatic functions and values. b. For purposes of 12- SPGP -01, "natural stream design" means that the channel should mimic the dimension, pattern, and profile of a representative reference stream reach. c. For purposes of 12- SPGP -01, VDEQ is the state agency responsible for ensuring permit applications meet the informational and technical requirements of the 12- SPGP -01 and for issuance of 12- SPGP -01 authorizations for qualifying Residential, Commercial, Institutional and Linear Transportation projects. d. For purposes of 12- SPGP -01, the "permittee" will be the responsible party in receipt of the 12- SPGP -01 authorization from the VDEQ. The permittee will be the responsible party for complying with all 12- SPGP -01 general conditions as well as any additional special conditions required of each project. e. For purposes of 12- SPGP -01, "lateral encroachment" is when a road, utility or other project encroaches into waters of the U.S., including wetlands, but does not cross the resource perpendicularly or diagonally. III. AUTHORIZED ACTIVITIES A. Residential, Commercial, and Institutional Development Activities: a. Eligibility Criteria: i. Activities are subject to Corps jurisdiction; ii. Activity involves the discharge of dredged or fill material associated with residential, commercial, and institutional projects causing the permanent loss of not more than one acre of nontidal wetlands or open waters or the permanent loss of not more than 2,000 linear feet of stream channel, unless otherwise excluded by 12- SPGP -01; iii. Activity meets the general conditions of 12- SPGP -01 listed on pages 7 -14 and any special conditions required of each project- specific authorization; iv. Compensatory mitigation is provided in accordance with the mitigation standards and general conditions on pages 10 -11; and V. Discharges associated with residential, commercial, and institutional development activities include those outlined in the VDEQ's General Permits (see 9 VAC 25 -660 et seq., 9 VAC 25 -670 et seq., 9 VAC 25 -680 et seq., and 9 VAC 25 -690 et seq.) and are associated with the construction or expansion of residential, commercial, or institutional building foundations, building pads, and attendant features that are necessary for the use and maintenance of the structures. Attendant features may include, but are not limited to, roads, parking lots, garages, yards, utility lines, stormwater management facilities, and recreational facilities such as playgrounds, playing fields, and golf courses (provided the golf course is an integral part of the residential development). Residential developments include multiple and single unit developments. Commercial developments include retail stores, industrial facilities, restaurants, business parks, and shopping centers. Institutional developments include schools, fire stations, government office buildings, judicial buildings, public works buildings, libraries, hospitals, and places of worship. For residential, commercial, and institutional developments, the aggregate permanent loss of waters of the U.S. cannot exceed one acre of nontidal wetlands or open water; or 2,000 linear feet of stream. vi. Residential, commercial, or institutional developments are consistent with the Corps' subdivision guidance dated March 15, 1993 and June 2, 1999, the Corps' and VDEQs' joint subdivision guidance dated June, 2007 and/or any subsequent guidance that supersedes or supplements those documents. b. Federal Screening Procedures: i. All residential, commercial, and institutional development activities that will cause or result in impacts to tidal waters, including wetlands, and/or permanent impacts that exceed 1/2 acre of non -tidal wetlands or open waters and/or exceed 300 linear feet of stream channel will be coordinated with the Corps, the U.S. Environmental Protection Agency (EPA), and the U.S. Fish and Wildlife Service (FWS) for federal review. ii. If EPA or FWS determines that there are project- specific concerns regarding avoidance and/or minimization of impacts to the aquatic environment or concerns regarding the amount and/or type of compensatory mitigation being proposed, the applicant will be required to address those concerns. If the concerns are not addressed to the satisfaction of the objecting agency(ies), the Corps District Commander may exert his/her discretionary authority to require the project to be processed under the Corps' individual permit process. iii. Any Corps' concerns shall be relayed to the VDEQ and addressed during the VDEQ permitting process. If concerns are not satisfied through that process, the Corps District Commander may exert his/her discretionary authority to require the project to be processed under an alternate Corps permitting process, possibly as an individual permit. B. Linear Transportation Activities: a. Eligibilitv Criteria: i. Activities are subject to Corps jurisdiction; ii. Activities involve the discharge of dredged or fill material associated with the construction, expansion, modification, or improvement of linear transportation projects not causing the permanent loss of more than 1/3 acre of waters of the U.S., including wetlands, at any single impact site with independent utility, unless otherwise excluded by 12- SPGP -01; iii. Activity meets all general conditions of 12- SPGP -01 listed on pages 7 -14 and any special conditions required of each project - specific authorization; iv. Compensatory mitigation is provided for all unavoidable impacts to wetlands; V. Compensatory mitigation is provided for all unavoidable stream impacts where total permanent impacts exceed 300 linear feet of