HomeMy WebLinkAboutSDP201400032 Review Comments 2015-08-19Short Review Comments Report for:
SDP201400032
SubApplication Type:
Montessori Community School - Minor
Minor Amendment
Date Completed:04/24/2014
Reviewer:Rachel Falkenstein Planning
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:04/21/2014
Reviewer:John Anderson Engineering
Review Status:Requested Changes
Reviews Comments:The stormwater management plan does not appear to follow the concept plan approved with the
special use permit(s) for this property. In addition, there is not enough information to know whether
the proposal would meet the requirements of the Water Protection Ordinance. I have invited the
designers to meet with us to discuss these issues prior to submitting revisions. That meeting is
pending. This will potentially have a significant effect on the layout of the proposed site plan minor
amendment.
Division:
Date Completed:04/02/2014
Reviewer:Jay Schlothauer Inspections
Review Status:No Objection
Reviews Comments:Based on plans dated March 31, 2014.
No comments or conditions.
Division:
Date Completed:04/18/2014
Reviewer:Margaret Maliszewski ARB
Review Status:Requested Changes
Reviews Comments:The site plan amendment corresponds to ARB-2013-180, which was reviewed by the ARB on
January 21, 2014. The action letter from that meeting outlined the revisions required for ARB
approval. A resubmittal for ARB-2013-180 is required. See the action letter dated January 24, 2014.
Division:
Date Completed:05/05/2014
Reviewer:Alexander Morrison ACSA
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:04/17/2014
Reviewer:Robbie Gilmer Fire Rescue
Review Status:Requested Changes
Reviews Comments:Based on plans dated 3/31/14
1. FDC location shall be on the address side of the building and with in 50 ft of a fire hydrant.
2.Fire Flow test is required before final approval.
Division:
Date Completed:04/22/2014
Reviewer:Troy Austin VDOT
Review Status:No Objection
Reviews Comments:
Division:
Page:1of4 County of AlbemarlePrinted On:November 09, 2015
Date Completed:04/15/2014
Reviewer:Andrew Slack E911
Review Status:Approved
Reviews Comments:Approved.
Division:
Date Completed:05/20/2014
Reviewer:Rachel Falkenstein Planning
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:05/20/2014
Reviewer:Margaret Maliszewski ARB
Review Status:Requested Changes
Reviews Comments:An ARB resubmittal has been received and is under review. Comments will be provided when that
review is complete.
Division:
Date Completed:05/29/2014
Reviewer:John Anderson Engineering
Review Status:Requested Changes
Reviews Comments:1. Ensure that revisions to plan sheet 4 (Phase 1 Layout and Dimension Plan) in response to
engineering comments are included. Comments relate to curb radii, length of a section of curb, and
sidewalk width.
2. Ensure that revisions to plan sheet 16 (Phase 1 Planter Plan Sections & Details) in response to
engineering comments are included. Comments (ref W PO project comments, 2014-May-28):
Plan-profile views require a scale to aid review and construction. Label bottom of wall elevation for
each wall shown in rain garden/sub-grade storage profile view. Show dimensions for RG-1, 2, 3, 4,
and sub-grade SW storage (beneath permeable pavers; plan view). Furnish RG-5
details/dimensions, including connection with inlet B3.
Division:
Date Completed:07/15/2014
Reviewer:Alexander Morrison ACSA
Review Status:Approved
Reviews Comments:The ACSA hereby recommends approval of the above referenced site plan.
Division:
Date Completed:07/16/2014
Reviewer:Robbie Gilmer Fire Rescue
Review Status:Approved
Reviews Comments:I’ve spoken with Alex Morrison with ACSA and we both agree that the plan can be approved with the
conditions that the final C.O. is not released until the sprinkler system or water line are finished. This
is a condition we discussed with Chris so that the project wouldn’t get held up while they decide on
the sprinkler system or water line upgrade.
Division:
Date Completed:05/23/2014
Reviewer:Margaret Maliszewski ARB
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:06/25/2014
Reviewer:Rachel Falkenstein Planning
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:06/24/2014
Reviewer:Margaret Maliszewski ARB
Review Status:Requested Changes
Division:
Page:2of4 County of AlbemarlePrinted On:November 09, 2015
Reviews Comments:
Date Completed:06/23/2014
Reviewer:John Anderson Engineering
Review Status:No Objection
Reviews Comments:Comments addressed
Division:
Date Completed:07/08/2014
Reviewer:Margaret Maliszewski ARB
Review Status:Approved
Reviews Comments:
Division:
Date Completed:07/18/2014
Reviewer:Rachel Falkenstein Planning
Review Status:Approved
Reviews Comments:
Division:
Date Completed:09/23/2014
Reviewer:Rachel Falkenstein Planning
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:09/23/2014
Reviewer:Margaret Maliszewski ARB
Review Status:Requested Changes
Reviews Comments:An ARB submittal is required for the proposed landscaping changes.
Division:
Date Completed:09/25/2014
Reviewer:John Anderson Engineering
Review Status:No Objection
Reviews Comments:Removal of guardrail at east end of parking lot leaves 6” curb and 5’ sidewalk. This is a low-speed
student dropoff/staff parking area. Moderate to low risk of road runoff, and absent underlying site
plan requirement specifying guardrail in this instance, no objection to proposed change to approved
site development plan, items 1 or 2: Removal of guardrail; reduction in landscaping plantings (fewer
+ proposed ornamental grass; defer to Planning).
Division:
Date Completed:10/17/2014
Reviewer:Rachel Falkenstein Planning
Review Status:Approved
Reviews Comments:
Division:
Date Completed:10/17/2014
Reviewer:John Anderson
Review Status:See Recommendations
Reviews Comments:App# keyed incorrectly: Engr review, this date, for SWPPP, WPO201400032.
(JA-10/30/14)
Division:
Date Completed:04/17/2015
Reviewer:Rachel Falkenstein Planning
Review Status:Approved
Reviews Comments:
Division:
Date Completed:04/15/2015
Reviewer:Margaret Maliszewski ARB
Review Status:Approved
Division:
Page:3of4 County of AlbemarlePrinted On:November 09, 2015
Reviews Comments:
Date Completed:08/19/2015
Reviewer:Rachel Falkenstein Planning
Review Status:Approved
Reviews Comments:
Division:
Page:4of4 County of AlbemarlePrinted On:November 09, 2015