Project title:
Project file number:
Plan preparer:
Owner or rep.:
Plan received date:
Date of comments:
Reviewers
VSMP Permit plan review
Oak Hill Phase 2 Sanitary Sewer Project
WP0201500003
O'brien & Gere
Jeremy M. Lynn
12 March 2015
Rev. 9 June 2015
27 March 2015
Rev. 11 June 2015
Max Greene
b lynn @serviceauthority. org]
County Code section 17 -410 and Virginia Code §62.1- 44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is Approved. The
rationale is given in the comments below. The VSMP application content requirements can be
found in County Code section 17 -401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17 -405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Requirement appears adequately addressed at this time.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17 -404.
1. Requirement appears adequately addressed at this time.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25- 870 -108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is approved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17 -403.
1. Linear Public utility installation is currently not required to submit a storm water protection plan.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1- 44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is approved with conditions, and the reasons are provided in the comments below. The
erosion control plan content requirements can be found in County Code section 17 -402.
Silt fence needs to be shown with up -turned ends on all silt fence locations so water is forced to
filter through the fabric instead of exiting from the ends. Please see Std. & Spec. plate 3.05 -2 for
example of how ends of silt fence should be higher than top of middle or low point in silt fence
Engineering Review Comments
Page 2 of 2
alignment.
Comment adequately addressed.
2. Please submit 2 copies of the revised plans for approval stamp. Comment adequately addressed.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms, which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2 -4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre - construction conference.
Applicants will need to complete the request for a pre - construction conference form, and pay the remainder
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre - construction
conference will be scheduled with the County inspector. At the pre - construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
http://www.albemarle.org/deptforins.asp?department=cdengmTo
File: E1_vsmp_ review projectname.doc