HomeMy WebLinkAbout2002-03-20 Budget4~
Call to Order.
BUDGET WORK SESSION:
Capital Improvements Program.
Issues from Prior Work Session.
4:00 P.M. - JOINT MEETING WITH SCHOOL BOARD
Call to Order.
Work Session: School Budget/Compensation.
From the Board and School Board: Matters not Listed on the Agenda.
Adjourn.
RECEIVED AT BOS MEETING
Date: 3
Agenda Item #:
Clerk's Initials:
WOrk SesSion
Capital': Improvements Program
March 20, 2002
Increasesgeneral fund transfer
~ to,the capital program and to debt service
growth to: the capital fund
l~t ~f ~he tax rete to the Ca~tal debt
service~
07-'1 ~1 As~ssment~
' current 5-year
FY 103-07' CIP amendments have
been reviewed by the ;Technical~Committae.
Schools
57%
OtherLocal
Z%
15%
ACE
Stormwater ~%
~.Hiwys & Trads
2% 4% 7%
~, To~be:aMid~cycle Amendme~it~ ithe~PrOposed
pi:oiect: Meet~ --
~ The ~OIIowing~definition of acritical need:
otherWise.
A specific Federal/State ~mandate:
A~pub!ic:policy established by the. BOardof
SuPervisors~ ~Or for. SchOol projects, by the
County SchOOl Board.
And/or the following:other sPeCifiC criteria:
Reflects updated cost :~al~ui~tions bas&d On
better' iitfOrmationand/or proem clarifie~ition.
RefleCtS a change:for an existing approved
be lOst; if.it was deferred until: the inext regular
revenue projections.
r.: ~ - ' - '*~;~
Amended!FY 03~)7CIP $109.2 Mi! Original FY03~OTCIP $103.9
Mil
Court) 0307 period.
~ 2. Increased costs by $7.0
4. TowePark Tennis
Court
~S. 6cotta-~ille CC
based on consultant study
4.Rel~lacement of court surface
-Sa~b~ i~sue, netS8,000 =in~r.
(Additional)
6; County Animal ~ 6; New Proiect- Addsa tota of
$250~000 {$50;000 peryear from
Shelter'Construction
Fu~d - SPCA contribUtiOn to the Construction
8: County FaCilities - upgrades to the county GIS.
Maintenance& ,~ 8, New - $80.000 to Co(~nty
Facilities Maintenance in FY 03
RePlacement for renOVation of COB
elevat0rs,=and MastetPlan for
County FacilitiesM~intenance.
Field~$t00~000 in FY 2006.
These items ~n ;be r~0nsidered in the FY
04-08 Update ~f the~fbll CIP~
;~ t; Crozet :KitChen ~ 1~ Add'l $40,000 needed in~FYO3
for CurrentprojeCt.
~ 2: string$~Pmgram ~ 2.~.~g~;.%addscla~ro0ms
~t dbd~U~ H~nley, & ~itOn MSfot
strings prog~m~ switc~s
~J;245L000: in ~02 ~nds ~
Sb~rn =Elemen~ co~tr~i~n
defe~l t0 pay for Jouett MS
~ 3~ Monti~llo HS additi0n~&~s~ings claSSt~m.
Additioa ,~ 3. Proje~cos~ updated. Funds
addition design wo~ in ~03,
I~V~ cons~u~on in ~ 06 as
Shown~in current ~02 CIP until
next vea~S~ ~visi6n.
Elementar~
5. School Site Land ~ 5. Moves $25,000 from FY 06 to~FY
AcquisitiOn 07~ movers $1~850,000 to out-years
6. :Post,High' House ~ 6.: New:- $250.0~0 in'l=Y 03 fer
HoUSe to teach livi0g! skills to post-
high school special education
students (18-21 year-olds); current:
eased space s be ng lost
7. Major Maintenance ~
~ 7. Adds Sl,200,000 in ~FY 03 and
adjus~ costs in FY=04~O6 10r
maintenance to address health &
safety.issues in schools.
MOntiCello HS AuditOHUm ($5;53'1 mill
8tor~ge !Area/Warehouse($O~g8O mill '0Z)
WAHS AuditOrium Wall (0.360 mill in ~07)
Advancing COnstruction of Monticello HS
Addition and Separating Gym from
addition.
These can be re-considered next year in
the:f i ill; FY O4~08 CIP Update.