stream channel (or mitigation for any lower level of impact if it is determined that it is necessary to ensure that a project's impacts are minimal in nature) in accordance with the mitigation standards general condition on pages 10 -11. Stream relocation using natural stream design may be considered self - mitigating, as determined on a case -by -case basis; vi. Lateral encroachments may be authorized by the 12- SPGP -01 if the project meets the following criteria: 1. Impacts due to all project lateral encroachments, including stream relocations, do not exceed 1/3 acre of waters of the United States or 2,000 linear feet of stream channel; 2. Total project lateral encroachments do not cause the permanent loss of more than 300 linear feet of stream channel due to the installation of piping, riprap, concrete, etc; 3. All project lateral encroachments exceeding 300 linear feet of stream channel are performed using natural stream design (unless waived in writing); and 4. Impacts due to lateral encroachment(s), new alignment projects and/or projects that impact the same aquatic resources multiple times will be considered cumulative for the entire project regardless of whether segments of that project may have independent utility; vii. Discharges associated with linear transportation projects include the construction, expansion, modification, or improvement of highways, roads, railways, trails, and airport runways and taxiways. Construction and/or relocation of utility lines within the right -of- way /easements of the project and performed in direct relation with the project are covered under this activity, with impacts counting toward permit thresholds. b. Federal Screening Procedures: L All linear transportation activities involving permanent impacts that exceed 300 linear feet of stream channel at any single impact area OR containing multiple single and complete impact areas on the same project that additively exceed 1/3 acre of impact to waters of the United States, including wetlands and/or exceed 300 linear feet of stream channel (lateral or crossing impact) will be reviewed by the Corps, the EPA, and the FWS. ii. If EPA or FWS determines that there are project specific concerns regarding avoidance and/or minimization of impacts to the aquatic environment or the amount and/or type of compensatory mitigation being proposed, the applicant will be required to address those concerns. If the concerns are not addressed to the satisfaction of the objecting agency(ies), the Corps District Commander may exert his/her discretionary authority to require the project to be processed under the Corps' individual permit process. iii. Any Corps' concerns shall be relayed to the VDEQ and addressed during the VDEQ permitting process. If concerns are not satisfied through that process, the Corps District Commander may exert his/her discretionary authority to require the project to be processed under an alternate Corps permitting process. c. VDOT Reporting -Only Procedures: VDOT may report by spreadsheet on a monthly basis to the VDEQ those VDOT projects meeting the following eligibility criteria: i. Permanent impacts do not exceed 1 /10 acre of waters of the United States, including wetlands; the definition of independent utility must be applied when determining permanent impact totals; ii. Section 7 — Endangered Species Act Review has been completed, includes FWS concurrence with findings, if needed; iii. Section 106 finding of "No Effect" has been reviewed and approved by the VDEQ- Cultural Resource Specialist; and iv. For projects with cumulative impacts exceeding 3 00 linear feet of stream channel, a pre- coordination email will be sent to the Corps with a project description, impacts, topographic quadrangle and photos. The VDEQ and VDOT Central Office will be copied on the email. If the Corps concurs that project can be included on the spreadsheet, VDOT will include the Corps concurrence email with the spreadsheet submittal. No additional Norfolk District review will be required. If the Corps does not concur that project can be included on the spreadsheet, VDOT will submit a JPA through its interagency coordination meeting and will include the Corps' response email in the application. C. Exclusions from Coverage: The following activities and resources areas are excluded from coverage by 12- SPGP -0 1 and require different types of Corps permits: a. Conversion of waters and/or wetlands for agricultural production and agriculture - related activities (crop fields or pasture); farm buildings; grain storage facilities; grassed waterways; low water crossings; impoundments for irrigation, livestock watering, and fire prevention purposes; animal feeding operations; waste storage facilities; and farm access roads; b. Wetland areas composed of 10% or more of the following species (singly or in combination) in any stratum: Atlantic white cedar (Chamaecyparis thyoides), bald cypress (Taxodium distichum), water tupelo (Nyssa aquatica), or overcup oak (Quercus lyrata) (Percentages may be based on stem counts, basal area, or percent aerial cover); c. Wetland areas underlain by histosols (Histosols are organic soils that are often called mucks, peats, or mucky peats. The list of histosols includes, but is not limited to, the following soil series: Back Bay, Belhaven, Dorovan, Lanexa, Mattamuskeet, Mattan, Palms, Pamlico, Pungo, Pocaty, and Rappahannock; d. Placement of septic tanks (does not include alternate onsite sewer systems); e. Residential gardening, lawn maintenance and landscaping; f. Construction of extended - detention basins and enhanced extended - detention basins