HomeMy WebLinkAboutWPO201300064 Bond Estimates 2016-03-25Project Name: Three Notch'd Center
WPO file number: wpo201300064
Stormwater Management Plan Bond Estimate
Item Item
Number
permanent diversion or ditch
standard manhole frame top (not inlet)
drop inlet or grate
manhole structure (per ft. rise)
pipe, rcp, cmp (15 to 48") 24.0 in d 0 ES -1,2
aggregate base or drainage stone 0.0 in d 0.0 ft L
Filterra 6x6
trees
shrubs
seedlings
underdrain (LF)
biofilter soil mix (Cl)
trash rack/ anti vortex devices
maintenance access road (LF)
rip -rap, placed depth 0 ft length
width 0.0 (tons)
survey and layout (price per 0.1 mi.) acres 2 basins
mobilization
as -built drawings (per facility)
materials testing (per facility)
compaction testing (per dam)
manufactured facilities (attach manufacturer's or contractor's price as a base)
No. Unit
Unit Cost
Cost
1 ea
installed
$150.00
0 ft
$13.00
$0.00
0 ea
$500.00
$0.00
1 ea
$3,500.00
$3,500.00
6 ft
$450.00
$2,700.00
0 EC -1 60.0 ft
$50.00
$3,000.00
0.0 ft w 0.0 ton
$35.00
$0.00
1 ea
$6,500.00
$6,500.00
1 ea
$150.00
$150.00
0 ea
$50.00
$0.00
0 ea
$5.00
$0.00
0 ft
$5.00
$0.00
0 cy
$38.00
$0.00
1 ft
$1,500.00
$1,500.00
0 ft
$50.00
$0.00
0.0 ft
0
$60.00
$0.00
1
$1,500.00
$500.00
1 ea
$2,000.00
$2,000.00
1 ea
$2,000.00
$2,000.00
1 ea
$5,000.00
$5,000.00
$0.00
cost sum $28,350.00
contingency $2,835.00
Total $31,190
3/25/2016