TO: Chris Perez
FROM: Alexander J. Morrison, P.E., Civil Engineer
DATE: December 8, 2015
RE: Site Plan Technical Review for: SDP201500055: Sunset Overlook — Initial Site Plan
The below checked items apply to this site.
✓ 1. This site plan is within the Authority's jurisdictional area for:
✓
A. Water and sewer
B. Water only
C. Water only to existing structure
D. Limited service
✓ 2.
A RWSA 20 inch water line is located approximately 30' distant.
3.
Fire flow from, nearest public hydrant, located distant from this site plan, is
Gpm + at 20 psi residual.
✓ 4.
An 8 inch sewer line is located approximately 675' distant.
5.
An Industrial Waste Ordinance survey form must be completed.
✓ 6.
No improvements or obstructions shall be placed within existing or future
easements.
7.
and plans are currently under review.
8.
and plans have been received and approved.
9.
No plans are required.
✓ 10.
Final and plans are required for our review and approval prior to
granting tentative approval.
11.
Final site plan may/may not be signed.
✓ 12.
RWSA approval for water and/or sewer connections.
13.
City of Charlottesville approval for sewer.
✓
Comments:
Submit 3 copies of the final utility plan, a water data sheet and a sewer data sheet to the
ACSA for review and approval. The submission shall be directed to the attention of
Michael Vieira, PE.
The ACSA is currently coordinating with the Department of Fire/Rescue on the final
locations for fire hydrants. This information will be provided to the applicant once it is
finalized.
RWSA review and approval for the nwater main connection is required.