designed, constructed, and maintained to function in accordance with the current Virginia Department of Conservation and Recreation (DCR) standards for such facilities or local standards that, at a minimum meet the DCR standards, unless the following requirements are met: i. The area within the entire basin and back - flooding limits are considered as permanent impacts. For the purposes of the 12- SPGP -01, back - flooding limits are defined as back - flooding that will not be released within 24 hours if the activity is east of I -95, or back - flooding that will not be released within 48 hours if the activity is west of I -95. ii. The proposed basins are attendant features associated with a "single and complete" residential, commercial, institutional or linear transportation project; g. Construction or maintenance of farm or stock ponds that do not fall under the authority of the Virginia Soil and Water Conservation Board pursuant to Article 2 (§ 10.1 -604 et seq.) of Chapter 6 pursuant to normal agricultural or silvicultural activities; and h. Discharges of dredged or fill material associated with residential, commercial, and institutional activities causing the permanent loss of more than one acre of nontidal wetlands or open waters or waters or over 2,000 linear feet of stream channel. IV. GENERAL CONDITIONS: The following conditions apply to all activities authorized under 12- SPGP -01. Work that does not meet one or more of the terms and general conditions of 12- SPGP -01, including work that has been determined to be more than minimal in nature (at any impact level), will require consideration under a different type of Corps permit. 1. Other permits. Authorization does not obviate the need to obtain other Federal, state, or local authorizations required by law or to comply with all Federal, state, or local laws. 2. Minimal effects. Projects authorized shall have no more than minimal individual or cumulative adverse environmental impacts, as determined by the Corps. 3. Discretionary authority. The Corps District Commander retains discretionary authority to require processing of an individual permit based on concerns for the aquatic environment or for any other factor of the public interest (33 C.F.R. § 320.4(a)). This authority is exercised on a case -by -case basis. 4. Single and complete projects. 12- SPGP -01 shall only be applied to single and complete projects. For purposes of 12- SPGP -01, a single and complete project means the total project proposed or accomplished by one owner /developer or partnership and which has independent utility. For linear transportation projects with multiple crossings or encroachments a determination of "single and complete" will typically apply to each crossing of waters that occurs (i.e., single waterbody and/or wetlands) at separate and distinct locations and with independent utility. However, in cases where there are many crossings in close proximity, numerous crossings of the same waterbody, multiple crossings, or multiple encroachments that otherwise may have more than minimal individual or cumulative impacts; the Corps has the discretion to consider all the crossings cumulatively as one single and complete project. 5. Independent utility. A project is considered to have independent utility if it would be constructed absent the construction of other projects in the project area. Portions of a multi -phase project that depend upon other phases of the project do not have independent utility. Phases of a project that would be constructed even if the other phases were not built can be considered as a separate, single and complete project with independent utility. For a linear transportation project, separate impact areas on a new location roadway are not considered to have independent utility thus impacts would be considered cumulatively and eligible for a single 12- SPGP -01 authorization. However, separate impact areas on a roadway that is being widened or where pipes are being replaced at multiple crossings are considered to have independent utility, and each crossing would be considered eligible for a separate 12- SPGP -01 authorization (impacts are not considered cumulatively for permitting, but are considered cumulatively when assessing the need for federal review). 6. Multiple general permit authorizations. The 12- SPGP -01 may be combined with other Corps general permits (including Nationwide, Regional or Letters of Permission) as long as the impacts are considered cumulatively and do not exceed the acreage limit or linear foot limits of the 12- SPGP -01. Two separate activities (e.g., Activity A and B), within 12- SPGP -01, may be combined as long as they do not exceed the acreage or linear footage threshold of the activity with the highest specified acreage or linear footage threshold. 7. Permit on -site. The permittee shall ensure that a copy of 12- SPGP -01 and the accompanying authorization letter are at the work site at all times. These copies must be made available to any regulatory representative upon request. Although the permittee may assign various aspects of the work to different contractors or sub - contractors, all contractors and sub- contractors shall be expected to comply with all conditions of any 12- SPGP -01 authorization. General Conditions Related to other federal laws or programs: 8. Historic Properties. Any activity authorized shall comply with Section 106 of the National Historic Preservation Act. If the permittee, during construction or work authorized herein, encounters a previously unidentified archaeological or other cultural resource, he /she must immediately stop work and notify the Corps and the VDEQ of what has been found. Coordination with the Virginia Department of Historic Resources will commence and the permittee will subsequently be advised when he /she may recommence work. 9. Tribal Rights. No activity authorized may impair reserved tribal rights, including, but not limited to, reserved water rights, treaty fishing and hunting rights. 