HomeMy WebLinkAboutSP201500021 Review Comments Special Use Permit 2015-07-02Short Review Comments Report for:
SP201500021
SubApplication Type:
Tandem Friends School - Middle School Expansion
Amend Existing Special Use Permit
Date Completed:07/02/2015
Reviewer:Scott Clark CDD Planning
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:06/15/2015
Reviewer:Troy Austin VDOT
Review Status:No Objection
Reviews Comments:
Division:
Date Completed:05/21/2015
Reviewer:Francis MacCall CDD Admin Zoning Review
Review Status:QC OK
Reviews Comments:
Division:
Date Completed:06/04/2015
Reviewer:Jay Schlothauer CDD Inspections
Review Status:No Objection
Reviews Comments:
Division:
Date Completed:06/09/2015
Reviewer:Margaret Maliszewski CDD ARB
Review Status:No Objection
Reviews Comments:The proposed building is not expected to be visible from the Entrance Corridor.
Division:
Date Completed:06/06/2015
Reviewer:Robbie Gilmer Fire Rescue Admin
Review Status:See Recommendations
Reviews Comments:Based on SP dated 5/18/15
Fire Rescue is not opposed to the approval of the SP, but something to keep in mind when moving
forward with this project. The fire hydrant located behind the Math and Science building will need to
be relocated, to a usable location on the northwest corner of the fire department turn around.
Division:
Date Completed:06/26/2015
Reviewer:John Anderson CDD Engineering
Review Status:See Recommendations
Reviews Comments:All comments are Minor-
1. Special Permit –Engineering Div. does not object to proposed request to expand Tandem
Friends School middle school.
2. Site Plan Amendment –Advance comments
a. Ensure paved traffic circle in front of 3-story middle-grades building meets ACDSM, F. Street
Standards, concentric cul-de-sac with unpaved center design standard; R =30’ Min., Unpaved Area
(Attached).
b. ‘Proposed parking lot islands and striping are shown per Approved Site Plan Amendment
SDP 1998-00119’ label is confusing. GIS shows parking lot is existing. It may be better to revise
label for clarity: Exist. Parking Lot. Islands and striping per Approved…’
c. It appears that Tandem Lane, which intersects Mill Creek Drive at two points, will be
discontinuous, with south entrance dedicated to fire/rescue access. T-type turnarounds and
branch-type turnarounds have been discontinued. Please revise proposed Fire Department
turnaround (ref. Attached –ACDSM, F. Detail).
d. Show Managed Steep Slopes (ref. County GIS).
e. Site Plan Amendment approval requires Approved WPO/VSMP Application.
3. (VSMP Advance comment) – Ensure that change in ground cover and runoff characteristics
are properly addressed. It may be possible to demonstrate WPO Part IIB compliance using single
proposed ‘Potential SWM Area’ shown east of new building on the Concept Plan, but drainage divide
directs gym expansion runoff west; it will not reach the SWM Area. Applicant discussion of ‘Impacts
on Environmental Features’ is comprehensive. No objection.
janderson2 6/26/2015 4:29 PM
Division:
Page:1 of 2 County of Albemarle Printed On:December 07, 2016
discontinuous, with south entrance dedicated to fire/rescue access. T-type turnarounds and
branch-type turnarounds have been discontinued. Please revise proposed Fire Department
turnaround (ref. Attached –ACDSM, F. Detail).
d. Show Managed Steep Slopes (ref. County GIS).
e. Site Plan Amendment approval requires Approved WPO/VSMP Application.
3. (VSMP Advance comment) – Ensure that change in ground cover and runoff characteristics
are properly addressed. It may be possible to demonstrate WPO Part IIB compliance using single
proposed ‘Potential SWM Area’ shown east of new building on the Concept Plan, but drainage divide
directs gym expansion runoff west; it will not reach the SWM Area. Applicant discussion of ‘Impacts
on Environmental Features’ is comprehensive. No objection.
janderson2 6/26/2015 4:29 PM
Date Completed:06/25/2015
Reviewer:Francis MacCall CDD Zoning
Review Status:See Recommendations
Reviews Comments:1. It appears that in their narrative they mention using TMP 91-8 for the school as well. I am
not sure if this was discussed at the preapp. If not then that should not be part of this application. I
am only seeing Parcel 2A referenced in the legal ad. Use of Parcel 8 would need further amendment
to the Tandem SP.
