HomeMy WebLinkAboutSDP200700115 Review Comments 2007-11-12j` OF :1I.ljl,lr a 9 Ff County of Albemarle Department of Community Development Memorandum To: Sam Saunders/ R.Lilley From: Gerald Gatobu, Senior Planner Division: Zoning and Current Development Date: November 12` 2007 Subject: SDP2007 -00115 Albemarle High School Major Amendment The County of Albemarle Division of Zoning and Current Development will grant or recommend approval of the final site plan referred to above once the following comments have been addressed: Each comment is preceded by the applicable reference, which is to the Subdivision/Zoning Ordinances unless otherwise specified.] 1. [32.5.6] Please provide a schedule of parking including the maximum amount of paved parking existing, amount required with the additions and the overall amount of parking to be provided. 2. [32.5.6] Indicate the amount of impervious cover on the site. 3. [32.5.6] A landscape plan is required with this site plan. Please show the maximum amount of paved parking and vehicular circulation areas. This will help with landscape plan calculations for Interior Landscaping. 4. [32.5.6]Provide on the site plan a description of all variances, zoning proffers, bonus factors or special use permits applicable to this site. 5. If Outdoor lighting is proposed: Provide a Lighting/Photometric Plan A) Make sure light fixture locations do not conflict with utilities and landscaping. B) All light fixtures with 3000 or more lumens must be full cut off. C) Provide cut sheets for each lighting fixture on a separate sheet of the site plan. (Catalog numbers on the cut sheets must match those on the luminaire schedule). D) Show /clearly delineate the property lines on the lighting plan. E) Light loss factor LLF /Maintenance Factor must be 1. F) Add the standard lighting note to the lighting plan. 6. Landscaping Plan A) The conservation plan checklist needs to be shown on the site plan. The conservation checklist must be signed. B) 10% tree canopy is required for the site. Provide tree canopy calculations. Show existing tree canopy, and delineate new /proposed trees. I will be glad to assist with providing good examples of tree canopy tables and calculations. C) Indicate additional street trees and indicate the amount required and the amount provided. D) Interior landscaping calculations need to be shown. An area equal to 5% of paved parking and circulation areas shall be landscaped with trees and shrubs. E) Interior landscaping shall include 1 large or medium shade tree per 10 parking spaces if 5 spaces or more. Show existing interior landscaping, and then show the additional interior landscaping required because of the additions. Indicate how the additional interior landscaping will be met. Please contact Gerald Gatobu at the Division of Zoning and Current Development at 296 -5832 ext. 3385 for further information. ti pF ALg, COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902 -4596 Phone (434) 296 -5832 Fax (434) 972 -4126 DATE: November 12th, 2007 Sam Saunders 919 2nd Street S.E. Charlottesville, VA, 22902. RE: SDP - 2007 -00115 Albemarle High School Major Amendment. Dear Sir, The Site Review Committee has reviewed the development proposal referenced above. Preliminary continents for the following divisions of the Department of Community Development and other agencies, as applicable, are attached: Albemarle County Division of Zoning & Current Development (Planner) Albemarle County Division of Zoning & Current Development (Engineer) Albemarle County Division of Planning (Principle Planner ARB) Albemarle County Division of Planning (Principle Planner Rural Area) Albemarle County Division of Inspections (Building Official) Virginia Department of Transportation (VDOT). Albemarle County Service Authority (ACSA). Albemarle County Fire and Rescue. Albemarle County Geographic and Data Services (GDS) Comments reflect information available at the time the development proposal was reviewed, and should not be considered final. However, the Site Review Committee has attempted to identify all issues that could affect approval of the proposed project. Please make the revisions that have been identified as necessary for preliminary approval by the Site Review Committee. If you choose not to make the requested revisions, please submit in writing justification for not incorporating such revisions. Submit eight (8) full size copies and one (1) 11" x 17" copy to the Department of Community Development including responses to each of