HomeMy WebLinkAboutWPO201400090 Correspondence 2014-12-16 Michael Baker Innovation Done Right...We Make a Difference INTERNATIONAL December 16,2014 Justin Deel Department of Community Development County of Albemarle 401 McIntire Road, North Wing Charlottesville,Virginia 22902-4596 RE: WP0201400090 VSMP Permit Plan Review Key West Water Main Replacement The following responses to County comments,dated November 5, 2014,are provided. Responses are provided in bold text. A. Stormwater Pollution Prevention Plan(SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain(1)a PPP,(2)an ESCP,(3)a SWMP,and(4) any TMDL measures necessary. 1. Please use the standard template from the county website. RESPONSE: SWPPP now follows the template from the county website. B.Pollution Prevention Plan(PPP) The PPP content requirements can be found in County Code section 17-404. 1. Please provide. RESPONSE: Pollution prevention plan can be found in section 6 of the SWPPP document. C. Stormwater Management Plan(SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is disapproved,and the reasons are provided in the comments below.The stormwater management plan content requirements can be found in County Code section 17-403. 1. Please provide. RESPONSE: Stormwater Management Plan can be found in section 5 of the SWPPP document. D.Erosion and Sediment Control Plan(ESCP) Virginia Code§62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is disapproved,and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17-402. Michael Baker INTERNATIONAL Mr.Justin Deel December 16, 2014 Page 2 of 2 1. Silt fencing on outside of channel from about STA 9+00 to about STA 13+00 will likely provide little sediment control. Use check dams here or show silt fencing between channel and disturbance. RESPONSE: The silt fence shown between stations 9+00 and 13+00 on sheet 6 of the plans has been removed,and replaced with check dams along the channel. 2. Please provide date and source of topographic information. RESPONSE: General Note 2 on plan sheet 3 was updated to include the date(November 9, 2011) and source of the topographic information(Rinker Design Associates) 3. Provide explanation of and for darkly hatched areas seen throughout plans. RESPONSE: The hatched areas represent gravel surfaces. The line weight has been modified to make it appear less pronounced.The line weight for these areas was changed in the updated plan sheets. 4. Show staging/stockpile area(s)on plans. RESPONSE: In accordance with direction provided from Glenn Brooks to Alex Morrison, the storage and staging areas were not shown on the plans,but rather expressed that the staging and storage area would be moving with the trench since it is a linear construction project.Section 6.6 of the SWPPP report contains this information. Thank you for assistance in this project. If you have any questions or require additional information, please do hesitate to contact me. Sincerely, MICHAEL BAKER INTERNATIONAL. eitse:f...) y,. . ,i6_ , Chip Votava, P.E. Project Manager