Admin
Pabli¢ Safety
12%
4%
SchOol Projects - BorrOwed ~*' $; ;8;700,
School, -Pay. as-Go* ~ 1.03t
General GOvt~ Projects ~, 5.5t9
stsrmwater Projects ~ 0~575
Total Projects e $15.825
rw ;eilteral: Fiind ~-ansfe:r ta~ the CaPital
~i:ii,i ~am and :~ ~::.debti sennce, ;ii, each, i~, ~,:: !i ::~ ;i i~year ~; i~,r byh ii1! I;'i ;B i: ,rrlthe ratel:,, ofil~ ~i ;total
revenue groWth
Past trend has bee,:~ about a 7% ~annual rgroW~h.
For FY 03. in November of:2002. Our estimated groWth
Slowd0wn~ and
· uncertain effects of aftermath ~September t 1th;
~ OediCate~amounts forCIP ~nd DebtService:were based
On these assumptions
~ Impact has been to use:some of tlie: ReServe~
~ 03'~Capital: Funds ($ in 000)
{inc; StormWater)
~ : FY 03 T0tal Need $6~203
~=~ransfer 5~520
Difference from ReserVe ~683
$5.579
5.520
Other Revenue 239
Total
Gert Gev~t Projects 6.094
SchoolS - LOcal 348
Tota I 6.442
Remaining CIP Reserve 4.896
The CapitalReserve is used for'the next 4
years t~ adjUst'fOr.
· ~ Change~ in the economy ;iffe~ti~g:
revenue growth,
· InCreasing debt: service ;costs ever time
for capital projects~
. Cushioning annual ~flu~uationS in
revenues and~'eroje~ COst~
RECEIVED AT BOS MEETING
County General Fund
Beginning Board Reserves
Less County Executive Adjustments
Agency Request - SHE to provide funding increase @ 2.5%
MACAA Teen Pregnancy Prevention Program funding
FICA for Parks & Recreation Summer P-T employees
Commonwealth's Attorney -continuation of full salary for 1 staff
Commission on Children & Families
Adjust Benefits for Senior Planner (1/2 yr)
Clerk's Initials
Recurring One-Time
405,597 850,000
941
32,656
20,000
12,000
1,766
1,900
Subtotal -- Subtract
Plus County Executive Resource Changes
Parks & Recreation Fees (Increase $1 on Entry Fees)
69,263
35,000
Subtotal - Add
Less Board of Supervisors' Adjustments
35,000
Subtotal - Subtract
Plus Board of Supervisors Resource Changes
Increase vehicle decal fee by $3.50 (40% local/60% school)
Increase E-911 surcharge by $0.26 to $1.65 (no Fire Dispatch increase)
Provide Tourism Funds for ACE/Other
262,500 262,500
159,588 159,588
450,000
450,000
Subto~l- Add
Subtract School Share of Vehicle Decal Revenues
872,088
422,088
157,500
450,000
Increase Compensation by 1.3% (to 3.3%)
Administration
1.0 FTE Budget Analyst I
Judicial
295,000 295,000
54,225 52,975
1,250
Public Safety
Adjusted request for Regional Jail operations & operating reserve
Adjusted request for BRJDC
1.0 FTE Fire/Rescue Trainer
152,731 52,731
26,370
45,189 45,189
100,000
26,370
HUman Development
~Smmision on Children & Families
18,000 18,000
Parks and Recreation
Library
30,000 30,000
FY03 BOS Budget Worksheet 3-20-02xls.xls Page I of 2 Printed 3~20~02 11:19 AM
Coun ,ty General Fund Recurring One-Time
Community Development
1.0 FTE Senior Planner 65,068 56,658 8,410
ACE (Tourism Fund) 450,000 450,000
ACE (General Fund) 550,000 550,000
School Division
Additional Initiatives Funded
1,686,583 550,553 1,136,030
School Division
Plus Additional Ongoing Resources - School Division
Subtotal
0
Plus Additional One-Time Resources - School Division
Subtotal
0
I Total School Board Resources 911,0021
Unfunded School Board Initiatives:
FY03 BOS Budget Worksheet 3-20-02.xls.xls
Page 2 of 2
Printed 3/20/02 11:19 AM
RECBVED AT BOS MEETING
County General Fund
Beginning Beard Reserves
Less County Executive Adjustments
Agency Request - SHE to provide funding increase @ 2.5%
MACAA Teen Pregnancy Prevention Program funding
FICA for Parks & Recreation Summer P-T employees
Commonwealth's Attorney-continuation of full salary for 1 staff
Commission on Children & Families
Adjust Benefits for Senior Planner (1/2 yr)
Subtotal - Subtract
Clerk's initials:.