the attached comments of the Site Review Committee by Monday November 26th 2007. Failure to submit this information by this date will result in suspension of the review schedule. Review will resume when revisions are submitted along with a reinstatement fee of $65. Please contact me at your earliest convenience if you have questions or require additional information. Sincerely, Gerald Gatobu, Senior Planner County of Albemarle Department of Community Development Current Development 401 McIntire Road Charlottesville, VA 22902 -4596 Phone: (434)296 -5832 Ext 3385 Fax: (434)972-4126 it J . f. HGIti County of Albemarle Department of Community Development Memorandum To: Gerald Gatobu, Current Development Project Planner From: Andrew Lowe, Current Development engineering review Date: 13 November 2007 Subject: SDP-2007-00115 — Albemarle High School Major Amendment The Major Amendment for Albemarle High School has been reviewed. The following comments are provided; 1. Please provide a professional seal, signed and dated for all plans. [18-32.6.1] 2. Please provide a drainage plan and computations per the Engineering Review Final Plan Checklist. 18- 32.6.6.d] 3. Please submit WPO application and appropriate fee along with Stonnwater Management and Erosion and Sediment Control Plans. 4. The SWM and ESC plans must be approved prior to the signing of final plan mylars. [18- 32.7.4.3] 5. VDOT approval will be needed before final approval. 6. Please show and label the available sight distance for the entrance to Lambs Lane SR 9885. [DM & VDOT] 7. It appears the entrance landing to Lambs Lane exceeds the maximum 4% grade within the 40' from the intersected street. Please revise accordingly. [DM & VDOT] g. Please label the entrance radii. [DM] 9. Please provide a typical section detail for the proposed pavement for the parking lot. [18- 4.12.13.b] 10. All sidewalks must be at least 5' wide exclusive of curb. [DM] 11. Please provide a sidewalk detail or specifications per the Albemarle County Design Manual. [DM] 12. All travelways without parking must remain 20' wide. [18- 4.12.17.c] 13. It appears that the storm drain inlet adjacent to J.I.L.L addition may need to be relocated. Please verify if the drainage structures will be removed or relocated due to construction. [18- 32.5.6.k] 14. The parking lot cannot drain into Lambs Lane SR 9885. [18- 4.12.15.b] 15. Please include the Albemarle County general construction notes from the Design Manual. [DM] IMF , DEPARTMENT OF TRANSPORTATION 1601 grange Road Culpeper, Virginia 22701 VirginiaDOT.org David S. Ekern, P.E. COMMISSIONER November 13` 2007 Mr. Glenn Brooks Department of Engineering and Development 401 McIntire Rd. Charlottesville, VA 22902 Subject: Site Review Meeting Comments November 13` 2007 site review meeting Dear Mr. Brooks: Below are VDOT's comments on the Site Plans for the November 15` 2007 Site Review Committee Meeting: SDP -2007 -00115 Albemarle High School Addition and Renovation -Major (Gerald Gatobu SDP - 2007 -00121 Greer Elementary School Addition — Major (Summer Frederick) The additional traffic according to TIT trip generation will be an increase in ADT of 696 and an increase in the AM peak hour by 199 trips for the two school additions. The 2005 traffic count on route 743 at this intersection has an ADT of 26,406. The AM peak hour traffic on Route 743 is 2577 VPD. The impact of the additional trips from the school additions is a 2.6% increase in the ADT and a 7.7% increase in the AM peak hour. Because the impacts of the combined additions are below the 10% threshold set in the Chapter 527 Regulations, the intersection should function adequately and no changes or improvements will need to be made. SDP - 2007 -00117 Bruce Property / Verizon Tier I][_ — Final (Gerald Gatobu SDP -2007 -00118 Mawyer Property / Verizon Tier II PWSF — Final (Megan Yaniglos) SDP - 2007 -00119 Shelton Property / Verizon Tier II PWSF — Final (Patrick Lawrence) The applicant has been in contact with VDOT on the multiple Verizon Tower projects throughout the county. VDOT has indicated the need for adequate sight distances on all of the sites but does not feel it to be necessary to upgrade these sites to the commercial entrance standards in order to preserve the rural nature of many of the sites. In the few cases that the entrances do not meet the sight distance requirements, the applicant has indicated they plan to propose other safety measures be taken to ensure safety. The C--,—YEARS COf Tit ANSPdRTFk7 @tltf E %CELLENCE 