COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
August 25, 2005
Katurah Roell
Virginia Land Company
195 Riverbend Drive
Charlottesville VA 22911
RE: SDP- 2005 -0011 Hollymead Town Center Area C Block 9 Preliminary Site Plan
Dear Sir:
The Department of Community Development hereby grants administrative approval to the above -
referenced site plan.
The approval of the preliminary site plan is valid for (1) one year in accordance with Zoning Ordinance
Section 32.4.3.1. Therefore, the preliminary approval shall expire August 25, 2006. If the preliminary
site plan approval expires, a new application must be filed and processed.
Please address all of the requirements and conditions listed below and submit eight (8) tentative plan
copies to the Department of Community Development. This letter must be submitted with the tentative
plans, as a checklist, to document that you have addressed all requirements or conditions, or the tentative
plan will be denied.
The Erosion and Sediment Control Plan and the BMP Stormwater Management Plan, with the associated
applications and fees, may also be submitted with the eight (8) tentative Plans. Failure to do so will result
in a separate application to be filed with the Department of Community Development at a later date.
After the initial tentative plan submittal, each department /agency will contact you to discuss any remaining
conditions. After all aforementioned department /agencies have granted a tentative approval, you may
submit the final mylars (2 sets), two paper copies, final site plan application, final site plan fee, and a copy
of all written tentative approvals to the Department of Community Development. Signing of the plans will
occur within one week once it is determined that the final site plan mylars reflect all tentative approvals.
The final site plan will be subject to all final site plan requirements (Zoning Ordinance Section 32.6), in
addition to the following conditions.
1.The Zoning & Current Development Division shall not accept submittal of the final site plan for
signature until tentative approvals for the following conditions have been obtained. The final site
plan shall not be signed until the following conditions are met:
A.Planner approval to include:
1.
32.6.3] Approval ofa landscape plan in compliance with Section 32.7.9. and,2.
32.6.60)] Submittal ofa description and photograph or diagram and show thelocationofeachtypeofoutdoorluminairethatemits3,000 or more initial lumens.Please be aware that installation of such luminaires in the future that are notshownonthisplanshallrequireanamendmenttothisplan. and,3 .
32.6.60)] [4.17.4(b)] Submittal ofa photometric plan on the site plandemonstratingthatparkingarealuminairesareincompliancewith4.17.4 b and,4.
30.6] The final plan approval is subject to the issuance ofa Certificate ofAppropriatenessfromtheArchitecturalReviewBoard.
B.Engineer approval to include:
1 •
Please supply written grading easements for grading on all adjacent parcels thathaveoff -site grading, [DM 1102] and,2.
All existing and proposed easements must be shown on the final site plan.Proposed easements must be recorded before final approval is given. [proffer, 18-32.5.6i, k, m] and,3 .
About a quarter of the site just north of the proposed buildings does not drain to adrainagestructure. This drainage area must be included in the stormwatermanagementplan. [ 32.5.6j,k] and,4.Please show the complete round about and its intersections on the final site plansotheroadgeometrycanbeverified. [18- 32.5.6m] and,5.
The westernmost BMP should be redesigned to capture more stormwater runoffandtoeliminateorreducetheretainingwallalongthedownhillside. [18-32.5..6.k].
The following items must be reviewed and approved by the Engineering Department before tentative
of the final site plan can be granted.tative
1 . A completed application and fee for erosion control and stormwater 17- 20303]management. [3, 17-2. An erosion control plan, narrative and computations.[14 -311, 17 -203]3.
A stormwater management13MP plan and computations. Computations must include wa terquality, and detention routings for the 2yr and 10yr storms. Please include required BMPremovalratecalculations. [17 -304]4 .
A completed stormwater management facilities maintenance agreement and fee. 17 -304
Albemarle County Service Authority approval to include:1.
Final approval win not be granted until a plumbing fixture count to size themetersisprovidedanduntilwaterandsewerconstructiondrawingshavebeenreviewedandapproved.
Please contact me at your earliest convenience if you have any questions or require additional Information.Sincerel
Cz/
Francis H. MacCail
Senior Planner
Zoning & Current Development