Recurring One-Time
405,597 850,000
941
32,656
20,000
12,000
1,766
1,900
69,263
Plus County Executive Resource Changes
Parks & Recreation Fees (Increase $1 on Entry Fees)
Subtotal - Add
Less Board of Supervisors' Adjustments
Subtotal - Subtract
Plus Board of Supervisors Resource Changes
Provide Tourism Funds for ACE/Other
Subtotal- Add
450,000
450,000
35,000
35,000
450,OO0
450,000
Increase Compensation by 1.3% (to 3.3%)
Administration
1.0 FTE Budget Analyst I
Judicial
295,000
54,225
295,000
52,975
1,250
Public Safety
Adjusted request for Regional Jail operations & operating reserve
Adjusted request for BRJDC
1.0 FTE Fire/Rescue Trainer
152,731
26,370
45,189
52,731
45,189
100,000
26,370
Human Development
Commision on Children & Families
18,000
18,000
Parks and Recreation
Library
30,000
30,000
FY03 BOS Budget Worksheet Costs 3-20-02.xls
Page 1 of 2
Printed 3/20/02 8:56 AM
Board of Supervisors' FY 2003 Operating Budget
County General Fund
Recurring One-Time
Community Development
1.0 FTE Senior Planner 65,068 56,658 8,410
ACE (Tourism Fund)
ACE (General Fund) 450,000 450,000
550,000 550,000
School Division
Additional Initiatives Funded
1,686,583 550,553 1,136,030
School Division
Plus Additional Ongoing Resources - School Division
Subtotal
0
Plus Additional One-Time Resources - School Division
Subtotal
0
i Total School Board Resources 911,002J
Unfunded School Board Initiatives:
FY03 BOS Budget Worksheet Costs 3-20-02.xls
Page 2 of 2
Printed 3~20~02 8:54 AM
OMB BUDGETANALYST
The OMB was established as a re-organization of County resources and as an
organizational enhancement to provide staff support services to the County leadership
and other officials that were not previously either available or optimally organized. The
workload demands assigned to OMB have increased as part of that re-organization, and
this additional position request is part of the base minimum level of staffing needed in
OMB to fulfill its responsibilities, as envisioned in the rationale for its establishment.
In FY 03, the County is scheduled to do a major revision of the Capital Improvement
Program (CIP) and Capital Budget. Review of capital project funding needs, estimates,
revenues, and bond financing issues will involve considerable staff work and input from
OMB. The County will also likely be implementing or planning other new budgeting
efforts, such as a Vehicle Maintenance and Replacement Fund.
The requested new Budget Analyst II position will
· perform complex budget development and fund monitonng analyses for assigned
departments and agencies sections of the operating and capital budgets,
· assess need for budget resources in alignment with strategic directions,
· develop financial forecasts and multi-year budgetary needs,
· analyze and forecast requirements for non-General Fund budgets,
· oversee performance, outcome, quality and customer service improvement efforts
being undertaken by assigned departments;
· perform financial condition forecasts, multiple-year budget forecasts, and future
budgetary needs planning linked to achieving strategic objectives; and
· assist in identifying new and un-tapped revenue sources, including grant funds and
borrowing to finance County programs.
RECEIVED AT BOS MEETING
Date:
Agenda Item #:
Clerk's Initials:
RECEIVED AT B,.i)-',~ MEETING
Date: .....--~L-("bJ
Agenda Item #:_
FUTURE OF COUNTY FIRE ~{Pi~_~H ~
County/City Fire Services Agreement states that the City will provide "free"
dispatch until June 30, 200~L
After that date, the County can choose to have dispatch services provided
through one of the following methods:
1. the City Fire Department
2. a combination of ECC and City Fire.
3. bythe ECC
OPTION 1: CITY CONTINUES TO DISPATCH ALL COUNTY FIRE CALLS
Two Cost Components per the Contract'
1. City dispatches County resources to County calls
· contract says County and City to negotiate a "reasonable" fee
· waiting on City for estimates
· have indicated additional dispatcher may be needed
2. City diSpatches City resources to County calls
· Formula in contract established based on midpoint of
dispatcher/firefighters salary plus benefit costs
Cost Estimate:
City cost to dispatch County resources to County calls
City cost to dispatch City resources to County calls (approx)
unknown
$34,OOO
Alternate Estimates:
60% of nine dispatcher sala~'ies and operating costs
$259,500
OPTION 2: ECC AND CITY DISPATCH COUNTY CALLS:
,Two Cost Components:
1. ECC dispatches County resources to County calls
· ECC has provided an estimate of $185,000 to add County fire dispatch
(5 dispatchers and operating costs)
2. City dispatches City resources to County calls
· Formula in contract established based on midpoint of
dispatcher/firefighters salary plus benefit costs
Cost Estimate:
ECC cost to dispatch County resources to County calls
City cost to dispatch City resources to County calls
$185,000
$ 34,000
$219,000
Option 3:,
ECC dispatches all calls for the region - County and City
resources dispatched to County and City calls based on
established protocols
One Cost Component:
1. Approximately 60% of total cost of ECC dispatch
· may vary based on actual dispatches for the region
· a formula will need to be developed to fairly distribute costs
Cost Estimate:
60% of $185,000 for 5 dispatchers and operating costs
$111,000
RECEIVED AT BOS
Date:
ALBEMARLE COJ~N;~I~"m
FY 2002/03 OPERATIbI~,~dktI~.G_ET.
