Loading...
HomeMy WebLinkAboutSDP200700109 Review Comments 2007-07-20iF ALgF,ti r IRGIN COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902 -4.596 Phone (434) 296 -5832 Fax (434) 972 -4012 July 20, 2007 Barry Creasy First Christian Church 1032 Linden Lane Charlottesville, VA 22902 RE: ARB- 2007 -44: First Christian Church - Preliminary Review of a Site Development Plan and Advisory Review for an Amendment to a Special Use Permit (Tax Map 79, Parcel 24A) Dear Mr. Creasy: The Albemarle County Architectural Review Board, at its meeting on July 2, 2007 completed the above -noted reviews and took the following actions. Regarding the Request for an Amendment to the Approved Special Use Permit the ARB voted unanimously (4:0) to forward the following recommendation to the Planning Commission: The ARB has no objection to the special use permit amendment. Re =ar in4 the Preliminary Site Plan by a vote of 4:0, the ARB unanimously voted for final approval of the Certificate of Appropriateness, pending staff administrative approval of the following conditions: 1. The details provided on July 2, 2007 of the outdoor picnic pavilion are acceptable with materials and colors as stated, with the possible addition of a stone knee wall to match the lower level of the main building. 2. Revise the building design in the south (rear) and west (left side) elevations (Sheet EL -1) to eliminate the appearance of blankness at the second story level using either window arrangement as presented on July 2, 2007 or vertical and horizontal banding as discussed and referenced in the drawing. 3. Revise the building design of the west (left side) elevation (Sheet EL -1), so that the hardiplank siding does not rest directly on the top of the first story windows. With building materials and design, provide a transition between the first and second floor levels of the elevation. This redesign should also provide a more balanced sense of scale and proportion between the hardiplank at the second story level and the building design above and below. 4. Revise the site plan and building elevations to provide the location and method of screening for HVAC and other equipment, indicating how visibility of the equipment will be eliminated from the EC. 5. Revise Sheet 4 Grading and Utilities Plan and Sheet 5 Landscape and Lighting Plan to show cut and fill slopes th, are rounded (minimum 10' radius) to meet v , xisting conditions. 6. Revise Sheet 3 La v, ind Dimension Plan, Sheet 4 Grading ai 'tilities Plan, and Sheet 5 Landscape and Lighting Plan and provide an erosion and sediment control plan clearly indicating proposed and existing tree lines (labeled), the limits of construction, the location and method of tree protection fencing for each tree /tree mass at the outermost limits of the canopy. Include a note on the landscape, grading and erosion control plans stating the following: The movement of heavy equipment and the storage of all materials outside the limits of construction are prohibited. No tree removal or grading will occur within the 75 foot setback adjacent to the Route 250 E. EC. 7. Revise Sheet 5 Landscape and Lighting Plan to show 2'/2" caliper trees, 40' on center, of a species common to the area, based on the County's Recommended Species List, along the eastern perimeter of the proposed parking lot. 8. Provide a lighting photometric plan showing all foot candle values across the site. Values at a right -of -way line or boundary line adjoining a rural area district shall not exceed the one -half 1/2) foot candle threshold. Provide alternate pole light fixtures that meet full cutoff requirements. Revise Sheet 5 Landscape and Lighting Plan to indicate the proposed finish, color and location of the Lumascape 461 -2 fixture. Provide information indicating the number of lumens that are emitted by this fixture. If 3,000 lumens or more, provide a full cutoff fixture. Revise the maintenance factor (LLF) in the luminaire schedule to 1.0. Indicate whether or not decorative lighting is proposed. If it is, show how it addresses all EC guidelines. 9. The Navajo Beige color shall be revised to be more gray /buff, and may be approved administratively. Please provide: 1. Two full sets of revised drawings addressing each of these conditions. Include updated ARB revision dates on each drawing. 2. A memo including detailed responses indicating how each condition has been satisfied. If changes other than those requested have been made, identify those changes in the memo also. Highlighting the changes in the drawing with "clouding" or by other means will facilitate review and approval. 