HomeMy WebLinkAboutSDP200500149 Review Comments 2006-01-06TO:David Pennock, Planner
FROM: Gary Whelan, Civil Engineer
DATE: January 6, 2006
RE:Site Plan Technical Review for: Hollymead Town Center Area C
Block 3
TM 32, Parcel 41D)
The below checked items apply to this site. SDP - 2005 -00149
X 1. This site plan is within the Authority's
jurisdictional area for:
X A. Water and sewer
B. Water only
C. Water only to existing structure
D. Limited service
X 2. A 12 inch water line is located onsite.
X 3. Fire flow from nearest public hydrant, located 250'
distant from this site plan, is 4006 gpm + at 20 psi
residual.
X 4. An 8 inch sewer line is located onsite.
5. An Industrial Waste Ordinance survey form must be
completed.
X 6. No improvements or obstructions shall be placed
within existing or future easements.
7.and plans are currently under review.
8.and plans have been received and
approved.
9. No plans are required.
X 10. Final water and sewer plans are required for our
review and approval prior to granting tentative
approval.
11. Final site plan may /may not be signed.
12. RWSA approval for water and /or sewer connections.
Comments: Separate metering for commercial and residential.
Backflow prevention required. A water connection between
Blocks 2 and 3 will be required.
The site plan does not show or incorrectly shows:
meter locations waterline size
waterline locations sewer line size
sewer line locations expected wastewater flows
easements expected water demands