BUDGET FORM #8 - NEW/EXPANDED PROGRAM
DEPARTMENT: Planning & Comm. Development
COST CENTER NAME: Planning & Community Development. Division
COST CENTER: 81010
BRIEF DESCRIPTION OF NEED: To implement the Board adopted Neighborhood Model Implementation
FUNDING
TOTAL INCREASED EXPENDITURES: $262,109
TOTAL INCREASED REVENUES: 0
NET LOCAL TAX FUNDING: $262,109
POSITIONS
GRADE: 16
1. Please provide a detailed description of the enhancement requested and how it fits into your
department's mission and goals. Be specific as to what is actually being enhanced, who, when,
& where.
1)
Funding for the third Neighborhood Master Plan to be initiated around March of FY 02/03, which is
based on the proposed timing of beginning each new Neighborhood Master Plan 6 months after the
previous Plan has been initiated. (The first Master Plan will be initiated in March 2002. The second
will begin 6 months later if funded as part of the County's baseline budget as previously requested
b ~artment.
3) Capital equipment needed to support Neighborhood Model/Master Plan. This includes one (1) new
laptop computer and projector for power point presentations, and six (6) easels.
2. What factors have caused the request for this enhancement in this budget cycle? Please use
data (such as workload measures, service levels and growth factors) to support your
justification for this request. If applicable, provide a graph to better communicate your data-
supported justification of this request.
Timely and effective implementation of the Neighborhood Model is this Department's highest priority
project and one the County's highest priority efforts. High expectations exist with the Board, Planning
Commission, general public, and the development community to implement the recommendations of
the model quickly and effectively. The development of the Neighborhood Master Plans is the highest
priority initiative. There are 11 designated Development Areas that need to be master planned. These
areas are to be covered by a total of seven (7) Neighborhood Master Plans. While starting a new
Neighborhood Master Plan every six months is an aggressive schedule, it will take about 5 years to
complete all master plans under this schedule. In order to meet this schedule and the scope
anticipated for the Master Plans, it will be necessary to use consultant services. Current staff levels
and expertise are insufficient to undertake multiple Master Plans of this complexity (See separate
attachment, Workload Information).
Development of each master plan necessitates management by staff. Therefore, an additional Senior
Planner will be necessary to begin work on the second neighborhood master plan while the first master
plan is still underway. Also, once each plan is completed, it is anticipated that expectations will
increase in each area for continuing planner involvement in the responsive implementation of each
master plan and other on-going planning initiatives in each area. The current level of staffing for the
Development Area core function is three (3). These three staff are responsible for all Comprehensive
Plan Amendments, rezonings, special use permits and other planning projects within the Development
Areas, with one Senior Planner (Susan Thomas) having primary responsibility as the neighborhood
planner for the Crozet Master Plan. In the current workload environment, this is not sufficient staffing
to take on all of the master plan work required to implement the Neighborhood Model (see separate
attachment, Workload Information, regarding current and future project demands). Staff estimates that,
at a minimum, a total of four (4) neighborhood planners will ultimately be needed to support the
development and implementation of all seven (7) master plans.
This expanded request also includes some of the equipment needs to support the initiatives described
above. This equipment will be needed to by provide presentations and work in the field on master plan
development. When multiple plans are under development, it is anticipated that the Department wide
demand for the Department's laptop computers will exceed their availability. Also, the Department must
now borrow a projector from other departments when available, which becomes inefficient in an
increased demand environment~
Breakdown of Task Areas/Personnel in the Planning & Comm. Devel. Division, FY 02-03
The fbllowing is a listing of projects identified in the Comprehensive Plan and Department work program
and ongoing assignments~ Adjacent to the listing is the staff person assigned to that project. The "----"
indicates projects unassigned, primarily do to staff limitations, timing of the project, or both.
