HomeMy WebLinkAboutSDP200700104 Staff Report 2007-12-11ti RC:INI ALBEMARLE COUNTY PLANNING STAFF REPORT SUMMARY Project Name: SDP 2007 -104 Church of Staff: David E. Pennock, AICP; Jonathan Jesus Christ Latter -Day Saints Sharp Planning Commission Public Hearing:Board of Supervisors Hearing: December 11, 2007 Not applicable Owners: Church of Jesus Christ Latter -Day Applicant: John Griffin Saints Acreage: 5.14 Acres Rezone from: Not applicable Special Use Permit for: Not applicable TMP: Tax Map 32, Parcels 17 and 17E3 By -right use: RA, Rural Areas and EC, Location: approximately 0.75 miles from the Entrance Corridor intersection of Seminole Trail [Rte. 29N] and Airport Road [Rte. 649] Magisterial District: Rivanna Proffers /Conditions: Yes Requested # of Dwelling Lots: n/a DA — X RA — Proposal: Request for approval of a waiver to Comp. Plan Designation: The allow disturbance of critical slopes related to Comprehensive Plan designates this property the construction of a regional stormwater as Industrial Service in the Hollymead detention pond that will serve adjacent Community development. Character of Property: The property is Use of Surrounding Properties: The currently being developed as a previously Charlottesville Albemarle Regional Airport is approved church building with associated located roughly one mile to the northwest. parking.The general area also contains the Airport Center Subdivision, which is light industrial, and undeveloped land, much of which is part of the University of Virginia Research Park. Factors Favorable: (see report)Factors Unfavorable: (see report) RECOMMENDATION Staff recommends denial of the critical slopes waiver. nnlJtl`tdrw 100 f SVAc6A 4- C PL9 F rRomonoNdF 6 -4.ST(la VP- 66r4ro tJ E57ggcllnlvTOF 57RRn BUAeR a 1 r'Gt rt'e RccFss v urvs r STAFF PERSON PLANNING COMMISSION AGENDA TITLE: APPLICANT PROPERTY OWNER(S) David E. Pennock, AICP; Jonathan Sharp December 11, 2007 SDP 2007 -104 Church of Jesus Christ Latter -Day Saints John Griffin Church of Jesus Christ Latter -Day Saints APPLICANT'S PROPOSAL Request for approval of a waiver to allow disturbance of critical slopes related to the construction of a regional stormwater detention pond that will serve adjacent development. This property is described as Tax Map 32, Parcels 17 and 17E3, and is zoned RA, Rural Areas and EC, Entrance Corridor. The property is located in the Rio Magisterial District. Access to this property is approximately 0.75 miles from the intersection of Seminole Trail [Rte. 29N] and Airport Road [Rte. 649]. COMPREHENSIVE PLAN: The Comprehensive Plan designates this area as Industrial Service in the Hollymead Community. Attachment D) PLANNING AND ZONING HISTORY SP 04 -057: A Special Use Permit was approved allowing the construction of a church consisting of a 24,000 square foot building with 270 parking spaces on this property. SDP 05 -060 and SDP 06 -086: The preliminary and final site plans for the church approved by the SP listed above were approved with final site plan approval in March, 2007. WPO 06 -055: (currently under review) In October, 2007, a revised stormater management plan was submitted for the church, which proposed relocating the previously approved stormwater management facility to different areas off -site of the church property. Comments made during the review of the WPO plan included the need for a critical slopes waiver, which is the subject of the current request. REASON FOR PLANNING COMMISSION REVIEW The applicant submitted a Water Protection Ordinance (WPO) application proposing two regional stormwater management facilities on the above referenced parcels. Stormwater management facilities are typically exempted from critical slopes protection ordinances, provided that the applicant demonstrates that no reasonable alternative location exists. However, in this case, a previously approved location for a stormwater management facility was part of the site plan for this church. Thus, a reasonable alternative exists for at least one of the proposed facilities, and this proposed facility is not deemed to be exempt. As such, the Planning Commission must review the proposed disturbance of critical slopes in accordance with the criteria specified in Section 4.2.5 of the Zoning Ordinance. CRITICAL SLOPES WAIVER The request for a modification has been reviewed for both the Engineering and Planning aspects of the critical slopes regulations. Section 4.2.3.2 of the Zoning Ordinance restricts earth- disturbing activity on critical slopes, while Section 4.2.5(b) allows the Planning Commission to waive this restriction. The applicant has submitted a request and justification for the waiver (Attachment C), and staff has analyzed this request to address the provisions of the Ordinance. Critical slopes cover approximately 2.6 acres, or 8.3 percent, of the 31 acres included in the parcels subject to this request. This request is to disturb 0.12 acres, or 4.6 percent, of these critical slopes. The critical slopes in the area of this request do not appear to be man -made. Staff has reviewed this waiver request with consideration for the concerns that are set forth in Section 4.2 of the Zoning Ordinance, entitled "Critical Slopes." These concerns have been addressed directly through the analysis provided herein, which is presented in two parts, based on the Section of the Ordinance each pertains to. Section 4.2.5(a) Review of the request by Current Development Engineering staff: The critical slope waiver request has been reviewed. The engineering analysis of the request follows: Description of critical slope area and proposed disturbance: The critical slope area, within Tax Map 32, Parcels 17 and 17E3, appears to be natural slopes. The critical slope disturbance is in the form of a proposed