HomeMy WebLinkAboutWPO201400068 Review Comments WPO VSMP 2014-10-07� OF AL
,. vIRGINIP
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902 -4596
Phone(434)296 -5832 Fax(434)972 -4126
Project title:
Project file number:
Plan preparer:
Owner or rep.:
Plan received date:
Date of comments:
Reviewers:
VSMP Permit plan review
Farmington Country Club South Side Improvements
WP0201400068
W &W Assoc. [email]
Joseph Krenn, COO General Manager Ukrenn @fccva.com]
25 August 2014
7 October 2014
Max Greene, Michelle Roberge
County Code section 17 -410 and Virginia Code §62.1- 44.15:34 requires the VSMP authority to act on
any VSMP permit by issuing a project approval or denial. This project is denied. The rationale is
given in the comments below. The application may be resubmitted for approval if all of the items
below are satisfactorily addressed. No additional fee is required for resubmittal. The VSMP
application content requirements can be found in County Code section 17 -401.
Stormwater Pollution Prevention Plan ( SWPPP)
The SWPPP content requirements can be found in County Code section 17 -405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Please provide a copy of the DEQ Coverage Letter with the expiration date of June 30, 2019.
2. The plan must demonstrate compliance with quality and quantity requirements using the Runoff
Reduction Method. Please use the VRRM spread sheet from VDEQ.
A. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17 -404.
1. A PPP was not found. Please submit a Pollution Prevention Plan (PPP) for review. Requirements can be
found in County Code 17 -404.
B. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25- 870 -108 requires the VSMP authority to approve or disapprove a SWMP.
This plan is disapproved, and the reasons are provided in the comments below. The stormwater
management plan content requirements can be found in County Code section 17 -403.
WPO (WP02014000068)
1) Show soil map of site.
2) The drainage area A table on sheet C -13 shows a BMP practice to a rain garden #2. The plan does not
show a rain garden. Please clarify if you are proposing a rain garden.
Engineering Review Comments
Page 2 of 3
3) The sloped area south of the proposed parking lot all drain to the biofilter, but only .5 acres is shown
going to the bioretention practice. It appears more than .5 acres will drain to biofilter. Please revise.
4) Add this note on C -12 for biofilter mix. "Tested for acceptable phosphorus index between 10 and 30
or between 7 and 23 mg/kg of P in soil media."
5) Submit perc rate for biofilter area. (One per 1,000 sq ft of filter surface). Also, verify that the bottom
of #57 aggregate is 2' above seasonably high water table.
6) Label underdrain with Schedule 40 PVC with cleanouts. Show 12" depth for #57 aggregate.
7) The geometry of basin does not meet spec of bioretention design criteria. Short circuiting should be
prevented. Please revise.
8) Show the 2' gravel diaphragm level spreader at pretreatment area. On profile view, show the lip on
level spreader.
9) I recommend moving the curb cut location away from the corner of parking lot and shifting layout of
gravel spreader to enter far east side of biofilter.
10) Two rip rap strips are shown on plan, but only one profile view is shown. Please show both since one
is from sidewalk and the other from the culvert under the golf cart path. My concern is that #57 stones
will wash away at steeper slopes. The detail shown is for sheet flows off pavement, then into a
pretreatment area that is flat. Please clarify design since the detail has been modified.
11) The water quantity analysis for channel protection should show the actual drainage area to the point of
analysis, such as drainage area A, B, C and existing areas. The CN should be different to drainage area
D. The spreadsheet shows how much phosphorus to remove, but channel analysis cannot be
determined by the separate disturbed drainage areas alone since the CN is not correct.
12) Please clarify the total drainage area to pond. It appears to be larger than what is shown.
13) Clarify the surface elevation of the bioretention area. The profile shows 607, but the plan view shows
606.
14) Relabel bioretention facility #2 under the Bioretention Facility sizing calculations. It should be
bioretention facility #1.
15) Submit a Pollution Prevention Plan and a Stormwater Pollution Prevention Plan.
Sincerely,
MQJ/T-
Michelle Roberge
C. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1- 44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This
plan is disapproved, and the reasons are provided in the comments below. The erosion control plan
content requirements can be found in County Code section 17 -402.
1. Sediment trap outlet needs to be extended to the bottom of the slope /disturbed soil area to prevent
Engineering Review Comments
Page 3 of 3
additional sediment loss during trap overflows.
Paved construction entrance detail needs to be on the plan. The Albemarle County Temporary Paved
Construction Entrance detail can be found in the County Design Standards Manual.
Please remove the bio- filter components from the E &SC plan sheets. Bio- filter components should be
shown on the SWM pages.
The VSMP permit application and all plans may be resubmitted for approval when all comments have been
satisfactorily addressed. For re- submittals please provide 2 copies of the complete permit package with a
completed application form.
Engineering plan review staff are available from 2 -4 PM on Thursdays, should you require a meeting to discuss
this review.
Process;
After approval, plans will need to bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will prepare
estimates and check parcel and easement information based on the approved plans. The County's Management
Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted
along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved
and signed by the County Attorney and County Engineer. This may take 2 -4 weeks to obtain all the correct
signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The
County's Management Analyst or other staff will prepare the forms and check for ownership and signature
information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local VSMP
authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the
state. For fastest processing, this is done electronically with the emails provided on the application. DEQ
should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will
issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre - construction conference.
Applicants will need to complete the request for a pre - construction conference form, and pay the remainder of
the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to
be paid. This will be checked by county staff, and upon approval, a pre - construction conference will be
scheduled with the County inspector. At the pre - construction conference, should everything proceed
satisfactorily, a joint VSMP and grading permit will be issued by the County so that work may begin.
County forms can be found on the county website forms center under engineering;
http:/ /www.albemarle.orWdeptforms.asp ?department= cdengwpo
File: E1_vsmp_review_projectname.doc