SWPPP /PPP review
Project: The Miller School of Albemarle — New Entrance
Plan preparer: Tim Miller, Meridian Planning Group, LLC, 1413 Sachem Place, Suite 1,
Charlottesville, VA 22903 [ tmiller(&meridianwbe.com ]
Owner or rep.: Miller School of Albemarle, 1000 Samuel Miller Loop,
Charlottesville, VA 22903
Plan received date: 22 Dec 2014
Date of comments: 26 Jan 2014, Accepted /Adequate
Reviewer: John Anderson
I have completed engineering review for WP0201400105, SWPPP/PPP (associated with WP02012- 00049). These
plans are accepted. Please note: on -site version of SWPPP/PPP must include documents sent as e- attachments from
Meridian Planning Group to ACCD /Engineering, 26- Jan -2015. On -site copy should be identical with copy on file,
evaluated accepted/adequate. In the future, SWPPP /PPP should reflect modifications, updates, etc as required by
General VPDES permit to be issued for this project. (Ref. VAR10, Part II.B.) Please furnish copy of General
VPDES Permit Coverage Letter, when received from VDEQ.
Process / Next steps:
County staff will need to enter project information in a DEQ database for state application processing. DEQ will
review the application information based on local VSMP authority approval. At this time, the DEQ portion of the
application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the
emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ
approves the application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre - construction conference. Applicants
will need to complete the request for a pre - construction conference form, and pay the remainder of the application
fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be
checked by county staff, and upon approval, a pre - construction conference will be scheduled with the County
inspector. At the pre - construction conference, should everything proceed satisfactorily, a joint VSMP and grading
permit will be issued by the County so that work may begin.
County forms can be found on the county website forms center under engineering;
http://www.albemarle.org/deptforms.asp?department--cdengmTo
File: WP0201400105- Miller School of Albemarle New Entrance SWPPP 012615