Project title:
Project file number:
Plan preparer:
Owner or rep.:
Plan received date:
Date of comments:
Reviewers:
VSMP Permit plan review
Timberwood Commons
WP0201500102
Shimp Engineering, P.C.
PEQUA LLC
7 December 2015
11 December 2015
Max Greene
[Justin@shimp-engineering.com]
[robby@tbmcom.com]
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is denied. The
rationale is given in the comments below. The application may be resubmitted for approval if all
of the items below are satisfactorily addressed. The VSMP application content requirements can
be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. A SWPPP plan is required for final plan approval. This department recommends using the Albemarle
County Template:
http://www.albemarle.org/upload/images/forms_center/departments/Community Development/forms/
Engineering and WPO Forms/Stormwater _Pollution _Prevention _ Plan_ SWPPP_template.pdf
Comment appears adequately addressed at this time
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. A PPP plan is required for final plan approval. The PPP is a portion of the Albemarle County
Template:
http://www.albemarle.org/upload/images/forms_center/departments/Community Development/forms/
Engineering and _WPO _Forms/Stormwater Pollution_ Prevention_ Plan SWPPP_template.pdf
Comment appears adequately addressed at this time
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is disapproved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-403.
A Stormwater Management Agreement is required. Please contact Ana Kilmer for SWM
agreement information.
This item will be addressed after plan approval during the bonding stage, see "Process"
below.
Engineering Review Comments
Page 2 of 3
2. Nutrient credit purchase will need to be approved by the Albemarle County Attorney's Office.
The following information is required"
Documentation of Nutrient Credits required by the County of Albemarle
1. Owner of the parcel must provide a copy of the executed Agreement for Purchase and Sale of
Nutrient Offset Credits and a copy of the Affidavit of Phosphorus Credit Sale. The following
information is required in the affidavit:
a. Owner's Name
b. Project Description as listed in the plan submitted to the County of Albemarle
c. Location/Address of the project
d. Tax Map and Parcel
e. HUC Code of nutrient bank
2. If ownership of the property is in the name of any type of legal entity or organization including,
but not limited to the name of corporation, partnership, limited liability company, trust,
association, etc., documents acceptable to the County must be submitted certifying that the person
that executed the agreement and the affidavit has the authority to do so.
This item is currently being reviewed by the County Attorney's Office.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is approved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. Plan requirements appear adequately addressed at this time.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms, which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
Engineering Review Comments
Page 3 of 3
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the remainder
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
hlt2://www.albemarle.org/deptforms.asl2?department--cdengno
File: CDDE2_vsmp_Review Timberwood Commons_wpo201500102.doc