Current Planning
Site Plans
Subdivisions
Tower review
Subdivision Ordinance
Amendments
{5 staff assigned)
Steve Waller, Margaret Doherty, Karl Guiler
Yadira Amarante, Francis McCall, Margaret D~
Steve W., Margaret D.
Current Planning team (Yadira/Marg. D, leads)
{2 staff assigned }
Margaret Maliszewski, Janet Miller
Margaret M.
Margaret M., Janet M.
Janet M.
Design Planning
ARB
Historic Preservation
Lighting Ord/policy
Landscape plan assist.
Historic District Plan:
· staff committee Marg. M~
Implement action agenda Marg. M.
Historic Site Survey ....
Historic Preservation Ord. ----
Development Area (DA)
ZMA's
Special Use Permits
CPA's/"2232" Rev.
Text Amend. (ZTA)
(3 staff assigned)
Elaine Echols, Michael Barnes
Elaine, Michael
Elaine, Michael
Elaine, Michael
Pub. Facilities Site Analysis:
Southe~ Elem. site
selection process
* Preddy Creek prop.
Study for future use
,, Development of an
Official map ....
Neigh Model Master Plan:
* Crozet Susan Thomas
* 2nd Neigh. Master Plan
.... (also Rural Planning staff member)
PACC Area B Study:
· JPA/Fontaine area
· Blue Ridge Hospital
Comp Plan Rev/Update
DA Holding Area Study ....
Indust. Area Bldg Study ....
Suburban Area Analysis
Rural Area (IL~)
Special Use Permits
CPA's/"2232" Rew
Rural Pres. Devel
ACSA Juris. Area Rev.
ACE
Ag/Forestal Districts
Rec Facil. Authority
Conserv~ Easements
Rural Area, Comp Plan
(3 Staff assigned + part-time temporary staff person[ACE Coordinator])
Joan McDowell, Scott Clark, Steven Biel
Joan, Scott
Joan, Scott, Steven Biel
Scott
Ches Goodall
Scott
Scott
Scott
Joan, Scott, Steven B~
Critical Res~ Inventory/Bio-
diversity Study Scott
Joint Jurisd. Planning of
Border Areas
Scenic Highways Study
Vol. Res. Protection
& Ag/For Ind. Support
Open Space Plan Update
Transportation (Juan Wade)
Six Year Primary and Secondary Plans
Traffic Model operation
Rt. 250 West Committee
JAUNT Board
Review of Devel. proposals for Trans. issues
TEA21 Enhancement Grants
Completion, Rt. 250 East Study
CHART regional transportation
plan, five year update
Various other
Fiscal Impact (Steve Allshouse)
Fiscal Impact Model Annual Update
Fiscal impact Model Refinement and Development
Fiscal Impact Analysis
CIP
Various other
FY00/01 staff time breakdown (Development Area and Rural Area)
This is breakdown of staff time in the two policy area core plamfing groups (Development Area and Rural
Area)
Joan
40% RA Review
25% SP's/ZTA's
10% supervisory
10% support of committees (ACE, PRFA, Ag/Forestal Comm.)
15% research, meetings, phone/walk-ins
Scott
S. Biel
30% SP's/RPD's/RA related devel review (farmers' mkt, winery sales SDP's)
30% RA Review
20% Ag/For Districts, PR~A, Bio-diversity
20% research, meetings, phone/walk-ins
(all of the assignments Scott has work on are expected to remain with hiru.)
45% SP's/RPD's/RA related devel review (fhrmers' nhkt, winery sales SDP's)
35% RA Review
20% research, meetings, phone/walk-ins
(all of the assignments Scott has work on are expected to remain with him.)
For your information, noted below are a number of "major" review projects that have a good possibility of
being submitted for review over the next 18 months to 2 years (begirming in Jan.,2002) for which staff are
not currently assigned, but will be obligated:
Golf Course and community proposed for Advance Mills Village
LI
pu~snoq,i, ~ad
To~
From:
Date:
Subject:
Members of the Board of Supervisors and School Board
Kimberly L. Suyes, Director of Human Resources
March 18, 2001
Joint Board Compensation/Benefits Update
In November, the Joint Boards directed staff'to develop the FY2002-03 budget
based on a 2.0% salary increase for employees and asked staff'to come back during the
budget process with an update based on data from the adopted competitive market.