3. The attached "Revised Application Submittal" form. This form must be returned with your revisions to ensure proper tracking and distribution. When staffs review of this information indicates that all conditions of approval have been met, a Certificate of Appropriateness may be issued. If you have any questions concerning any of the above, please feel free to call me. Sincerely, Brent Nelson Landscape Planner Cc: First Christian Church, 1032 Linden Lane, Charlottesville, VA 22902 Jim Thompson, PO Box 368, Forest, VA 24511 Scott Clark File w . ill V Jib,1 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902 -4596 Phone (434) 296 -5832 Fax (434) 972 -4126 Project: First Christian Church [SDP200700109, WP0200700022] Plan preparer: Keith Whipple [email: kwhippleL'mckeecarson.com] Owner or rep.: First Christian Church [address: 4476 Campbell Rd Troy, VA 22974] Plan received date: 16 Oct 2007 14 Nov 2007 (Revl) Date of comments: 30 Oct 2007 12 Dec 2007 (Revl) Reviewer: Engineering Expedited Review There are serious issues with this plan. It is not in accord with the special use permit, and the Erosion and Sediment Control plan is inadequate. It appears that with the proposed layout and area not to be disturbed," there is no room left to provide adequate E &S measures. Until these items can be properly addressed, it is ineligible for further Engineering expedited review. A. Final Site Plan (SDP200600109) 1. Please revise the final site plans. No grading is allowing within the buffers. Also, the SWM and ESC facilities are not allowed to be located within the "Area not to be disturbed" as shown on the application plan reviewed with the special use permit. Rev]: comment not addressed. The "Area not to be disturbed" boundan line is shown incorrectly. Please show the boundary line in accord with tie special use permit plan you provided dated May 29, 2007. No construction /grading is permissible within the "Area not to be disturbed. " The current proposal shows grading, stormwater management facilities, erosion and sediment control treasures, retaining walls, etc. within the "Area not to be disturbed. " This comment must be addressed to be in accord with Special Use Permit condition #3. 2. Please show the "Area not to be disturbed" boundary lines on all applicable sheets. This boundary line needs to match the line shown on the application plan of the special use permit. Rev]: comment not addressed See comment W. 4. The final site plans needs to meet the criteria of the special use permit. No grading is permitted within the buffers. Please revise accordingly. Rev]: comment not addressed. See comment W. 5. Needs VDOT approval. Revl: VDOT approval is required. We have j to receive comments back from VDOT. A latest copy of the plans will be submitted to them for review. Albemarle Mounty Community Development Engineering Review Comments Page 2 of 5 9. Dumpster needs to be larger. Rev]: The dumpster pad needs to be a minimum of 10x18 feet. 11. Entrance access way needs to be less than 10%0 grades. Revl: comments not addressed. The travehvay shown exceeding 10 %, near contours 86 to 94. 12. Please revise the pipe outfalls at the entrance access pipe and biofilter pipe. Rev]: comment not addressed. As shown on the site plan sheet S -3, the outlet to the biofilter outlets on top of'the outlet for the road culvert. Please revise the biofilter outlet to not allow runoff to drain overtop the culvert outlet. In addition, the outlet to the sediment trap during the E &S phase should not direct runoff overtop the culvert outlet. 14. [Omitted] 15. Additional comments may be forthcoming on the next submittal due to the required changes. a. (Revl) The curb cut directing travelway runoff to biofilter 2 is not shown on sheet S- 2 of the plans. b. (Revl) Please specify the maximum height for the retainings walls shown on the plans. Any wall exceeding 4 feet in height requires safety railing. B. Stormwater Management Plan (WPO200700022) 16. Revise the SWM plans. No grading is allowed within the buffers. Also, the SWM facilities are not allowed to be located within the "Area not to be disturbed" as shown on the application plan reviewed with the special use permit. Rev]: comment not addressed. See comment #1. 17. Please submit a signed copy of the Stormwater Maintenance Agreement and $17 fee to the County. Rev]: Corrections /additions /additional info needed to process the agreement. Please contact Pam Shifflett about this: pshitfl {u albemarle.oj:Z or 296 -5832 ex. 3246. 18. Please provide forebays on all of the proposed SWM facilities. Revl: comments not addressed. Please see the Foreba} Waiver request denial letter attached to the end of'the comment letter. 