Loading...
HomeMy WebLinkAboutSDP200600041 Review Comments 2009-05-20II COMMONWEALTH of VIRCjINIA DEPARTMENT OF TRANSPORTATION CHARLOTTESVILLE RESIDENCY OFFICE 701 VDOT WAY CHARLOTTESVILLE, VA 22911 DAVID S. EKERN, P.E. COMMISSIONER May 201h, 2009 Mr. Glenn Brooks Department of Engineering and Development 401 McIntire Rd. Charlottesville, VA 22902 Subject: Site Review Meeting Comments May 21st , 2009 site review meeting Dear Mr. Brooks: Below are VDOT's comments on the Site Plans for the May 21st, 2009 Site Review Committee Meeting: SDP - 2006 -00041 Briarwood Phase 1A- 1,1B -1, 8 (Elizabeth Marotta) 1. Engineering comments were provided by VDOT on 4 -23 -09 for the additional phase of the project. SDP - 2009 -00030 Forest Lakes Office Park -Maior (Summer Frederick) 1. No comments SDP - 2009 -00031 Collins Medical Center - Preliminary (Gerald Gatobu) 1. Final plans need to show the proposed entrance profile. 2. Final plan needs to show details for CG -6, CG -11, and CG -12B and detectable warning. 3. A Land Use Permit will be required for construction within the public road right of way. SDP - 2009 -00033 University Villalle Retirement Community(Phase I) Summer Frederick 1. The proposed connection to Route 29 needs to be a minimum of 510 feet from the existing intersection or line up with the intersection at the signal. WE KEEP VIRGINIA MOVING 2. This site plan exceeds the threshold to require a Chapter 527 Traffic Impact Analysis. 3. The proposed road must provide a connection to the existing Boulders Road to meet the connectivity requirements of SSAR's, 24VAC 30 -92. Without the connection the road may not be eligible for acceptance into the State Secondary System of Highways. 4. The CG -12 detail needs to be updated and show the proper detectable warning. 5. The proposed Functional Classification needs to be indicated on the plan. 6. If the connection is made to Boulders Road, additional traffic will need to be shown to properly determine the design speed and pavement structural section of the road. 7. Provide the horizontal alignment data on the roads. 8. Street design data on sheet R -4 lists University Village Road but the plans show University Village Dr. Is this the same road? 9. The sight distance on University Village Dr. / Rd. need to be based on the correct design speed on the road. 10. Pavement design on University Village Dr. needs to be designed in accordance with the AASHTO method if this is designed as a collector road. 11. Storm sewer pipes need to be as perpendicular as possible to the centerline of the road and cannot exceed 45 degrees. 12. Street Trees on University Village Dr. need to be located outside of the clear zone of the road if this road is to be classified as a collector. SDP - 2009 -00034 Martha Jefferson Outpatient Care Center (Proffit)- Ma_ior (Gerald Gatobu 1. It appears that the parking and detention facility for this site is in conflict with a previous plan for the widening of Proffit Road and the construction of a roundabout at this intersection. The road plan indicates that there has been a dedication of right of way for the road widening and intersection improvement. Please request the applicants provide a written description of revisions with re- submissions. If you have any questions or comments, please contact me prior to sharing these comments with the applicants. Sincerely, Joel DeNunzio, P.E. Staff Engineer VDOT Charlottesville Residency 434 - 293 -0011 WE KEEP VIRGINIA MOVING