HomeMy WebLinkAboutARB201400140 Certificate of Appropriateness 2015-01-26COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, North Wing
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
January 26, 2015
Ryan Lorey
Edens
7200 Wisconsin Ave Ste 400
Bethesda, MD 20814
RE: ARB -2014-140: The Shops at Stonefield Phase 2 Block G
Dear Ryan,
I have reviewed the plans listed on the following page, submitted for the above referenced project. The
changes made in these plans address the conditions of approval outlined at the ARB meeting held on
January 20, 2015. You may consider this letter your Certificate of Appropriateness.
This approval is predicated on the fact that the design and materials, as proposed and exhibited for review,
will be used. The acceptance of approval implies that the applicant has agreed to execute the design as
indicated on the site plan, attachments, materials, samples, and other submittal items presented. Any
change in the approved design or materials will require an amendment to the plan and must be reviewed
and approved by the Architectural Review Board.
Please note the following:
1. This application is approved with the condition that mechanical equipment shall not be visible from the
Entrance Corridor.
2. Certificates of Appropriateness are valid for the same period that the corresponding site plan is valid. If
there is no site plan required for the proposed work, the Certificate of Appropriateness is valid for 3
years. Applicants requesting an extension of the period of validity must do so in writing. The letter
must be received by the Director of Planning prior to the expiration date.
If you have any questions, please do not hesitate to call.
Sincerely,
Margaret Maliszewski
Principal Planner
cc: ARB -2014-140
Sheet #
Drawing
Revision Date
10
Cover Sheet
2-6-2015
12
Comment Responses & Narrative
2-6-2015
C6
Existing Conditions & Demolition Plan
2-6-2015
C7
Site Layout Plan
2-6-2015
C8
Grading and Drainage Plan
2-6-2015
C9
Water & Sanitary Sewer Layout Plan
2-6-2015
C-22
Landscape Plan
2-2-2015
C-23
Landscape Details
2-2-2015
LT1
Site Lighting
2-6-2015
LT2
Site Lighting
2-6-2015
AO
Material Schedule and Key Plan
2-6-2015
Al
Building G 1
2-6-2015
A2
Building G2
2-6-2015
A3
Building G3
2-6-2015
A4
Building G4
2-6-2015
A5
Entrance Corridor Views
2-6-2015
A00
Com rehensive Sign Plan
3-6-2015
CSP -1
Com rehensive Sign Plan
4-1-2015
CSP -2
Comprehensive Sign Plan
4-1-2015