Staffwill be making a presentation to the Joint Boards this Wednesday, March
20, 2002. In preparation for this meeting, staff conducted a survey of the adopted market
to gather data on both the projected salary increase and the cost split on medical
insurance for next year. Of the 30 localities/organizations in the adopted market, 20
organizations responded to the salary survey and 21 organizations responded to the
medical insurance surVey.
Enclosed is a copy of the survey data for your information and review.
The results of the survey indicate that the jurisdicti6ns in our market are pursuing
the following proposed salary increases for next year:
· A 3.8% salary increase for teachers based on the median of the market data
· A 3.5% salary increase for classified employees based on the median of the
market data.
The survey also indicated that within our fnarket, the average employer
contribution for medical insurance is as follows:
('Albemarle Board.contribution Employee Only 95.5% - no additional for employee +
family,)
· Employee Only 91.5%
· Employee + Family 26.6% beyond contribution for the individual employee
In general, it appears that the WorldatWork projections after the events of
September 11 were somewhat conservative based on our current projected market data.
I look forward to discussing this information with you on Wednesday. In the
meantime, please feel free to contact me if you have any questions or require any
additional information.
I I I
I I
I I I
0 0 0 0 O0 ·
o~ o~ O~ o~ o~ o~ o~ o~ O~ o~ o~ o~ o~
c o c ~ ~ o o ~ ~
o c 0 ~ E c 0
0 ~ ~ 0 ~ o ~ c c
= 'E E = ~ c ~ c ~ c o c c ~
~ 0 0 0
RECEIVE~p~' AT_BOS MEETING
Date:
Agenda Item #:
Clerk's Initials: ~"~c~ ~ _ .
Funding
Request
2002-2003
I High & Expectations
[ WhatG°alSDoes It Take'~'~'~
· Activities don't always mean success.
o Effort doesn't always make success.
· Money alone doesn't always mean success.
· What Works:
Goal & Data Driven £eadership
- Focused Coordinated Instruction
- Dedicated, Motivated, Quali~ Staff
Perceatage of Second-Gradem Reading Below
Grade Level
25.6
1995 1996 1997 1998 1999 2000 2001
Year
AP: Number of Scores at Each
Score Point
20O 177 t68
150 11G 117 114 131
$0
Percentage of Schools Accredited in 2001 ·
134 Virginia School Divisions
i ESottom25%'jJ ~25%. 2nd25% [j Top25% .]
"Teacher effectiveness has a
greater influence on student
academic growth than any other
factor, including class size,
ethnicity, location, or poverty."
University of Tennessee Study
IAustere Budget
· State Budget Mess
· 9/11 and Fear of Recession
· Use of"One Time Money" in 2002
· Other Strains on County Budget
· Hunker Down - Plan For Disaster
-No New Initiatives.
- Level-funding of schools~departments
March 20, 2002
· Conditions more favorable since
November
· Still Austere
· Other County Needs
] What Works??? ]
· Goal & Data Driven Leadership
- Focused Coordinated Instruction
· Dedicated, Motivated, Quality
Staff
Success for Albemarle 'l'
County Schools Requires...
~~ to Reward
Driven // / ~ ~ ~ High-
Leadership / / [ I ~",.performing
~ [ J ",,,,_..... Staff
Focused Coordinated Instruction
RECEIVED AT BOS MEETING
Date: -.-~-- ~ - =,~ ~,~-
Agenda Item #:
Clerk's Initials: ~'~z'b ~
3/20/02
Albemarle County
Joint Board Update
Compensation and Benefits
For
2002-2003
March 2002
Joint Board Adopted .
and Benefits
Compensation .