10. Federal Lands. Authorized activities shall not impinge upon the value of any National Wildlife Refuge, National Forest, National Park, or any other area administered by the FWS, U.S. Forest Service, or National Park Service unless approval from the applicable land management agency is provided with the permit application. 11. Endangered Species. No activity is authorized under this 12- SPGP - Olwhich may affect a proposed/listed threatened or endangered species or proposed/listed critical habitat (as identified under the Federal Endangered Species Act (ESA)), is likely to jeopardize the continued existence of such species or which will destroy or adversely modify the critical habitat of such species unless Section 7 consultation addressing the effects of the proposed activity has been completed. a. Federal agencies should follow their own procedures for complying with the requirements of the ESA. Federal permittees must provide the VDEQ and Corps with the appropriate documentation to demonstrate compliance with those requirements. b. Non - federal permittees shall notify the VDEQ and Corps if any listed species or designated critical habitat might be affected or is in the vicinity of the project, or if the project is located in designated critical habitat, and shall not begin work on the activity until notified by the VDEQ or Corps that the requirements of the ESA have been satisfied and that the activity is authorized. Information on the location of threatened and endangered species and their critical habitat can be obtained directly from the USFWS at: http: / /www.fws.gov/ northeast / virginiafield / endspecies /Project_Reviews.html and/or NOAA Fisheries Habitat Conservation Division, P.O. Box 1346, 7580 Spencer Road, Gloucester Point, VA 23062. c. Section 7 coordination will be performed in accordance with the NAO ESA Review Process. The applicant may not begin work until the VDEQ or Corps has notified them that the Section 7 consultation has been completed. d. As a result of formal or informal consultation with the FWS or NOAA Fisheries the Corps District Commander may add species - specific regional endangered species conditions to the 12- SPGP -01. e. Authorization of an activity by 12- SPGP -01 does not authorize the "take" of a threatened or endangered species as defined under the ESA. In the absence of separate authorization (e.g., an ESA Section 10 Permit, a Biological Opinion with "incidental take" provisions, etc.) from the FWS or the NOAA Fisheries, both lethal and non - lethal "takes" of protected species are in violation of the ESA. 12. Bald and Golden Eagle Protection Act. The bald eagle (Haliaeetus leucocephalus) is no longer a federally listed threatened or endangered species; therefore, the Endangered Species Act provisions are not applicable to this species. The Bald and Golden Eagle Protection Act ( BGEPA) does not require that a federal agency involved in permitting the proposed action conduct coordination. The coordination under the BGEPA is the responsibility of the applicant. The applicant should either obtain a FWS bald eagle take permit or a letter of concurrence from FWS indicating that a permit is not necessary prior to initiating construction activities. You should contact FWS concerning this matter at U.S. Fish and Wildlife Service, Virginia Field Office, ATTN: Kim Smith, 6669 Short Lane, Gloucester, VA 23061. Information on active bald eagle nests in the project area can be obtained via The Center for Conservation Biology (CCB) Virginia Eagles Nest Locator: httn: / /www.ccb- wm.org /vir ing iaeagles /index.htm. 13. Wild and Scenic Rivers. Currently, there are no designated Wild and Scenic Rivers in the Commonwealth of Virginia; however, the portion of the Upper New River from Glen Lyn, Virginia to the West Virginia/Virginia state line was designated a "study river" by Congress on October 26, 1992. No activity may occur in a component of the National Wild and Scenic River System, or in a river officially designated by Congress as a "study river" for possible inclusion in the system, while the river is in an official study status, unless the appropriate Federal agency with direct management responsibility for such river has determined, in writing, that the proposed activity will not adversely affect the Wild and Scenic River designation or study status. Information on Wild and Scenic Rivers may be obtained from the appropriate Federal land management agency in the area (e.g., National Park Service, U.S. Forest Service, Bureau of Land Management, U.S. Fish and Wildlife Service). Impacts that occur in these resource areas will require coordination with the appropriate Federal agency. 14. Department of Defense (DOD) Siting Clearinghouse Coordination. For all commercial and institutional development projects that include the construction of wind energy generating structures, solar towers, or overhead powerlines the VDEQ must coordinate the project with the DOD Clearinghouse. The VDEQ will send a copy of the joint permit application and SPGP authorization to the following address: Department of Defense Clearinghouse, Attn: Mr. Marshal Williams and Mr. Davis Blalock, 101 Marietta St., NW, Suite 3120, Atlanta, George 30303 or via email to: Frederick. m.williams2 8. civ(2mail.mil and David. c.blalock2. civgmail. mil. 15. Federal navigation projects. Authorized activities may not interfere with any existing or proposed Federal navigation projects. 