July 6,.20 10
William Moore
Balzer and Associates
1561 Commerce Road
Verona, VA 24482
RE: SDP-w2010-46 Kingdom Hall Major Amendment
Dear Sir:
The Site Review Committee has reviewed the development proposal referenced above. Preliminary
comments for the following divisions of the Department of Community Development and other agencies,
as applicable, are attached:
Albemarle County Division of Current Development (Planner)
Albemarle County Division of Current Development (Engineer)
Albemarle County Service Authority (ACSA)
Albemarle County Division of Planning (E911)- no objection
Albemarle County Division of Planning
Albemarle County Department of Fire Rescue
Albemarle County Division of Inspections
Albemarle County Division of Planning (Architectural Review Board) pending 812110 meeting
Virginia Department of Transportation (VDOT)- pending
Comments reflect information available at the time the development proposal was reviewed, and should
not be considered final. However, the Site Review Committee has attempted to identify all issues that
.could affect approval of the proposed project.
:Please make the revisions that have been identified as necessary for preliminary approval by the Site
Review Committee. If you choose not to, make the requested revisions, please submit in writing
justification for not incorporating such revisions. Submit eight (8) full size copies and one (1) 11" x 17"
copy to the Department of Community Development including responses to each of the attached
comments of the Site Review Committee by July 19, 2010. Failure to submit this information by this .
date will result in suspension of the review schedule. Review will resume when revisions are submitted
along with areinstatement fee of $65.
Please contact me at your earliest convenience i f you have questions or require additional information.
Sincerely,
Elizabeth M. Marotta, Senior Planner
Current Development
$� of
0
�'jRGIN1P
County of Albemarle
Department of Community Development
Memorandum
To: William Moore, Balzer and Associates, Inc.
I—;rw/o'm: er: Morgan Davis, East Congregation of Jehovah's Witnesses
Elizabeth Marotta, Senior Planner
Division: .Zoning & Current Development
Date: July 1, 2010
-Subject: SDP 2010 -46- Charlottesville Kingdom Hall Major Amendment
The Planner for the Current .Development Division of the Albemarle County Department
Community Development will recommend approval of the plan referred to above when
the following.items have been satisfactorily addressed. (The following comments are
those that have been identified at this time. Additional comments or conditions may be
added or eliminated based on further review.) [Each comment is preceded by the
applicable reference to the Albemarle County Code.]
[SP2009 -29] Plan must be in conformance with the Concept Plan (dated 11 -16-
09) and conditions approved with the Special Use Permit (June 11, 2010).
COMMENT: SP condition #3 indicates the sidewalk easement shall be reserved
for future dedication; therefore please amend sidewalk easement callout to say
"Proposed sidewalk easement and 5' right -of -way to be dedicated upon demand
of the County."
2. [32.5.6.a] Name of development: COMMENT.: Add to the cover sheet and/or
title blocks that this is "Major Site Plan Amendment SDP2010 -46"
3. [32.5.6.a]:COMMENT: Provide magisterial district (Scottsville) on the cover
sheet.
4. [32:5.6.a] Descriptions of all variances, zoning proffers, and bonus factors:
COMMENT: Conditions of SP2009 29 must be provided on the plan. Typically,
these are added as a list to the cover sheet or notes /details sheet.
5. [32.5.6.a] Source of survey /topography: ;COIV MENT: Provide dates for survey,
topography, and tree location.
6. [32.5.6.a] Datum reference: ,COMMENT: Benchmark symbol on cover sheet Cl
does not match that on Sheet C4. Please revise so that Legend matches symbol
used in the plans.
7. [32.5.6.a] Total number of sheets: COMMENT: While not required for approval,
please add total number of sheets to each sheet, as in "1115" or "1 of 15 ". This is
very helpful when/if the sheets get separated from the set.
8. [32.5.6.a] Minimum setback lines: COMMENT: While setbacks are drawn on C4
etc., please list minimum setbacks as a note on the cover sheet.
9. [32.5.6.d] Critical slopes: - COMMENT: On the cover sheet, indicate critical
slopes waiver was approved. Then, on the site plan, indicate the critical slopes
that were approved for disturbance in the waiver.
10. COMMENT: Remove sign height note; this will be reviewed at the time the sign
permit is reviewed.
11. [32.6.6.f] Signature panel COMMENT: Signature panel is not required; this is an
amendment and will get an approval stamp.
12. [32.5.6.p, 32.6.61] Landscape Plan: COMMENT: Is Note #10 on the cover sheet
C1 referring to "interior parking lot landscaping ?" If so, please change the term
"green space" to "interior parking lot landscaping" so that it is more clear what
.code requirements are being met.
a. If this is discussing interior parking lot landscaping, then the calculation
should be 5% of paved parking and vehicular circulation areas. [32.5.6.n.]