0 6 2 1) 11 6 applicant is contacting VDOT on the individual sites and each site is being addressed for safety. Each site needs to indicate if commercial site distance requirements have been met or if other measures have been or are being taken to address safety. SUB - 2007 -00257 PJ Land Trust (Megan Yaniglos) Adequate sight distance should be shown on routes 677 and 601 where the private road intersects the state roads. The speed limit on 677 is 35 mph and a corresponding sight distance is 390 feet. There is no resolution for a posted speed on 601 in this section so the intersection should be evaluated for 55 mph and a 610 foot sight distance. Information on sight distance triangles can be found in VDOT's Road Design Manual, Appendix B. Please request the applicants provide a written description of revisions with re- submissions. If you have any questions or comments, please contact me prior to sharing these comments with the applicants. Sincerely, Joel DeNunzio, P.E. Staff Engineer VDOT Charlottesville Residency 434 - 293 -0011 cc Allan Schuck, Bill Fritz, David Benish, Juan Wade, Elaine Echols, Joan McDowell, Judith Wiegand, Margaret Maliszewski, David Pennock, Francis McCall, Jon Sharp, Summer Frederick, Patrick Lawrence, and John Giometti Application #: SDP200700 - 5 1Q1" Re tf11t11 @1'1tS Project Name:Albemarle High School Add't & Renov -Major Preliminary - Non - residential Date Completed:11/09/2007 Reviewer:Andrew Slack E911 Review Status:No Objection Reviews Comments:NO OBJECTION. Date Completed:11/12/2007 Reviewer:James Barber Fire Rescue Review Status:No Objection Reviews Comments:Must comply with the Virginia Statewide Fire Prevention Code. Approval is subject to field inspection and verification. Date Completed:11/28/2007 Reviewer:Jay Schlothauer Inspections Review Status:No Objection Reviews Comments:Based on plans revised November 26, 2007. No further comments or conditions. -I Date Completed:11/09/2007 Reviewer:Jay Schlothauer Inspections Review Status:Requested Changes Reviews Comments:Based on plans dated October 15, 2007. Indicate the total number of parking spaces, existing and proposed. This information is necessary in order to determine the required number of barrier -free parking spaces. - Date Completed:11/06/2007 Reviewer:Margaret Maliszewski ARB Review Status:Requested Changes Reviews Comments:This proposal is scheduled for ARB review on December 3, 2007. Comments will be provided after that meeting. Date Completed:12/10/2007 Reviewer:Margaret Maliszewski ARB Review Status:Requested Changes Reviews Comments:This was reviewed by the ARB on December 3, 2007. The action letter will be forwarded as soon as it is complete. Date Completed:03/04/2008 Reviewer:Margaret Maliszewski ARB Review Status:Requested Changes Reviews Comments:There are remaining outstanding conditions of ARB approval. Date Completed:04/01/2008 Reviewer:Margaret Maliszewski ARB Review Status:Requested Changes Reviews Comments: ,There are outstanding ARB conditions Page: 1.00 County of Albemarle Printed on: Tuesday, August 26, 2008 1UF ,a f.lfF'1 J . 1 I It(a V County of Albemarle Department of Community Development Memorandum To: Gerald Gatobu, Current Development Project Planner From: Andrew Lowe, Current Development engineering review Date: 13 November 2007 Rev. 1: 7 December 2007 Subject: SDP - 2007 -00115 — Albemarle High School Major Amendment The Major Amendment for Albemarle High School has been reviewed. The following comments are provided; 1. Please provide a professional seal, signed and dated for all plans. [18- 32.6.1] Rev. 1: This comment Inrs been addressed. 2. Please provide a drainage plan and computations per the Engineering Review Final Plan Checklist. 18- 32.6.6.d] Rev. 1: This comment has been addressed. 3. Please submit WPO application and appropriate fee along with Stormwater Management and Erosion and Sediment Control Plans. Rev. 1: This cominent tivill need to be addressed b'fore approval. 4. The SWM and ESC plans must be approved prior to the signing of final plan mylars. [18- 32.7.4.3] Rev. 1: This comment will need to be addressed before, final approval. 5. VDOT approval will be needed before final approval. Rev. 1: This comment will need to be addressed b(- fore final approval. 6. Please show and label the available sight distance for the entrance to Lambs Lane SR 9885. [DM] Rev. 1: This comment has been addressed. 7. It appears the entrance landing to Lambs Lane exceeds the maximum 4% grade within the 40' from the intersected street. Please revise accordingly. [DM & VDOT] Rev. 1: This comment has been addressed. 