16. Navigation. (a) No authorized activity may cause more than a minimal adverse effect on navigation. (b) The permittee understands and agrees that if future operations by the United States require the removal, relocation, or other alteration of the structure or work herein authorized, or if, in the opinion of the Secretary of the Army or his /her authorized representative, said structure or work shall cause unreasonable obstruction to the free navigation of the navigable waters, the permittee will be required, upon due notice from the Corps, to remove, relocate, or alter the structural work or obstructions caused thereby, without expense to the United States. No claim shall be made against the United States on account of any such removal or alteration. 17. Floodplains. All practicable efforts shall be made to conduct the work authorized by 12- SPGP -01 in a manner so as to avoid any adverse impact on the Federal Emergency Management Agency (FEMA) designated 100 -year floodplain. 18. Real estate. Activities authorized under 12- SPGP -01 do not grant any Corps or Federal real estate rights. If real estate rights are needed from the Corps, you must contact the Corps Real Estate Office at (75 7) 201 -7735 or at the address listed on the front page of this permit. 19. Environmental justice. Activities authorized under 12- SPGP -01 must comply with Executive Order 12898, "Federal Actions to Address Environmental Justice in Minority Populations and Low - Income Populations ". 20. Federal liability. In issuing 12- SPGP -01, the Federal government does not assume any liability for the following: (a) damages to the permitted project or uses thereof as a result of other permitted or unpermitted activities or from natural causes; (b) damages to the permitted project or uses thereof as a result of current or future activities undertaken by or on behalf of the United States in the public interest; (c) damages to persons, property, or to other permitted or 10 unpermitted activities or structures caused by the activity authorized by 12- SPGP -01; (d) design or construction deficiencies associated with the permitted work; (e) damage claims associated with any future modification, suspension, or revocation of this permit. General Conditions Related to Minimizing Environmental Impacts: 21. Avoidance and minimization. Except as provided under section 404(b)(2), no discharge of dredged or fill material shall be permitted if there is a practicable alternative to the proposed discharge which would have less adverse impact on the aquatic ecosystem, so long as the alternative does not have other significant adverse environmental consequences. (40 CFR 230.10(a) Section 404 (b)(1) Guidelines). 22. Mitigation standards. a. Wetland mitigation will generally be required for all residential, commercial, and institutional development projects where the total permanent impacts exceed 1 /10 acre AND for all impacts on linear transportation projects. Generally, the minimum required wetland mitigation ratios will be as follows: 2:1 for forested wetlands, 1.5:1 for scrub -shrub wetlands, 1: for herbaceous emergent wetlands, and 1:1 for conversion of forested wetlands to herbaceous emergent wetlands. Mitigation for open waters impacts will be determined by the project manager on a case -by -case basis. All wetland mitigation will comply with the Corps -EPA Compensatory Mitigation for Losses of Aquatic Resources dated April 10, 2008 (33 CFR 325 and 332/40 CFR 230). b. Stream mitigation will generally be required for all residential, commercial, institutional developments AND linear transportation projects where the total permanent stream channel impacts exceed 300 linear feet. Minimum stream mitigation requirements will be determined using the current Corps and the VDEQ endorsed assessment methodology. All stream mitigation will comply with Corps -EPA Compensatory Mitigation for Losses of Aquatic Resources dated April 10, 2008 (33 CFR 325 and 332; 40 CFR 230). c. For the purposes of the 12- SPGP -01, definitions for enhancement, establishment (creation), preservation, and re- establishment will be consistent with the definitions listed in the Corps -EPA Compensatory Mitigation for Losses of Aquatic Resources dated April 10, 2008 (33 CFR 325 and 332; 40 CFR 230). d. Where local zoning ordinances provide for riparian and floodplain protection pursuant to the Chesapeake Bay Preservation Act (Virginia Code 10.1 -2100 et seq.) and the Chesapeake Bay Preservation Area Designation and Management Regulations(9 VAC 1 -20 et seq. ), the use of buffers as a form of compensatory mitigation shall be allowed only (a) where the extent of the buffer exceeds the lateral extent already required by local ordinances pursuant to the Act and the regulations or (b) where the quality of the existing protected buffer area is enhanced to provide greater water quality protection benefits. 23. Heavy equipment working in wetlands must be placed on mats, or other measures must be taken to minimize soil disturbance. 11 24. Temporary fills. All temporarily disturbed waters and wetlands must be restored to their pre - construction contours within 6 months of commencing the temporary impact's construction. Impacts that will not be restored within 6 months (calculated from the start of the temporary impacts construction) will be considered permanent unless otherwise approved by the 12 -SPGP- 01. Once restored to their natural contours, soil in these areas must be mechanically loosened to a depth of 12 inches and wetland areas must be seeded or sprigged with appropriate native vegetation. 