Please confirm parking and vehicular circulation areas are accurate, i.e.
that the 23,600 stated in Note #11 is correct, as opposed to the 21,095
stated in Note #10. Both figures should match.
b. If your calculations are based on something different, please explain in
your response letter, or make adjustments on the sheet as necessary.
13. [32.5.6.p, 32.6.61] Landscape plan: Conservation Checklist must be updated.
Please review checklist to make sure it is accurate, and re -sign and date.
14. [32.5.6.p,.32.6.6.i] Landscape plan: "JS" should probably be called out as "ZS"
in the drawing. Also, identify 4 plants to the immediate east of the proposed
dumpster. Please revise either landscape schedule or the plan. accordingly.
a.. Trees are proposed very close to water and power lines. Please place trees
farther away from the utilities to allow room for utility work and root
growth.
b. Waterline linetype is not provided in the legend on Cl. Please add it to the
legend, or revise linetype.
15. [32.6.6J] Lighting plan: The lighting plan must conform to Chapter 18 Section
4.17. Therefore, provide cut - sheets on the plan for all fixtures proposed. (All
fixtures must be full- cutoff.)
16. [32.6.6 j] Lighting plan: Lighting is not permitted to be over 0:5 footcandle at the
property line. Please address 0.8 at the northern property line (entrance).
17. [32.6.6.j] Lighting Plan: Albemarle County Code requires a LLF of 1.0. Please
revise data and photometrics accordingly.
18. [32.5.6.n] Trash containers: Be sure to label details on Sheet C10 consistently
2
with Legend on C4. For example, C4 calls "T" a "trash enclosure ", but on C10
there is no "trash enclosure." I assume it is the "fence screen detail," but for
clarity purposes, either provide a "T" with the detail on C 10, or change the name
to match what it is called out on C4.
a. Similarly, indicate under "C" and "H" and any other details in the Legend
on C4 where exactly that detail can be found (C10).
19., COMMENT: ACSA approval is required prior to approval of this amendment.
However, before ACSA can issue their approval, Rivanna Water and Sewer
Authority (RWSA) must approve the plans. Unless otherwise directed by ACSA,
please coordinate directly with both ACSA and RWSA to obtain ACSA approval.
RWSA contact is Justin Weiler, (434)977 -2970 x206. His email is
Jweiler@rivanna.org.
20. COMMENT: This project proposes private septic; Health Department approval/
confirmation of system proposed is required in writing. If it has already been
obtained, please forward a copy of the approval to me for verification.
21.�COMMENT: ARB approval is required. ARB meeting is set for August 2,20 10,
after which comments will be received.
22. COMMENT: Inspections Division approval is required. See comment in County
View dated 6/21/10, and included in the SRC package 7/8/10.
23. COMMENT: Engineering approval is required. See Comments dated July 1,
.2010, available online on County View, and included in the 7/8/10 SRC package.
24. COMMENT: VDOT approval is required. Comments are -pending.
Please contact Elizabeth Marotta, Senior Planner at the Department of Community
Development 296 -5832 ext. 3432 for further information.
OF Al,
� IRGINIP
COUNTY OF ALBEMARLE
Department of Community Development
,401 McIntire Road, Room 227
Charlottesville, Virginia :22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
Project: Kingdom Hall of the Jehovah's Witness [SDP201000046,
WP0201000034]
Plan preparer: William Moore [wmoore @balzer.cc]
Owner or rep.: East Congregation of Jehovah's Witnesses; Morgan Davis ETAL TRS
Plan received date: 15 June 2010
Date of comments: 1 July 2010
Reviewer: John P. Diez — Current Development - Engineering Technician
A. Final site plan (SDP201000046)
1. Please provide the application number of the previously approved site plan that this plan is
amending.
2. All proposed slopes steeper than 3:1 must have low maintenance (not grass) ground cover
specified on the plan.
3. All entrances must have VDOT designations (PE -1, CG -9a, etc.)
4. VDOT approval must be obtained for any plan affecting right -of -way.
5. Please clarify arrow stripping in the parking area.
B. Stormwater Management Plan (WP0201000034).
6. Please provide a completed copy of the standard stormwater maintenance agreement and fee for
recordation for any stormwater management facilities.
7. Please label STR #3 and #4 on the profile.
8. Please replace the sidewalk turn -down with a CG 72 and shift 6" out to allow the minimum 5'
width of sidewalk.
9. Please show all utility crossings on the profiles.
10. Minimum pipe sizes into and out of the facility must be 15" diameter for maintenance.
11. It appears that the some of the runoff in post - development is now flowing to a SWM facility. The
run -off from DA #2 must be captured for stormwater management treatment.
12. With the added impervious from DA #2, please revise the size for the biofilter. If the facility is to
treat 50% removal rate, then the. first 0.5" of runoff is to be treated. Please size the biofilter using
the 2.5% of the total impervious area. In addition:
- Please provide 2.5' of sand /soil media.