Strategy To Ach~eve..a. nd
Maintain Market Pos~t~on
· Base Salary
· At market levels (i.e., 100th percentile)
Benefits
· Slightly above market levels (i.e., 105th
percentile)
3/20102
3/20/02
Why we need to stay at market
Valuing our employees · Ability to Attract, Retain, and Motivate
· Externally competitive
· Internally equitable
· Flexible
· Simple to administer and.communicate
· Viable classified/administrator
performance-based pay
IWhere we were
Competitive Review
CLASSIFIED SCALE
CLOSING THE GAP
FY~I FY 01J02
Market · Albonmrle J
2
3/20/02
Competitive Review
TEACHER'S SCALE
IWhere we were
Market Salary Survey - July 2001
Market Salary Survey Data
50000 il ~ r-ca r.~ I
4oooo~ _ ~ t~1~1-11~
Sa*ar~ 2oooot~~~1~I1:1~
E E E E
E m m E
Step
lla Market
la Nbemade
Where we were
November 2001
Staff Recommi~ndations
· Initially proposed adopting a 4.3% salary
increase (based on WorldatWork data)
· After Sept. 11th, revised increase to
3.3%for 2002~2003 (based on
WorldatWork data)
· Adopt 3.0% salary scale adjustment for
2002~2003
· Plan on 16% increase in medical
insurance plan
3/20/02
I Where we were
Board Budget Direction in
No~ember
Build the budget based on'
· 2.0% salary increase for teachers and
classified staff
· No increase in medical insurance
premiums for employees
3/'20/02
· Directed staff to resurvey the market
and advise
I Where we are
Current Status
(March 2002)
· Market Forces · Local business forecast
· Unemployment levels
· Cost of living
· Competitiveness of Total
Compensation (salary and benefits)
3/20102
8
3/20/02
I Where we are
Chamber of Commerce
2002 Local Business Forecast
· Local economy is changing
· 41% expect employment level to rise
· 56.6% expect employment level to
hold steady
· 57.8% expect increased profits
· 73.8% expect rise in operating costs
· Source: Charlottesville Regional Chamber of Commerce
Economic Survey for 2002
3/20/02
~* " I Where we are
Unemployment Levels
3/20/02
· Charlottesville area still has one of the
lowest unemployment levels in Virginia
· Change since July
· Albemarle
+ 1.4% in July
+ 1.9% in December
+ 2.4% in January
· , Charlottesville + 2.3% in July
+ 2.1% in December
+ 2.8% in January
· Source: Virginia Em ployment Commission
lO
3/20/02
Cost of Living
Charlottesville has the 2nd
highest Cost of Living of the
8 largest urban areas in Virginia
I Where we are
· Charlottesville is second only to
Northern Virginia
· Source: American Chamber of Commerce
Research Association 3rd Qtr 2001
3/20/02
IWhere we are
Competitive Market Survey
· 30 localities/organizations
surveyed in the Board adopted
market
· 20 organizations responded to
the salary survey
3/20/02
· 2'1 organizations responded to
the medical insurance survey
12
6
3/20/02
Where we are
Survey Results - Salary
Teachers
· 4.1% average salary increase
· 3.8% median salary increase
· Classified · 3.8% average salary increase
· 3.5% median salary increase
3/20/02
13
IWhere we are
Survey Results - Medical
Insurance
Albemarle Board contribution rate · Employee Only 95.5%
· Employee+Family No add'l
· 'Survey of Board contributions for
medical insurance (average)
· Employee Only 91.5%
· Employee+Family Add'l 26.6%
3/20/02
14
7
3/20/02
Where We Are Now vs. Market
Teacher Salary Market Data
101.0% ~ nn no/_ 4 nn no/~.~
lOO.O% ............
99.0% ~
98.0%
97.0%
Now 2% 3.8%
Proposed Market
Percentage Of Market
3/20/02
15
3/20/02
Where We Are Now vs. Market
Classified Salary Market Data
102.0% !00.0°/-
100'0% t 97.5%
96.0%
94.0%
Now 2% 6%
Proposed Market
Percentage Of Market
16
3/20/02
Board Contribution For
Medical Insurance
I~,,OOO,O00
ILO00,OOO
I0,000,000
~ ~,000,000
3120102
17
3/20102
I Where
we are
Actions To Achieve
Board Strategy
To Achieve Market:
· 3.8% salary increase for teachers
based on median of market (includes
step and scale adjustment)
· 6.0% merit pool for classified
employees based on median of
market (adjust the scale)
· $3,840 Board contribution per
employee to cover full increase in
medical costs
18
9
3/20/02
Staff Recommendations
· 3.3% to 4.3% salary increase for
both teachers and classified
(based on WorldatWork data)
· $3,840 Board contribution to
cover full increase in medical
insurance
3/20102
Develop long-term plan to reach
market for classified employees
19
Funding Impacts
· Each additional 0.1% increase in salary's