2. No objection to the use proposed for middle school building. Only a small revision to the
concept plan is recommended.
a. The concept plan with SP2013-19 had specifics regarding the parking and landscaping near
the field house and some HC parking. Please make sure that the proposed concept plan reflects
those changes from SP-2013-19 concept plan. If the note on the plan is OK by Planning then it
should be revised to reference the landscaping from the 1998 site plan.
Division:
Page:2 of 2 County of Albemarle Printed On:December 07, 2016
A
�jRGIl`IlA
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, North Wing
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4176
July 2, 2015
Mr. Michael Myers, P.E.
Dominion Engineering
172 South Pantops Drive
Charlottesville VA 22911
RE: SP201500021 Tandem Friends School — Middle School Expansion
Dear Mike --
Thank you for the recent application for this special use permit. Please find review comments
included in this letter.
Please see the attached re- submittal schedule for a list of dates on which you can submit your
revisions and responses to review comments (below and attached), as well as for possible
Planning Commission dates. (Please note that the listed dates are the earliest possible, but actual
dates need to be selected to suit the revision schedule for each project.)
Review Comments
Planning (Scott Clark)
The conceptual plan shows a building envelope, but the narrative does not give a
proposed maximum building footprint. Please provide what information you have on
that size.
Please confirm that the maximum three stories shown in the note on the building
envelope include the basement, and that three stories above ground are not proposed.
This note should be clarified on the plan. Note that there is a maximum structure
height of 35 feet in the R1 zoning district.
Rather than the "preservation/conservation area" that is currently shown (with the
accompanying note containing several possible exceptions), it would be better to
show the existing and approximate proposed tree line after development. We
appreciate the effort to retain as much tree cover as possible.
Please note that I have contacted VDOT and addressed the first question included in
their comments.
Please note that the outstanding notification fees ($405.30) must be paid before this
application can be scheduled for public hearings.
Zoning (Francis MacCall)
1. It appears that in their narrative they mention using TMP 91 -8 for the school as well.
I am not sure if this was discussed at the preapp. If not then that should not be part of
this application. I am only seeing Parcel 2A referenced in the legal ad. Use of Parcel
8 would need further amendment to the Tandem SP.
2. No objection to the use proposed for middle school building. Only a small revision to
the concept plan is recommended.
a. The concept plan with SP2013 -19 had specifics regarding the parking and
landscaping near the field house and some HC parking. Please make sure that
the proposed concept plan reflects those changes from SP- 2013 -19 concept
plan. If the note on the plan is OK by Planning then it should be revised to
reference the landscaping from the 1998 site plan.
Historic Resources /Architectural Review Board (Margaret Maliszewski)
The proposed building is not expected to be visible from the Entrance Corridor.
Engineering (John Anderson)
All comments are minor:
1. Special Permit — Engineering Div. does not object to proposed request to expand
Tandem Friends School middle school.
2. Site Plan Amendment — Advance comments
a. Ensure paved traffic circle in front of 3 -story middle - grades building meets
ACDSM, F. Street Standards, concentric cul -de -sac with unpaved center
design standard; R =30' Min., Unpaved Area (Attached).
b. `Proposed parking lot islands and striping are shown per Approved Site Plan
Amendment SDP 1998 - 00119' label is confusing. GIS shows parking lot is
existing. It may be better to revise label for clarity: Exist. Parking Lot.
Islands and striping per Approved...'
Fire /Rescue (Robbie Gilmer)
Fire Rescue is not opposed to the approval of the SP, but something to keep in mind
when moving forward with this project. The fire hydrant located behind the Math and
Science building will need to be relocated, to a usable location on the northwest corner of
the fire department turn around.
Virginia Department of Transportation (Troy Austin)
Please see attached memo.