- The floor of the biofilter must be flat (0% slope)
- Please provide l'— 1.5' of stone drain in geotech fabric under media, with 6" perforated
pipe to daylight.
- Please provide 1' ponding depth.
Please refer to the SWMH Section 3.11A and 5 -6.1 and the Design Standards. Manual for specs.
and details.
Engineering Review Comments
Page 2 of 2
C. Erosion Control Plan (WPO201000034)
13. Please provide a stockpile location.
14. Please provide a staging and parking area.
15. Please show on the detail or plan that the wet storage side slope is 1:1 or flatter.
16. Please extend the diversion dike towards the northeast side of the proposed building.
17. Please provide a construction entrance prior to #6 of the construction sequence. Protection must be
provided for all stages of construction.
Once these comments have been addressed, please submit two (2) copies of the revised plans, calculations,
and narratives to Current Development Engineering.
Current Development Engineering is available from 2:30pm — 4:OOpm on Thursdays to discuss these
review comments. Please contact Amy Pflaum at 434- 296 -5832 or apflaum @albemarle.ork to schedule an
appointment.
If you have any questions, you can reach me, John Diez, at (434) 296 -5832 ext. 3025, or my email:
idiez@albemarle.org.
a:i €?i( iiyv' to ..l;1;}:3<}ws "'Et1i;.t:1f ".y�:P til?I(t004ihirAgdoalJ-tsi ti<a,x? {:;.�:�i::i i .;; ,sti � .1.i't:)....1 Paz -l; tzIA?AIA'x'
a
:Service Auth`rity
��� ♦conSQ��n�
'TO: Elizabeth Marotta
PROM: Gary Whelan, Civil Engineer
'DATE: June.25, .2010
'RE: Site Plan Technical Review for: Kingdom Hall of the Jehovah's Witnesses
SDP201000046
TM 76 -51
The below checked items apply to this site.
✓ 1. This site plan is within the Authority's jurisdictional area for:
✓ A. Water and sewer
B. Water only
C. Water only to existing structure
D. Limited service
✓
2. A .20 inch water line is located approximately 50' distant.
3. Fire-flowftom, nearest public hydrant, located distant from-this site plan, is
Gpm + at 20 psi residual.
J .4. An 8 inch sewer line is located approximately 400' distant.
5. An Industrial Waste Ordinance survey form must be completed.
J 6. No improvements or obstructions shall be placed within existing orfuture
easements.
7. and plans are currently under review.
8. and plans have been -received and approved.
J 9. No plans are required.
'10. Final and plans are required for our review.and approval prior to
granting tentative approval.
1.1. =Final site plan may /may-not be�signed.
'12. 'RWSA approval for water and /or sewer connections.
-13. City of Charlottesville approval-for sewer.
✓ Comments: ACSA records indicate a 1" water meter. If demand requires a larger
water meter a new tap might be required. RWSA must approve all new water
connections-to-their pipes. -Backflow prevention is required and should be
indicated on-the utility plan.
The site plan does not show or incorrectly shows:
meter locations
water line size
waterline locations
sewer line size
sewer line locations
expected wastewater flows
168 Spotnap Road Charlottesville VA 22911 Tel (434) 977 -4511 • Fax (434) 979 -0698
www. servicea uthoriy. org
Memo& County
:.
:'Service .Auth6Hty
Serving 6 Conserving —
easements - expected water demands
168 Spotnap Road • Charlottesville VA 22911 • Tel (434) 977 -4511 Fax (434) 979 -0698
www.serviceauthoriy.org
Application #: SDP.201000046 Short Review Comments
Project Name:1 Kingdom Hall of The Jehova's Witnesses -- Major Major Amendment
Date Completed: 06/24/2010
Reviewer: Andrew Slack E911
Review Status: Approved
Reviews Comments:
Date Completed:
Reviewer:
Review Status:
Reviews Comments:
Date Completed:
Reviewer:
Review Status:
Reviews Comments:
Date Completed:
Reviewer:
Review Status:
Reviews Comments:
Date Completed:
Reviewer:
Review Status:
Reviews Comments:
%PPROVED.
07/02/2010
Claudette Grant Planning
Requested Changes
Fhis is a reminder that the applicant needs to remember to show Condition #3 on the final site plan.
06/23/2010
James Barber Fire Rescue
No Objection
please indicate the location of fire hydrants. Hydrants must be located within 400 feet of the building
)y way of a prepared travel way.
06/21/2010
Jay Schlothauer Inspections
Requested Changes
Based on plans dated June 11, 2010.
Relocate the three barrier -free parking spaces to the eastern -most row of parking (adjacent to the
-urb and gutter), as close as practicable to the main building entrance.
06/29/2010
Margaret Maliszewski ARB
Requested Changes
phis plan is scheduled for review by the ARB on August.2, 2010. Comments will be provided after thal
neeting.