21. The SWM portion of the Water Protection Bond has not been computed at this time. 22. Additional comments may be forthcoming on the next submittal due to the required changes. a. (Revl) A minimum of 6" diameter pipe is needed for underdrains in the biofilters. b. (Rev 1) The downstream slope of the embankment for biofilter #1 needs to maintain a 3:1 slope. c. (Revl) Please specify a minimum of 3 species of shrubs and 3 species of trees for biofilters. d. (Revl) Trees are not allowed on the embankment of biofilter 1 (per the Virginia Stormwater Management Handbook). e. (Revl) Please show an adequate biofilter outlet detail. The biofilter needs to maintain all adequate freeboard requirements for the 100 year storm. Engineering recommends providing a weir design that will adequately detain the 2 and 10 year storm, as well as maintaining 1 foot of freeboard below the top of the embankment Albemarle Muunty Community Development Engineering Review Continents Page 3 of 5 for the 100 year storm. L (Revl)For biofilter 1, the areas below the curb cuts directing runoff into the facility need to be protected from erosion by appropriate scour protection, stone, or energy dissipation measures. Currently, it appears that runoff is being directed through a mulched landscaping area. g. (Revl)Please remove all landscaping from the forebay in biofilter 2. An adequate forebay for the biofilters can simply be a ring of rip rap following surrounding the outlets of concentrated flows (curb cuts, pipe outlets), thus successfully separating the forebay area from the main biofilter floor. The forebay(s) size should total 10- 25% of the biofilter. Forbay floor area is included in the square footage for water quality requirements. Please see the Virginia Stormwater Management Handbook for proper design of forebays. C. Erosion and Sediment Control Plan (WPO200700022) 23. Please revise the ESC plans. No grading is allowed within the buffers. Also, the SWM and ESC facilities are not allowed to be located within the "Area not to be disturbed" as shown on the application plan reviewed with the special use permit. No grading is allowed within the buffers. Revl: comment not addressed. See continent #1. 24. Please remove all proposed ESC measures from the buffer areas. Rev]: comment not addressed. See comment #1. 25. Please show the "Area not to be disturbed" boundary lines on all applicable sheets. This boundary line needs to match the line shown on the application plan of the special use permit. Revl: comment not addressed See comment #1. 27. Just a reminder, DCR is enforcing the VSMP General Permit Registration Statement. Please contact Mr. Matthew Grant, DCR, at 804.225.3068 for more information. This does not affect your review /approval of this plan. 28. The ESC portion of the Water Protection Bond has not been computed at this time. 29. Additional comments may be forthcoming on the next submittal due to the required changes. a. (Revl) The E &S plan is inadequate. There are inadequate perimeter controls. Most of the E &S measures cannot even be installed until grading is complete. For example, sediment trap #1 cannot be installed properly until most of the grading for the site is complete. Another example is a fill diversion located on the top of a proposed retaining wall. All erosion and sediment control measures are to be placed prior to or as the first step in clearing. A complete E &S review cannot be done at this time. b. (Revl) The narrative refers to requiring notification to the City. Please correct this to notify the County. c. (Revl) Please state the proposed acreage of disturbance in the narrative. d. (Rev I) Culvert inlet protection shall be designed and displayed in accordance with Std. & Spec. 3.08, page I1I -46 of the VESCH. Drainage areas from I to 2.99 acres will be designed in accordance with Std. &Spec. 3.13, temporary sediment trap. e. (Revl) Gravel curb inlet protection without overflow protection are not recommended. This office recommends the block and gravel curb inlet protection as shown in plate 3.07 -8 on page III -45 of VESCH. L (Revl) Please clarify the design and purpose of the temporary slope drain specified on the plans. Temporary slope drains shall be designed in accord with the Virginia Erosion and Sediment Control Handbook. Albemarle aunty Community Development Engineering Review Comments Page 4 of 5 g. (Revl) Please clarify the design and purpose of the Utility Stream Crossing specified on the plans. Utility Stream Crossings shall be designed in accord with the Virginia Erosion and Sediment Control Handbook. h. (Revl) Please clarify the design and purpose of the Stormwater Conveyance Channel specified on the plans. Stormwater Conveyance Channels shall be designed in accord with the Virginia Erosion and Sediment Control Handbook. Albemarle