RE: SDP2009 -21 Patricia Ann Byrom Forest Preserve Park Improvements - Preliminary
Dear Sir:
The Planning Commission approved the above - referenced site plan at its June 9, 2009 meeting
and the Planning Commission granted approval of your request for the following waiver:
1. Modification of Section 4.2.5 — disturbance of critical slopes
The approval of the preliminary site plan is valid for (1) one year in accordance with Section
32.4.3.1 of Chapter 18 of the Albemarle County Code. Therefore, the preliminary approval shall
expire on July 21, 2010. If the preliminary site plan approval expires, a new application must be
filed and processed.
Please address all of the requirements and conditions listed below and submit eight (8) tentative
plan copies to the Department of Community Development. This letter must be submitted with
the tentative plans, as a checklist, to document that you have addressed all requirements or
conditions, or the tentative plan will be denied.
Erosion and Sediment Control, BMP Stormwater Management, and road plans with the
associated applications and fees must also be submitted with the eight (8) tentative Plans.
Once the tentative plan is submitted and reviewed you will receive comments from all
departments /divisions /agencies that have made comment on the tentative plan. Any
further responses must be made directly to each department /division /agency that has
further comment. After all aforementioned departments /divisions /agencies have granted
a tentative approval, you must verify with the Planner that you may submit the final
mylars (2 sets), two paper copies, the final site plan application, and final site plan fee to
the Department of Community Development. Signing of the plans will occur within one
week once it is determined that the final site plan mylars reflect all tentative approvals.
The final site plan will be subject to all final site plan requirements (Zoning Ordinance Section
32.6), in addition to the following conditions.
The Department of Community Development shall not accept submittal of the final site plan for
signature until tentative approvals for the following conditions have been obtained:
Zoning & Current Development approval to include:
• Plan to be in accord with that which was presented to the Planning Commission at its
June 9, 2009 meeting.
• Plan to meet all applicable items as specified in Section 32.6 of the ordinance.
Please contact Summer Frederick at 296 -5832 if you have questions or require additional
information.
Engineerinq approval to include:
• [Chapter 17 and Design Manual] Approval of the ESC and SWM plans.
• [Design Manual] Approval of the site plan
• [Design Manual] Approval of the road plan
Please contact Max Greene at 296 -5832 if you have questions or require additional information.
Fire & Rescue approval to include:
• Must comply with the Virginia Statewide Fire Prevention Code.
• Approval is subject to field inspection and verification.
Please contact James Barber at 296 -5833 if you have questions or require additional
information.
VDOT approval to include:
• Approval of entrance onto public road.
Please contact Joel DeNunzio at 293 -0014 if you have questions or require additional
information.