25. Sedimentation and erosion control. Appropriate erosion and sediment controls must be employed and maintained in effective operating condition during construction, and all exposed soil and other fills, as well as any work below the ordinary high water mark, must be permanently stabilized at the earliest practicable date. 26. Aquatic life movements. Following consultation with the Virginia Department of Game and Inland Fisheries (DGIF), the Norfolk District has determined that fish and other aquatic organisms are most likely present in any stream being crossed, in the absence of site - specific evidence to the contrary. Although prospective permittees have the option of providing such evidence, extensive efforts to collect such information is not encouraged, since countersinking will in most cases be required with some exceptions as outlined below: a. Pipes should be adequately sized to allow for the passage of ordinary high water with the countersinking and invert restrictions taken into account. b. All pipes and culverts placed in streams will be countersunk at both the inlet and outlet ends, unless indicated otherwise by the Norfolk District on a case -by -case basis (see below). Pipes that are 24" or less in diameter shall be countersunk 3" below the natural stream bottom. Pipes that are greater than 24" in diameter shall be countersunk 6" below the natural stream bottom. The countersinking requirement does not apply to bottomless pipes /culverts or pipe arches. All single pipes or culverts (with bottoms) shall be depressed (countersunk) below the natural streambed at both the inlet and outlet of the structure. In sets of multiple pipes or culverts (with bottoms) at least one pipe or culvert shall be depressed (countersunk) at both the inlet and outlet to convey low flows. c. Extensions and certain maintenance: The requirement to countersink does not apply to extensions of existing pipes or culverts that are not countersunk, or to maintenance to pipes /culverts that does not involve replacing the pipe /culvert (such as repairing cracks, adding material to prevent/correct scour, etc.). d. Floodplain pipes: The requirement to countersink does not apply to pipes or culverts that are being placed above ordinary high water, such as those placed to allow for floodplain flows. The placement of pipes above ordinary high water is not jurisdictional (provided no fill is discharged into wetlands). e. Pipes on bedrock or above existing utility lines: Different procedures will be followed for pipes or culverts to be placed on bedrock or above existing buried utility lines where it is not 12 practicable to relocate the lines, depending on whether the work is for replacement of an existing pipe /culvert or a new pipe /culvert: i. Replacement of an existing pipe /culvert: Countersinking is not required provided the elevations of the inlet and outlet ends of the replacement pipe /culvert are no higher above the stream bottom than those of the existing pipe /culvert. Documentation (photographic or other evidence) must be maintained in the permittee's records showing the bedrock condition and the existing inlet and outlet elevations. That documentation will be available to the Norfolk District upon request, but notification or coordination with the Norfolk District is not otherwise required. ii. Replacement in a new location: If the prospective permittee determines that bedrock or an existing buried utility line that is not practicable to relocate prevents countersinking, he /she should evaluate the use of a bottomless pipe /culvert, bottomless utility vault, span (bridge) or other bottomless structure to cross the waterway, and also evaluate alternative locations for the new pipe /culvert that will allow for countersinking. If the prospective permittee determines that neither a bottomless structure nor an alternative location is practicable, then he /she must submit a pre - construction notification (PCN) to the Norfolk District in accordance with General Condition 31 of the NWPs. In addition to the information required by General Condition 31, the prospective permittee must provide documentation of measures evaluated to minimize disruption of the movement of aquatic life as well as documentation of the cost, engineering factors, and site conditions that prohibit countersinking the pipe /culvert. Options that must be considered include partial countersinking (such as less than 3" of countersinking, or countersinking of one end of the pipe), and constructing stone step pools, low rock weirs downstream, or other measures to provide for the movement of aquatic organisms. The PCN must also include photographs documenting site conditions. The prospective permittee may find it helpful to contact his/her regional fishery biologist for the Virginia Department of Game and Inland Fisheries ( VDGIF), for recommendations about the measures to be taken to allow for fish movements. When seeking advice from VDGIF, the prospective permittee should provide the VDGIF biologist with all available information such as location, flow rates, stream bottom features, description of proposed pipe(s), slopes, etc. Any recommendations from VDGIF should be included in the PCN. The Norfolk District will notify the prospective permittee whether the proposed work qualifies for the nationwide permit within 45 days of receipt of a complete PCN. NOTE: Blasting of stream bottoms through the use of explosives is not acceptable as a means of providing for countersinking