August 12, 2004
Valerie Long
McGuire Woods, LLP
Court Square Building
310 4th Street
Charlottesville, VA 22902
RE: SP-2004-012 Verulam Farm Conservation Group (LLC/Nextel Partners) (Sign #85,86)
Tax Map 74, Parce3117
Dear Ms. Long:
On July 14, 2004, the Albemarle County Board of Supervisors took action on SP-2004-012 to allow
to allow construction of a personal wireless service fac w/wooden monopole, approx 101 feet in total
height & 10 feet above height of tallest tree within 25 feet. The proposed facility would include flush-
mounted panel antennas & ground equipment stored in a 200 square foot building. This application is
being made in accord with Section 1 0.2.2.6 of the Zoning Ordinance which allows for microwave & radio-
wave transmission & relay towers in the RA zoning district. This special use permit was approved based
on the following conditions:
The facility shall be desiqned. constructed and maintained as follows:
1. With the exception of any minor changes that would be required in order to comply with the
conditions listed herein, the facility including the monopole, the ground equipment building, and
any antennas shall be sized, located and built as shown on the concept plan entitled, "SP-004-012
- Nextel PartnershipNerulam Farm Conservation Group LLC/Meechum", last revised May 25,
2004 and provided with Attachment A;
2. The calculation of pole height shall include any base, foundation or grading that raises the pole
above the pre-existing, natural ground elevation;
3. The top of the pole, as measured Above Mean Sea Level (AMSL), shall never exceed seven (10)
feet above the top of the tallest tree within twenty-five (25) feet. In no case shall the pole exceed
one hundred one (101) feet in total height at the time of installation without prior approval of an
amendment to this special use permit or personal wireless facility permit;
4. The monopole shall be made of wood and be a dark brown natural wood color;
5. The ground equipment building, antennas, concrete pad and all equipment attached to the pole
shall be the same color as the pole and shall be no larger than the specifications set forth in the
application plans;
6. Only flush-mounted antennas shall be permitted. No antennas that project out from the pole
beyond the minimum required by the support structure shall be permitted. However, in no case
shall the distance between the face of the pole and the faces of the antennas be more than twelve
(12) inches;
7. No satellite or microwave dishes shall be permitted on the monopole;
e
e
8. No antennas or equipment, with the exception of a grounding rod, not to exceed one (1)-inch in
diameter and twelve (12) inches in height, shall be located above the top of the pole;
9. No guy wires shall be permitted;
10. No lighting shall be permitted on the site or on the pole, except as herein provided. Outdoor
lighting shall be limited to periods of maintenance only. Each outdoor luminaire shall be fully
shielded such that all light emitted is projected below a horizontal plane running though the lowest
part of the shield or shielding part of the luminaire. For the purposes of this condition, a luminaire
is a complete lighting unit consisting of a lamp or lamps together with the parts designed to
distribute the light, to position and protect the lamps, and to connect the lamps to the power
supply;
11. The permittee shall comply with section 5.1.12 of the Zoning Ordinance. Fencing of the lease
area shall not be permitted;
12. Size specifications and other details, including schematic elevations of the antennas shall be
included in the construction plan package;
13. Site grading and all construction around the facility shall be minimized to only provide the amount
of space that will be necessary for placement of the monopole and equipment building; and
14. Details and cross sections for any future plans to upgrade the existing dirt logging road shall be
subject to review and approval by the County's Engineering Department
Prior to the issuance of a buildinq permit. the followinq requirements shall be met:
15. Certification by a registered surveyor stating the height of the reference tree that has been used
to justify the height of the monopole shall be provided to the Zoning Administrator;
16. Prior to beginning construction or installation of the pole, the equipment cabinets or vehicular or
utility access, an amended tree conservation plan, developed by a certified arborist shall be
submitted to the Zoning Administrator for approval. The plan shall specify tree protection
methods and procedures, and identify any existing trees to be removed on the site - both inside
and outside the access easement and lease area. All construction or installation associated with
the pole and equipment pad, including necessary access for construction or installation, shall be
in accordance with this tree conservation plan. Except for the tree removal expressly authorized
by the Director of Planning and Community Development, the permittee shall not remove existing
trees within two hundred (200) feet of the pole and equipment pad. A special use permit
amendment shall be required for any future tree removal within the two hundred (200)-foot buffer,
after the installation of the subject facility; and
17. With the building permit application, the applicant shall submit the final revised set of site plans for
construction of the facility. During the review of the application, Planning staff shall review the
revised plans to ensure that all appropriate conditions of the special use permit have been
addressed.
After the completion of the pole installation and prior to the issuance of a Certificate of Occupancy or to
any facilitv operation. the followinq shall be met:
18. Certification by a registered surveyor stating the height of the pole, measured both in feet above
ground level and in elevation above sea-level (ASL) using the benchmarks or reference datum
identified in the application shall be prOVided to the Zoning Administrator;
19. Certification confirming that the grounding rods: a) height does not exceed two (2) feet above the
monopole; and, b) width does not exceed a diameter of one (1 )-inch, shall be provided to the
Zoning Administrator; and
20. No slopes associated with construction of the facility shall be created that are steeper than 2: 1
unless retaining walls, revetments, or other stabilization measures acceptable to the County
Engineer are employed.
After the issuance of a Certificate of Occupancy. the followinq requirements shall be met:
21. The applicant, or any subsequent owners of the facility, shall submit a report to the Zoning
Administrator by July 1 of each year. The report shall identify each personal wireless service
provider that uses the facility, including a drawing indicating which equipment, on both the tower
and the ground, are associated with each provider; and
22. All equipment and antennae from any individual personal wireless service provider shall be
disassembled and removed from the site within ninety (90) days of the date its use is
discontinued. The entire facility shall be disassembled and removed from the site within ninety
(90) days of the date its use for personal wireless service purposes is discontinued. If the Zoning
Administrator determines at any time that surety is required to guarantee that the facility will be
removed as required, the permittee shall furnish to the Zoning Administrator a certified check, a
e
e
bond with surety satisfactory to the County, or a letter of credit satisfactory to the County, in an
amount sufficient for, and conditioned upon, the removal of the facility. The type of surety
guarantee shall be to the satisfaction of the Zoning Administrator and the County Attorney.
Please be advised that although the Albemarle County Board of Supervisors took action on the
project noted above, no uses on the property may lawfully begin until all applicable approvals
have been received and conditions have been met. This includes compliance with:
. conditions of the SPECIAL PERMIT; and
. approval of a ZONING COMPLIANCE CLEARANCE.
In the event that the use, structure or activity for which this special use permit is issued is not commenced
within twenty-four (24) months from the date of Board approval, it shall be deemed abandoned and the
permit terminated. The term "commenced" means "construction of any structure necessary to the use of
the permit."
If you have questions or comments regarding the above-noted action, please do not hesitate to contact
Keith Lancaster at 296-5832.
Sincerely,
"