RE: SDP201100033 Dunlora Forest - Preliminary
Tax Map Parcel 062F0- 00- 00 -000A0
Dear Mr. Myers:
Fax (434) 972 -4126
The Albemarle County Planning Commission, at its meeting on, October 18, 2011 approved the above -
noted petition, by a vote of 6:1. The Department of Community Development shall not accept submittal of
the final site plan for signature until tentative final approvals for the following conditions have been
obtained. The final site plan shall not be signed until the following conditions have been met:
1. Community Development Planner approval to include:
a. Meet all the requirements in Chapter 18 Section 32 for site plans, including landscaping and
lighting plans.
2. Community Development Engineer approval to include:
a. Additional provisions and easements for drainage across three or more lots may be required
for final approval. "Dense development where fencing, decking, etc is expected should
provide yard inlets and pipes rather than ditches. Narrower easements for private yard drains
may be acceptable and will be reviewed for adequacy."
b. The plan must meet all engineering requirements of the Water Protection, Subdivision, and
Zoning Ordinances in addition to all engineering standards detailed in the County's Design
Manual.
3. E911 approval to include:
a. The applicant should contact Community Development E911 staff with a list of three (3) road
names for "Road A ", "Road B ", and the 34 foot access and utility easement for approval
before the final plans are submitted.
4. Albemarle County Service Authority approval to include:
a. Water easement for future interconnection will be required by ACSA before final site plan
approval.
5. Fire and Rescue Division approval to include:
a. Adequacy of fire flow
b. Location of fire hydrants
6. Virginia Department of Transportation approval
7. Final site Plan to be reviewed by the Planning Commission prior to final site plan approval.
In addition the Planning Commission approved, by a vote of 6:1 the Critical Slopes waiver for modification of
Section 4.2.5.
If you should have any questions or comments regarding the above noted action, please do not hesitate to
contact me at (434) 296 -5832.
Sincerely,
Megan Yaniglos
Senior Planner
Current Development Division
Cc: Keith Lancaster /Southern Development