Mounty Community Development Engineering Review Comments Page 5 of 5 Waiver Request — Waiver of biofilter forebay: Keith, Engineering cannot approve a waiver of a forebay to biofilter 1. In order to approve a waiver, the plans need to meet at least one of the following criteria: Runoff sheet flows through a grassed area before entering the biofilter. The removal rate needed for the area draining to the facility is significantly lower than the removal rate provided by the facility. In this case, neither of these criterion have been met. The removal rate needed for the drainage area (70 %) exceeds the removal rate provided by the facility (65 %). Also, every point of discharge draining to the facility is concentrated flow (pipes or curb cuts). Even if all of the curbing directly adjacent to the biofilter were removed, the runoff would drain through landscaping /mulch rather than grass. Engineering denies this waiver request. Engineering requires adequate forebay(s) to biofilter 1. At this time it is difficult to recommend how to provide adequate forebays, as the facility is also partially located in an area designated "Area not to be Disturbed" per the approved Special Use Permit for this site. Sincerely, Jon Sharp Engineering Staff Y lH \! COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 -4596 Phone (434) 296 -5832 Fax (434) 972 -4126 Project: First Christian Church [SDP200700109, WP0200700022] Plan preparer: Keith Whipple [email: kwhipple(ti,)mckeecarson.com] Owner or rep.: First Christian Church [address: 4876 Campbell Rd Troy, VA 22974] Plan received date: 16 Oct 2007 14 Nov 2007 (Revl) 02 January 2008 (Rev. 2) Date of comments: 30 Oct 2007 12 Dec 2007 (Revl ) 09 January 2008 (Rev. 2) Reviewer: Engineering Expedited Review At this time, Engineering review is ready to give tentative approval to the plan. However, a few changes to the set will be required before final approval can be granted and a grading permit can be obtained. A. Final Site Plan (SDP200600109) 5. Needs VDOT approval. Rev 2: VDOT approval is required. We have yet to receive comments back from VDOT. A latest copy of the plans will be submitted to them for review. 9. Dumpster needs to be larger. Revl : The dumpster pad needs to be a minimum of 10x18 feet. Rev. 2) The dumpster pad is the correct size but the widening has caused a parking ~pace to be in violation of the County Ordinance. Please show all parking spaces at least 9ft wide. 118- 4.12.1 SJ 11. Entrance access way needs to be less than 10% grade. Revl : comments not addressed. The travelway shown exceeding 10 %, near contours 86 to 94. Rev. 2) Comment not addressed. 15. Additional comments may be forthcoming on the next submittal due to the required changes. b. (Rev 1) Please specify the maximum height for the retainings walls shown on the plans. Any wall exceeding 4 feet in height requires safety railing. Alben. County Community Development Engineering Review Comments Page 2 of 3 Rev. 2) Please show a safety railing on detail O /S7. A safety railing will be required on all sections of wall that are Oft in height or taller. It appears that a railing will be required for most of the wall adjacent to the pavilion. Additionally, during construction, the zoning inspector may require a railing to be placed on a wall if it is deemed a safety hazard. B. Stormwater Management Plan (WPO200700022) 18. Please provide forebays on all of the proposed SWM facilities. Revl : comments not addressed. Please see the Forebay Waiver request denial letter attached to the end of the comment letter. Rev. 2) Comment addressed ESC inspector may require the contractor to place riprap from the forebay of Biofilter I down to the bed 21. (Rev. 2) The SWM portion of the Water Protection Bond has been set at $27,000. For questions regarding bond posting procedures, please contact Pam Shifflett at 296 -5832. 22. Additional comments may be forthcoming on the next submittal due to the required changes. c. (Revl) Please specify a minimum of 3 species of shrubs and 3 species of trees for biofilters. Rev. 2) Comment not addressed. The 3 species variety of trees and shrubs must be within the bed material. Please follow Biofilter planting guidelines in pages 3.11 -16 to 3.11 -21 of the Virginia Stormwater Management Handbook. For bonding purposes, we have estimated the minimum number of trees and shrubs for each biofilter facility from the guidelines on page 3.11 -20 (1: 6 trees, 12 shrubs; 2: 6 trees, 13 shrubs; 3: 2 trees, 4 bushes). The applicant may wish to provide more if desired. g. (RevI )Please remove all landscaping from the forebay in biofilter 2. Rev. 2) Comment not addressed. C. Erosion and Sediment Control Plan (WPO200700022) 27. Just a reminder, DCR is enforcing the VSMP General Permit Registration Statement. Please contact Mr. Matthew Grant, DCR, at 804.225.3068 for more information. `Phis does not affect your review /approval of this plan. 28. (Rev. 2) The ESC portion of'the Water Protection Bond has been set at $46,000. For questions regarding bond posting procedures, please contact Pam Shifflett at 296 -5832. 