of pipes on bedrock. E Pipes on steep terrain: Pipes being placed on steep terrain (slope of 5% or greater) must be countersunk in accordance with the conditions above and will in most cases be non - reporting. It is recommended that on slopes greater than 5 %, a larger pipe than required be installed to allow for the passage of ordinary high water in order to increase the likelihood that natural velocities can be maintained. There may be situations where countersinking both the inlet and outlet may result in a slope in the pipe that results in flow velocities that cause excessive scour at the outlet and/or prohibit some fish movement. This type of situation could occur on the side of a mountain where falls and drop pools occur along a stream. Should this be the case, or should the prospective permittee not want to countersink the pipe /culvert for other reasons, he /she must submit a Pre - Construction Notification to the Norfolk District in accordance with General Condition 31 of the Nationwide Permits. In addition to the information required by General 13 Condition 31, the prospective permittee must provide documentation of measures evaluated to minimize disruption of the movement of aquatic life as well as documentation of the cost, engineering factors, and site conditions that prohibit countersinking the pipe /culvert. The prospective permittee should design the pipe to be placed at a slope as steep as stream characteristics allow, countersink the inlet 3 -6 ", and implement measures to minimize any disruption of fish movement. These measures can include constructing a stone step /pool structure, preferably using river rock/native stone rather than riprap, constructing low rock weirs to create a pool or pools, or other structures to allow for fish movements in both directions. Stone structures should be designed with sufficient -sized stone to prevent erosion or washout and should include keying -in as appropriate. These structures should be designed both to allow for fish passage and to minimize scour at the outlet. The quantities of fill discharged below ordinary high water necessary to comply with these requirements (i.e., the cubic yards of stone, riprap or other fill placed below the plane of ordinary high water) must be included in project totals. The prospective permittee may find it helpful to contact his/her regional fishery biologist for the Virginia Department of Game and Inland Fisheries (DGIF), for recommendations about the measures to be taken to allow for fish movements. When seeking advice from DGIF, the prospective permittee should provide the DGIF biologist with all available information such as location, flow rates, stream bottom features, description of proposed pipe(s), slopes, etc. Any recommendations from DGIF should be included in the PCN. The Norfolk District will notify the prospective permittee whether the proposed work qualifies for the nationwide permit within 45 days of receipt of a complete PCN. g. Problems encountered during construction: When a pipe /culvert is being replaced, and the design calls for countersinking at both ends of the pipe /culvert, and during construction it is found that the streambed/banks are on bedrock, then the permittee must stop work and contact the Norfolk District (contact by telephone and/or email is acceptable). The permittee must provide the Norfolk District with specific information concerning site conditions and limitations on countersinking. The Norfolk District will work with the permittee to determine an acceptable plan, taking into consideration the information provided by the permittee, but the permittee should recognize that the Norfolk District could determine that the work will not qualify for a nationwide permit. h. Emergency pipe replacements: In the case of an emergency situation, such as when a pipe /culvert washes out during a flood, a permittee is encouraged to countersink the replacement pipe at the time of replacement, in accordance with the conditions above. However, if conditions or timeframes do not allow for countersinking, then the pipe can be replaced as it was before the washout, but the permittee will have to come back and replace the pipe /culvert and countersink it in accordance with the guidance above. In other words, the replacement of the washed out pipe is viewed as a temporary repair, and a countersunk replacement should be made at the earliest possible date. The Norfolk District must be notified of all pipes /culverts that are replaced without countersinking at the time that it occurs, even if it is an otherwise non - reporting activity, and must provide the permittee's planned schedule for installing a countersunk replacement (it is acceptable to submit such notification by email). The permittee should anticipate whether bedrock or steep terrain will limit countersinking, and if so, should follow the procedures outlined in (f) and/or (g) above. 14 27. Discharge of pollutants. All authorized activities involving any discharge of pollutants into waters of the United States shall be consistent with applicable water quality standards, effluent limitations, standards of performance, prohibitions, and pretreatment standards and management practices established pursuant to the CWA (33 U.S.C. § 1251 et seq.) and applicable state and local laws. No discharge of dredged or fill material in association with this authorization may consist of unsuitable material such as trash, debris, car bodies, asphalt, etc. 28. Obstruction of high flows. Discharges of dredged or fill material must not permanently restrict or impede the passage of normal or expected high flows. 