County Code section 17 -410 and Virginia Code §62.1- 44.15:34 requires the VSMP authority to act on any
VSMP permit by issuing a project approval or denial. This project is Approved. The rationale is given in
the comments below. The VSMP application content requirements can be found in County Code section
17 -401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17 -405. A SWPPP must contain
(1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Existing SWPPP plan will be updated with this information.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17 -404.
1. Existing PPP plan will be updated with this information.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25- 870 -108 requires the VSMP authority to approve or disapprove a SWMP.
This plan is approved, and the reasons are provided in the comments below. The stormwater management
plan content requirements can be found in County Code section 17 -403.
1. No changes to the existing SWM plan is proposed with this modification
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1- 44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan
is approved, and the reasons are provided in the comments below. The erosion control plan content
requirements can be found in County Code section 17 -402.
The modification can be approved with the addition of the Storm Drain Inlet Protection, Std. & Spec. 3.07 to the
inlet of the new M -1 manhole structure. The inlet protection will be installed with each lifting of the manhole
structure top section. A stone filter ring may be required by the VSMP inspector if excessive sediment is
documented leaving the outlet pipe. A detail of the inlet protection has been added to the approved plans sets.
County forms can be found on the county website forms center under engineering;
h!Ltp://www.albemarle.ora/deptfonns.asp?department=cdengzMo
File: CDDEI_vsmp_review_5th Street Station modification of basin #3_wpo201500017.doc
VSMP Permit plan review
Project title:
5t' Street Station Modification of basin #3 outlet system
Project file number:
WP0201500017
Plan preparer:
Bohler Engineering [dhines @bohlereng.com]
Owner or rep.:
AVON HOLDINGS LLC [steve @sjcollinsent.com]
Plan received date:
25 March 2015
Date of comments:
27 March 2015
Reviewers:
Max Greene
County Code section 17 -410 and Virginia Code §62.1- 44.15:34 requires the VSMP authority to act on any
VSMP permit by issuing a project approval or denial. This project is Approved. The rationale is given in
the comments below. The VSMP application content requirements can be found in County Code section
17 -401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17 -405. A SWPPP must contain
(1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Existing SWPPP plan will be updated with this information.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17 -404.
1. Existing PPP plan will be updated with this information.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25- 870 -108 requires the VSMP authority to approve or disapprove a SWMP.
This plan is approved, and the reasons are provided in the comments below. The stormwater management
plan content requirements can be found in County Code section 17 -403.
1. No changes to the existing SWM plan is proposed with this modification
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1- 44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan
is approved, and the reasons are provided in the comments below. The erosion control plan content
requirements can be found in County Code section 17 -402.
The modification can be approved with the addition of the Storm Drain Inlet Protection, Std. & Spec. 3.07 to the
inlet of the new M -1 manhole structure. The inlet protection will be installed with each lifting of the manhole
structure top section. A stone filter ring may be required by the VSMP inspector if excessive sediment is
documented leaving the outlet pipe. A detail of the inlet protection has been added to the approved plans sets.
County forms can be found on the county website forms center under engineering;
h!Ltp://www.albemarle.ora/deptfonns.asp?department=cdengzMo
File: CDDEI_vsmp_review_5th Street Station modification of basin #3_wpo201500017.doc