If we have not received a response from you within 30 days, we will contact you again. At that
time, you will be given 10 days to do one of the following: a) request withdrawal of your
application, b) request deferral of your application to a specific Planning Commission date as
mutually agreed to with staff, or c) request indefinite deferral and state your justification for
requesting the deferral. If none of these actions is taken, staff will schedule your application for
a public hearing based on the information provided with your original submittal.
Please be advised that, once a public hearing has been advertised, only one deferral prior to the
Planning Commission's public hearing will be allowed during the life of the application. The
only exception to this rule will be extraordinary circumstances, such as a major change in the
project proposal by the applicant or more issues identified by staff that have not previously been
brought to the applicant's attention. As always, an applicant may request deferral at the Planning
Commission meeting.
Please feel free to contact me if you wish to meet or need additional information. I would be
happy to meet with you to discuss the issues raised by this application.
Sincerely,
Scott Clark
Senior Planner, Planning Division
AIL
[ IRCI*«
County of Albemarle
Department of Community Development
Memorandum
To: Scott Clark, Senior Planner
From: Francis MacCall, Principal Planner
Division: Zoning
Date: June 25, 2015
Subject: SP 2015- 0121Tandem Friends School Amendment - initial zoning
comments
Please consider the following comments.
1. No objection to the use. Only a small revision to the concept plan is recommended.
a. The concept plan with SP2013 -19 had specifics regarding the parking and
landscaping near the field house and some HC parking. Please make sure that
the proposed concept plan reflects those changes from SP- 2013 -19 concept
plan. If the note on the plan is OK by Planning then it should be revised to
reference the landscaping from the 1998 site plan.
AIL
[ IRCI*«
County of Albemarle
Department of Community Development
Memorandum
To: Scott Clark, Senior Planner
From: Francis MacCall, Principal Planner
Division: Zoning
Date: June 25, 2015
Subject: SP 2015- 0121Tandem Friends School Amendment - initial zoning
comments
Please consider the following comments.
1. It appears that in their narrative they mention using TMP 91 -8 for the school as well. I
am not sure if this was discussed at the preapp. If not then that should not be part of
this application. I am only seeing Parcel 2A referenced in the legal ad. Use of Parcel 8
would need further amendment to the Tandem SP.
2. No objection to the use proposed for middle school building. Only a small revision to the
concept plan is recommended.
a. The concept plan with SP2013 -19 had specifics regarding the parking and
landscaping near the field house and some HC parking. Please make sure that
the proposed concept plan reflects those changes from SP- 2013 -19 concept
plan. If the note on the plan is OK by Planning then it should be revised to
reference the landscaping from the 1998 site plan.
4
a , %
COMMONWEALTH of VIRGINIA
DEPARTMENT OF TRANSPORTATION
i6II1 Orange Road
Culpeper,,tiirg n a 2270
Charles A.Kilpatrick,F.E.
Commissioner
June 15,2015
Mr.Scott Clark
Senior Planner
County of Albemarle
401 McIntire Road
Charlottesville,VA 22902
Re: SP-2015-00021 Tandem Friends School--Middle School Expansion
Dear Mr.Clark:
We have reviewed the special use permit request and plan for the proposed middle school
expansion at Tandem Friends School and offer the following comments:
1. We need clarification on the use of the proposed new building. The narrative indicates
that the new building will have a maximum enrollment of 130 students and teachers. If
that is the case,how is total enrollment/trips generated not going to increase?
2. Tandem lane currently loops around the school complex with an ingress/egress entrance
onto Mill Creek Drive to the north and a egress only entrance to the south. The proposed
building is shown to break this loop,resulting in all traffic being forced to use the
northern entrance. Is that entrance adequate to accommodate all generated trips of the
school?
If you need additional information concerning this project,please do not hesitate to contact me at
(434)422-9782.
Sincerely,
1 /1141: 4
Troy stip,P.E.
Area Land Use Engineer
Culpeper District
WE KEEP VIRGINIA MOVING
1 40
IMF
COMMON W EALI if of VIRq NIA
SPPwt R♦CA OF , MNaPuRi,9i UR
Orange Road
Cd—n V .fmi- 22701
Charles A. KIlpa,rlcR, P.E.