29. Additional comments may be forthcoming on the next submittal due to the required changes. b. (Revl) The narrative refers to requiring notification to the City. Please correct this to notify the County. Alben. County Community Development Engineering Review Comments Page 3 of 3 Rev. 2) Comment not addressed. Please see "Offsite Areas" of the ESC narrative. c. (Revl) Please state the proposed acreage of disturbance in the narrative. Rev. 2) Comment not addressed. a . COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 -4596 Phone (434) 296 -5832 Fax (434) 972 -4126 Project: First Christian Church [SDP200700109, WP0200700022] Plan preparer: Keith Whipple [ email: kwhippleOmckeecarson.com] Owner or rep.: First Christian Church [address: 4876 Campbell Rd Troy, VA 22974] Plan received date: 16 Oct 2007 14 Nov 2007 (Revl ) 02 January 2008 (Rev. 2) 14 January 2008 (Rev. 3) Date of comments: 30 Oct 2007 12 Dec 2007 (Revl) 09 January 2008 (Rev. 2) 17 January 2008 (Rev. 3) Reviewer: Engineering Expedited Review Engineering review reconmlends approval to the site and WPO plans for First Christian Church. Please contact your planner to discuss any remaining items before final approval can be granted. The WPO bond must be posted before a grading permit can be issued. B. Stormwater Management Plan (WP0200700022) 21. (Rev. 2) The SWMportion of the Water Protection Bond has been set at $27,000. For questions regarding bond posting procedures, please contact Pam Shiflett at 296 -5832. C. Erosion and Sediment Control Plan (WP0200700022) 28. (Rev. 2) The ESC portion of the Water Protection Bond has been set at $46,000. For questions regarding bond posting procedures, please contact Pam Shifflett at 296 -5832. OF =17.I COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902 -4596 Phone (434) 296 -5832 Fax (434) 972 -4012 May 20, 2008 Keith Whipple McKee Carson and Field Sport Concepts, Ltd. 301 East High Street Charlottesville, VA 22902 RE: ARB- 2007 -44: First Christian Church Tax Map 79, Parcel 24A) Dear Mr. Whipple: 1 have reviewed your revised submittal for the above- referenced project which consisted of the following: Site plan drawings; Sheet l: Cover Sheet, latest revision date 5/12/08 Sheet 2: Existing Conditions, latest revision date 5/12/08 Sheet 3: Layout and Dimension Plan, latest revision date 5/12/08 Sheet 4: Grading & Utilities Plan, latest revision date 5 112/08 Sheet 5: Landscape Plan, latest revision date 5 /12/08 Sheet 6: Lighting & Photometric Plan, latest revision date 5/12/08 Sheet 7: Landscape & Lighting Details, latest revision date 5 /12/08 Sheet 8: Erosion & Sediment Control Plan, Phase 1, latest revision date 5/12/08 Sheet 9: Erosion & Sediment Control Plan, Phase 2, latest revision date 5/12/08 Sheet 10: Erosion & Sediment Control Plan, Details, latest revision date 5 /12/08 Building elevation drawings: Sheet 11: Proposed Exterior Elevations (EL -1), latest revision date 5/12/08 Sheet 12: Proposed Exterior Elevations (Et. 2), latest revision date 5 112/08 The revisions included in this latest submission address all outstanding conditions of ARB approval. You may consider this letter your Certificate of Appropriateness This approval is predicated on the fact that the design and materials, as proposed and exhibited for review, will be used. The acceptance of approval implies that the applicant has agreed to execute the design as indicated on the site plan, attachments, materials, samples, and other submittal items presented. Any change in the approved design or materials will require an amendment to the plan and must be reviewed and approved by the Architectural Review Board. If you have any questions, please do not hesitate to contact me. Sincerely, Brent W. Nelson Landscape Planner cc: Summer Frederick, Senior Planner (via email) ARB File Application #: 1 i SDP20070010! ( Short Review Gorr, ,ents Project Name: First Christian Church - Final - J F - — Administrative Date Completed 01/30/2008 Reviewer:Summer Frederick Planner Z &CD Review Status:Pending Reviews Comments:Issues with A approval Date Completed:01/09/2008 Reviewer:unassigned engineer Engineer Z &CD Review Status: Requested Changes Reviews Comments: Expedited Engineering Review. Requested Changes. 9 January 2008 Page: 1.00 County of Albemarle Printed On: Tuesday, September 23, 2008