29. Waterbird breeding areas. Discharges of dredged or fill material into breeding areas for migratory waterfowl must be avoided to the maximum extent practicable. 30. Native trout and anadromous fishes. Authorizations for discharges of dredged or fill material into native trout waters or anadromous fish spawning areas are conditioned to limit in- stream work within the timeframes recommended by the DGIF. 31. Water supply intakes. No discharge of dredged or fill material may occur in proximity of a public water supply intake. 32. Invasive Species. Plant species on the most current Virginia Department of Conservation and Recreation's Invasive Alien Plant List shall not be used for replanting activities authorized by the SPGP. The list of invasive plants in Virginia may be found at: http: / /www.dcr.virginia.gov /natural heritage /documents /invlist.pdf. General Procedural Conditions: 33. Inspections. The permittee understands and agrees that the Corps and/or the VDEQ are permitted and allowed to make periodic inspections at any time the Corps or VDEQ deems necessary in order to assure that the activities being performed under authority of this permit are in accordance with the terms and conditions prescribed herein. The Corps reserves the right to require post - construction engineering drawings and/or surveys of any work authorized underl2- SPGP -01, as deemed necessary on a case -by -case basis. 34. Maintenance. The permittee shall maintain the work authorized herein in good condition and in conformance with all terms and conditions of this permit. All fills shall be properly maintained to ensure public safety. 35. Property rights.12- SPGP -01 does not convey any property rights, either in real estate or material, or convey any exclusive privileges, nor does it authorize any injury to property or invasion of rights or any infringement of Federal, state, or local laws or regulations. 36. Modification, suspension, and revocation.12- SPGP -01 and individual verificationsunderl 2-SPGP-0 I maybe either modified, suspended, or revoked in whole or in part pursuant to the policies and procedures of 33 C.F.R. § 325.7. Any such action shall notbe the basis for any claim for damages against the United States. 15 37. Restoration directive. The permittee, upon receipt of a restoration directive, shall restore the waters of the United States to their former conditions without expense to the United States and as directed by the Secretary of the Army or his/her authorized representative. If the permittee fails to comply with such a directive, the Secretary or his /her designee, may restore the waters of the United States to their former conditions, by contract or otherwise, and recover the cost from the permittee. 38. Special conditions. The Corps may impose other special conditions on a project authorized pursuant to 12- SPGP -01 that are determined necessary to minimize adverse navigational and/or environmental effects or based on any other factor of the public interest. Failure to comply with all conditions of the authorization, including special conditions, constitutes a permit violation and may subject the permittee, or his/her contractor, to criminal, civil, or administrative penalties and/or restoration. 39. False or incomplete information. In granting authorization pursuant to this permit, the Corps has relied upon information and data provided by the permittee. If, subsequent to notification by the Corps or the VDEQ that a project qualifies for this permit, such information and data prove to be materially false or materially incomplete, the Corps may suspend or revoke authorization, in whole or in part, and/or the United States or Corps may institute appropriate legal proceedings. 40. Abandonment. If the permittee decides to abandon the activity authorized underl2- SPGP -01, unless such abandonment is merely the transfer of property to a third party, he /she may be required to restore the area to the satisfaction of the Corps. 41. Transfer of authorization. In order to transfer authorization underl2- SPGP -01, the transferee and permittee must supply the Corps and the VDEQ with a written and signed, by all appropriate parties, request to make such a transfer. Such transfer is not effective until written approval has been granted by the Corps or the VDEQ. 42. Binding effect. The provisions of the permit authorization shall be binding on any assignee or successor in interest of the original permittee. General Conditions Re2ardins Duration of Authorizations: 43. Duration of authorization. Activities authorized underl2- SPGP -01 must be completed by May 31, 2017. 44. Time extensions. If a permittee is unable to complete the work authorized underl2- SPGP -01 in the time limit provided in the initial authorization, he /she must submit a request for a time extension to the Corps and the VDEQ for consideration at least one month prior to the expiration of the permit authorization. 16 45. Expiration ofl2- SPGP -01. Unless further modified, suspended, or revoked, 12 -SPGP- 01 will be in effect until May 31, 2017.Upon expiration, it may be considered for revalidation. Activities which have commenced (i.e., are under construction) or are under contract to commence construction in reliance upon 12- SPGP -01 will remain authorized provided the activity is completed within twelve months of the date of this I2- SPGP -0I's expiration of May 31, 2017, unless discretionary authority has been exercised on a case -by -case basis to modify, suspend, or revoke the authorization in accordance with 33 CFR 325.7(a -e). Date PAUL B. OLSEN, P.E. Colonel, Corps of Engineers Commanding 17