requires the following additional funding:
· School General Fund - $69,000
· General Government Fund - $23,000
3/20/02
20
10
County General Fund
Beginning Board Reserves
Less County Executive Adjustments
Agency Request - SHE to provide funding increase @ 2.5%
MACAA Teen Pregnancy Prevention Program funding
FICA for Parks & Recreation Summer P-T employees
Commonwealth's Attorney-continuation of full salary for 1 staff
Commission on Children & Families
Adjust Benefits for Senior Planner (1/2 yr)
Subtotal -- Subtract
Recurring One-Time
405,597 850,000
941
32,656
20,000
12,000
1,766
1,900
69,263 0
Plus County Executive Resource Changes
Parks & Recreation Fees (increase $1 on Entry Fees)
35,000
Subtotal - Add
35,000
Less Board of Supervisors' Adjustments
Subtotal ~ Subtract
Plus Board of Supervisors Resource Changes
increaSe E~911 surcharge by $0;36 to $1.75 for Fire Dispatch
Provide Tourism Funds for ACE/Other
Subtotal- Add
220,968
450,000
220,968
450,000
670,968 220,968 450,000
ear
increase Compensation by 1.3% (to 3.3%)
Administration
1~0 FTE Budget Analyst ! (Octi I hire)
Judicial
295,000
54,225
295,000
39,731
1,250
Public Safety
Adjusted request for Regional Jail operations & operating reserve
Adjusted request for BRJDC
1 0 FTE Fire/Rescue Trainer (Jan 2003 Hire)
1:0 FTE Police Officer (Jan! 2003 Hire)
Fire Dispatch Center Cost (Option 2)
Human Development
Commision on Children & Families
152,731 52,731 100,000
26,370 26,370
45,189 22,595
72,750 21,375 30,000
219,000 219,000
18,000
18,000
Parks and Recreation
Library
30,000
30,000
No RevOption FY03 BOS Budget Worksheet 3-20-02.xls Page 1 of 2 Printed 3/20/02 4:33 PM
County General Fund
Community Development
1:0 FTE Senior Planner (Jan~ 2003 Hire)
ACE (Tourism Fund)
ACE (General Fund)
School Division
Recurring One-Time
65,068 28,329 8,410
450,000 450,000
550,000 550,000
Additional Initiatives Funded
1,978,333 726,761 1,166,030
School Division
Plus Additional Ongoing Resources - School Division
Subtotal
0
Plus Additional One-Time Resources - School Division
Subtotal
0
IT°ta` Sch°°l B°ard Resources 911,0021
Unfunded School Board Initiatives:
No RevOption FY03 BOS Budget Worksheet 3-20-02xls
Page 2 of 2
Printed 3/20/02 4:33 PM
County General Fund
Beginning Board Reserves
Less County Executive Adjustments
Agency Request - SHE to provide funding increase @ 2.5%
MACAA Teen Pregnancy Prevention Program funding
FICA for Parks & Recreation Summer P-T employees
Commonwealth's Attorney-continuation of full salary for 1 staff
Commission on Children & Families
Adjust Benefits for Senior Planner (1/2 yr)
Subtotal -- Subtract
Recurring One-Time
405,597 850,000
941
32,656
20,000
12,000
1,766
1,900
69,263 0
Plus County Executive Resource Changes
Parks & Recreation Fees (Increase $1 on Entry Fees)
Subtotal - Add
35,000
Less Board of Supervisors' Adjustments
Subtotal- Subtract
35,000
Plus Board of Supervisors Resour~ce Changes
Increase vehicle decal fee by $3.50 (40% local/60% school)
Increase E-911 surcharge by $0.26 to $1 65 (no F re D spatch ncrease)
Provide Tourism Funds for ACE/Other
Subtotal- Add
262,500 262,500
159,588 159,588
450,000
450,000
1,093,056 643,056 450,000
Subtract School Share of Vehicle Decal Revenues
157,500
Increase Compensation by 1.3% (to 3.3%)
Administration
1.0 FTE Budget Analyst I
Judicial
295,000 295,000
54,225 52,975
1,250
Public Safety
Adjusted request for Regional Jail operations & operating reserve
Adjusted request for BRJDC
1.0 FTE Fire/Rescue Trainer
152,731 52,731
26,370
45,189 45,189
100,000
26,370
Human Development
Commision on Children & Families
18,000 18,000
Parks and Recreation
Library
30,000 30,000
Option 2 FY03 BOS Budget Worksheet 3-20-02.×1s
Page 1 of 2
Printed 3/20/02 4:35 PM
County General Fund
Recurring One-Time
Community Development
1.0 FTE Senior Planner 65,068 56,658 8,410
ACE (Tourism Fund)
ACE (General Fund) 450,000 450,000
550,000 550,000
School Division
Additional Initiatives Funded
1,978,333 812,303 1,166,030
School Division
~Avaiiabie S~h~l ~ Rese~e
Plus Additional Ongoing Resoumes - School Division
Subtotal
0
Plus Additional One-Time Resources - School Division
Subtotal
0
l Total School Board Resources 9tl,0021
Unfunded School Board Initiatives:
Option 2 FY03 BOS Budget Worksheet 3-20-02.x15
Page 2 of 2
Printed 3/20/02 4:35 PM