8. Please label the entrance radii. [DM] Rev. 1: This connnent has been addressed. 9. Please provide a typical section detail for the proposed pavement for the parking lot. [18- 4.12.13.b] Rev. 1: This comment has been addressed. 10. All sidewalks must be at least 5' wide exclusive of curb. [DM] Rev. 1: This comment has been addressed. 11. Please provide a sidewalk detail or specifications per the Albemarle County Design Manual. [DM] Rev. 1: This continent has been addressed. 12. All travelways without parking must remain 20' wide. [18- 4.12.17.c] Rev. 1: This continent has been adth•essed. 13. It appears that the storm drain inlet adjacent to J.LL.L addition may need to be relocated. Please verify if the drainage structures will be removed or relocated due to construction. [18- 32.5.6.k] Rev. 1: This conrrnieiit htrs been crdth•essed. 14. The parking lot cannot drain into Lambs Lane SR 9885. [18- 4.12.15.b] Rev. 1: This connnent has been addressed. 15. Please include the Albemarle County general construction notes from the Design Manual. [DM] Rev. I: This conmicnt has been addressed. c.J_i_ i• County of Albemarle Department of Community Development Memorandum To: Gerald Gatobu, Current Development Project Planner From: Andrew Lowe, Current Development engineering review Date: February 27, 2008 Subject: SDP -2007 -00115 — Albemarle High School Major Amendment The Major Amendment for Albemarle High School has been reviewed. The following comments are provided; 1. It appears all previous Engineering comments have been addressed and Engineering has no objections with the approval of the Final Site Plan. Page 1 of 1 Gerald Gatobu From: Ron Higgins Sent: Tuesday, March 25, 2008 4:47 PM To: Lisa Glass; Gerald Gatobu Cc: Bill Fritz Subject: Albemarle High School Parking Study Lisa & Gerald: I have been considering the various points made in the parking analysis provided by Lisa in her memo, dated February 28, 2008. 1 have also considered data from other ordinances that address high school parking needs as well as my own observations of the use patterns at the site. I have concluded that the 552 spaces will be sufficient given the nature of the AHS additions (no increase in student capacity, no increase in number of teaching spaces, removal of teaching "trailers ", etc.), the number of total staff at AHS and the actual use of parking on regular school days (w/ 20 -30 empty of the present 550). 1 trust this information will be adequate to satisfy this parking requirements for the AHS Additions site plan. If you have any questions please feel free to contact me. Ron Higgins 5/6/2008 of AI.F3, r COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902 -4596 Phone (434) 296 -5832 Fax (434) 972 -4126 April 25, 2008 Albemarle County Facilities Development c/o Ron Lilley 401 McIntire Road, Room 222 Charlottesville, VA 22902 RE: ARB2007 -00150 Albemarle High School Addition & Renovations Tax Mp 60, Parcel 172A Dear Mr. Lilley, I have reviewed your recent submittal for the above - referenced project, consisting of sheets A1.2, 2.1 -3, 2.6, 31, 41-2, 5.1, 6.1, 6.3, and C1.2 all revised 3/13/08 and sheets C4.1 -3 revised 4/25/08. The revisions included in these drawings satisfy all outstanding conditions of ARB approval. You may consider this letter your Certificate of Appropriateness. This approval is predicated on the fact that the design and materials, as proposed and exhibited for review, will be used. The acceptance of approval implies that the applicant has agreed to execute the design as indicated on the site plan, attachments, materials, samples, and other submittal items presented. Any change in the approved design or materials will require an amendment to the plan and must be reviewed and approved bytheArchitecturalReviewBoard. If you have any questions concerning this action, please feel free to contact me. Sincerely, Margaret Maliszewski Principal Planner cc: ARB File Page 1 of 2 Gerald Gatobu From: Denunzio, Joel D., P.E. [ Joel .Denunzio @VDOT.virginia.gov] Sent: Wednesday, May 14, 2008 4:25 PM To: Gerald Gatobu Subject: RE: Albemarle High School Renovation Gerald, The only comment I have is that any work within the VDOT ROW will need to have a permit from the VDOT Charlottesville office. Thanks, Joel Joel DeNunzio, P.E. Staff Engineer 434 - 293 -0011 Ext. 120 joel.denunzio(q ) vdot.virginia.gov From: Gerald Gatobu [mailto:ggatobu @albemarle.org] Sent: Wednesday, May 14, 2008 4:09 PM To: Ammy George Cc: Denunzio, Joel D., P.E.; Gary Whelan; Margaret Maliszewski; Ron Lilley; Jay Schlothauer; Andrew Lowe; James Barber Subject: RE: Albemarle High School Renovation Hello everyone, We are approaching final site plan approval for this project. This is the last call for anyone who has any reason why this final site plan for Albemarle high school renovation (SDP200700115) should not be signed /approved. Please let me know before i ask for final copies (mylars and paper copies). I will wait to hear any objections tomorrow and Friday. Thank you. IIN=rem From: Ammy George [mailto:Ammy.George @timmons.com] Sent: Tuesday, May 13, 2008 11:11 AM To: Gary Whelan; Jeremy Lynn Cc: Ron Lilley; Charles Tilley; Sam Saunders; Gerald Gatobu Subject: FW: Albemarle High School Renovation Gary, since we now have RWSA approval, will you please send out your letter of approval for this project as soon as possible? Amity From: Justin Weiler [mailto:jweiler @rivanna.org] Sent: Tuesday, May 13, 2008 10:49 AM 8/26/2008 Page 2 of 2 To: 'Gary Whelan' Cc: Ammy George; 'Michelle Simpson' Subject: Albemarle High School Renovation Gary, RWSA has reviewed the plans titled "Albemarle High School Additions and Renovations" prepared by Timmons Group and dated 4/1/08, with sheets C2.0, C2.1 and C2.2 dated 4/17/08, and consents to the proposed construction within the existing RWSA easement. All changes to the proposed work within the existing RWSA easement from that shown in the drawings shall be approved in writing by RWSA prior to construction of the work. RWSA reserves all existing rights associated with its easement, including (but not limited to) its rights to access, construction, operation, maintenance and repair of its facilities within the easement, and such consent shall not be construed to modify or increase in any way RWSA's obligations, if any, to repair and restore following such activities. All future construction or site improvements made within the RWSA easement shall not limit, modify, or prohibit any existing easement rights held by the RWSA, nor modify or increase its obligations, if any, to repair or restore. Please let me know if you have any questions. Justin Justin Sterling Weiler, E.1 T. Civil Engineer Rivanna Water and Sewer Authority 695 Moores Creek lane Charlottesville, VA 22902 Phone: 434.977.2970 ext.206 Fax: 434295.1146 8/26/2008 Albemarle 6) u; 6y Service Auth4rit serving Corr.er ving June 23, 2008 Mr. Samuel E. Saunders, III, P.E. Timmons Group 9192 d Street, S. E. Charlottesville, Virginia 22902 Re: Albemarle High School Additions & Renovations Dear Sam: The plan, entitled "Albemarle High School Additions & Renovations" dated March 10, 2008, last revised June 6, 2008, is hereby approved for construction. One set of the approved plan is enclosed for your records. Any previously approved plans are voided with this approval. This approval is for basic compliance with the General Water & Sewer Construction Specifications of the Albemarle County Service Authority (ACSA) and does not relieve the contractor from responsibility for his work as it relates to the plan and specifications. The ACSA requires that a copy of the approved construction plan be on the job site. The contractor is responsible for marking up a copy of the approved construction plan showing as -built information and provide this data to your client at the completion of utility installation. The final as -built plan shall be submitted in a format of one paper copy and one mylar copy. A preconstruction conference shall be scheduled with the project manager to ensure coordination and answer any questions. This will be a short meeting to review the project, materials, test methods and schedule, in order to expedite construction. Please have the proper party call me at 977 -4511 to schedule the meeting. This approval is valid for a period of 18 months from this date. If construction is not in progress at the end of this time period, the approval shall be void. 168 Spotnap Road • Charlottesville, VA 22911 • Tel (434) 977-4511 • Fax (434) 979 -0698 www.serviceauthority.org The pressure for water may exceed 80 psi at some meter locations If you have any questions, or if we can be of assistance, please give us a call at 434) 977 -4511. Sincerely, 6 'Ovt -j Gary M. Whelan Civil Engineer GMW:dmg cc: Jeffrey W. Rogers State Health Department Planning Department Bldg Codes & Zoning Services Soil Erosion Inspector ACSA Inspector 050601 AIbema rleHS061008