Unaddressed previous comments:
1. Regarding proffer 3; the proffer needs clarification and updating. It is unclear what an "in -only
entrance" is exactly. There is no "Engineering Department".
2. Regarding proffer 7; this proffer needs updating. It may need to refer to "initial site plan " in the
county process. County Engineering should refer to County Engineer.
New comments:
The proposed improvements plan shows an inaccurate WPO buffer of 50 feet. The WPO buffer is
100 feet and should be shown as such. Disturbances within the WPO buffer must be approved by
the program authority. Types of structures, improvements and activities which may be allowed in
a stream buffer by the program authority can be found in Albemarle County Code 17-604.
2. The provided John McNair & Associates plan, dated 4/29/2002, shows a "proposed FEMA 100 -
year flood limit" that appears to be contingent upon the topography proposed with that plan. Your
new plan, dated 3/9/2015, shows what appears to be the same floodplain limits, labeled as
"approved 100' year floodplain per approved FEMA map revision". This floodplain limit does
not appear to be consistent with the FEMA LOMR dated 8/8/2008 (below). When/how were the
floodplain limits you're showing approved? Is there a more recent LOMR for this area?