C;omRRiz;z;ieRzP
June 15, 201 a
M,. Scott ClarK
Senior P[a,,er
County of Aloemr.HC
401 McIntire Road
Charlottesville_ VA 22902
Re: SP- 2015 -00021 Tandem, Friends Schaal Middle School Expansion
Dear Mr. Clark:
We nave reviewed the special use permit request and plan for the proposed middle scnuul
%,Xpansion at Tandem Friends School and Otte, the fullvwi,,g comments:
I . We need clarification on the use of tnz; proposed vic,ry building. Tne narrative i„dicates
,hat the new building will have a maximum enrollment ur 130 student3 and teaches. It
that is the cabe, how is to,al e,uollment/trips generated not going to increase:
2. Tan5cm [tine curre „t[y maps around the school cumplex with an ingress ?egress entrance
onto Mill CreZK Drive to the north and a egress only unt,a„ce to the bumh. The proposed
building is shown to break this loot,, ,Z3.1ting in an traffic being turced tu u5e the
northeut entrance. Is that entrance adequate to accomn,zdatz all generated trips ut the
SLnool'i
if you need addition,.i inmrmation cv „xerning this p,nject, please do no, hesitate to contact me at
(434) 422 -9782.
Si„ce,ely,
I
Troy sti,,, P.E.
Aru Land Uac Engineer
Culpeper District
vv= K =EP vjRGINIA MOVING
y}.� r i `lui -A
:.�c t,
1 7131
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road,North Wing
Charlottesville,Virginia 22902-4596
Phone(434)296-5832 Fax(434)972-4126
Memorandum
To: Mr. Paul Erb
From: Scott Clark, Senior Planner
Date: March 9, 2015
Subject: Mandatory pre-application meeting for Tandem Middle School Expansion
The following are County staff comments regarding the above noted pre-application meeting. This meeting
satisfies the requirement for a pre-application meeting prior to submittal of your zoning map amendment
application ("rezoning") and/or a special use permit application. The purpose of for the meeting is summarized
below:
The purposes for a pre-application meeting are to:(i)provide the applicant and the county a common
understanding of the proposed project; (ii)inform the applicant about the proposed project's consistency
with the comprehensive plan, other relevant policies, and county regulations; (iii) broadly identify the
planning, zoning and other issues raised by the application that need to be addressed by the applicant; (iv)
inform the applicant about the applicable procedure;and(v) allow the director to identify the information
the applicant must submit with the application, including the supplemental information delineated in
subsection (c). Receiving the relevant supplemental information will allow the application to be
comprehensively and efficiently reviewed.
As we understand it, your plan is to remove an existing school building and build a new, larger one for middle-
school students, without changing the permitted enrollment.
The following are staff comments:
(ii) Consistency with the Comprehensive Plan:
• Given that enrollment would not expand and the character of the use would not change, we feel that
Comprehensive Plan issues have been sufficiently addressed in prior approvals.
(iii) applicable procedures
• Community Meeting—the applicant is required by ordinance to undertake a community meeting process
as part of the review of the SP request. This meeting should be held, if possible, within 30 days from the
date the rezoning application is submitted, and can be held prior to the submittal of the rezoning
application.Adjacent property owners and neighborhoods(and the Coordinating Reviewer/planner)
should receive advance notification of this meeting (date/time/location).
• If the applicant knows of any of any waivers or modifications that are needed to implement the proposed
plan, staff recommends that those requests be submitted with the initial application. Staff will then
determine if the waivers should be approved with the rezoning action or deferred for action with site plan
and/or subdivision plat approval.
2
(iv) Identify the information the applicant must submit with the application, including the supplemental
information
• A conceptual plan should be submitted with the special use permit application.
■ As discussed in the meeting, a building envelope would be an acceptable alternative to specific
building design/location on the plan, provided that the application narrative includes proposed
limits on building size and height.
• The conceptual plan should include the parking design shown in the last approved site plan.
• Unless you definitely plan to discard the recently-approved gym design for some other
approach, it would be better to include that design on the plan, rather than the old one.
• Attached SP Checklist—please see the checklist for items to be included on the conceptual plan
If you have any further questions, please contact me.
Sincerely,
Scott Clark
Senior Planner