stormwater management facility. This proposed facility is intended to serve roughly 8 acres of future development on portions of parcels 17, 17E1, 17E2, and 17E3. The proposed facility will also serve the LDS Church on parcel 17A1 (roughly 4 acres), which is currently under construction. Areas Acres Total site 31.3 acres approximately Critical slopes 2.6 8.3% of site Critical slopes disturbed 0.12 4.6% of critical slopes Below, each of the concerns of Zoning Ordinance section 18 -4.2 is discussed: Compliance with Zoning Ordinance 18 -4.2: movement of soil and rock" Proper slope construction, control of drainage, and vegetative stabilization will prevent any movement of soil. excessive stormwater runoff" Stormwater runoff will not increase, as the proposed stormwater facility will provide adequate stormwater detention. siltation " Inspection and bonding by the County will ensure siltation control during construction. Proper stabilization and maintenance will ensure long term stability. loss of aesthetic resource " The proposed disturbance will be partially visible by neighboring properties. The plans show clearing of an additional 3 acres of wooded area will be necessary in order to install the proposed facility. septic effluent " The LDS church is served by public sewer. Exemptions to critical slopes waivers for driveways, roads and utilities without reasonable alternative locations: As discussed above, the proposed critical slope disturbances associated with this plan are not exempt. The previously approved plans for the LDS Church (WPO 2006 -055) show a proposed bioretention basin in the location of the sediment basin currently on site (after final stabilization, the sediment basin will be retrofitted to a bioretention basin). This approved plan presents a reasonable alternative location for a stormwater management facility. 3 The proposed facility will serve parcels in addition to that on which the church is being constructed. However, at this point, no plans have been submitted showing the future development that the proposed stormwater facility will serve. If a preliminary plan were submitted showing the future development, the location might be demonstrated to be a reasonable location in order to serve future development, and thus a critical slopes waiver might not be necessary. However, without any plans of the proposed development, engineering staff cannot support the proposed facility. Based on the above review, engineering recommends denial to the critical slope waiver. Review of the request by Current Development Planning staff: Summary of review of modification of Section 4.2: Section 4.2.5 establishes the review process and criteria for granting a waiver of Section 4.2.3. The preceding comments by staff address the provisions of Section 4.2.5(a). Staff has included the provisions of Section 4.2.5(b) here, along with staff comment on the various provisions. The commission may modify or waive any requirement ofsection 4.2 in a particular case upon finding that: Strict application of the requirements of section 4.2 would not forward the purposes of this chapter or otherwise serve the public health, safety or welfare, or that alternatives proposed by the developer would satisfy the purposes ofsection 4.2 to at least an equivalent degree; or Added I1- I5 -89) The Open Space Plan is the primary tool used by staff to identify aesthetic resources. The maps in the Open Space Plan include inventory maps which show all resources. The composite map indicates those resources that are of the highest significance or are part of a system forming a significant resource, such as a stream valley or mountain range. The Open Space Plan shows slopes > 25 %" on this property on the "Inventory Map F. However, they are not reflected on the "Composite Map ". Based on the content of the Open Space Plan, staff opinion is that the critical slopes on this site do not represent a significant resource. The developer has proposed alternatives to the proposed layout. However, as discussed above, one such alternative — the approved site plan for the church — is deemed to satisfy the intent of the Ordinance to a greater degree than the proposed alternative. As indicated in the applicant's request letter, the primary reasons for the relocation of the approved facility are to serve future development that has not been reviewed by the County and to move the facility off of the more valuable developable portion of the property. Staff finds that a strict application of the requirements set forth in Section 4.2 would forward the purposes of this chapter and otherwise serve the public health, safety or welfare. 2. Due to its unusual size, topography, shape of the property, location of the property or other unusual conditions, excluding the proprietary interest of the developer, the requirements of section 4.2 would effectively prohibit or unreasonably restrict the use of the property or would result in significant degradation of'the site or adjacent properties. Such modification or waiver shall not be detrimental to the public health, safety or welfare, to the orderly development of the area, or to adjacent properties, or be contrary to sound engineering practices; or (Added 11 -15- 89) 4 Denial of this waiver would not prohibit or restrict the use of the property. A site plan was previously approved that allows the development of the church to the full extent that was allowed by the Special Use Permit. 3. Granting such modification or waiver would serve a public purpose of greater import than would be served by strict application of section 4.2. (Added 11-15-89) This property is in the Development Areas, and the resources on the site have not been indicated as significant resources in the Open Space Plan. Stormwater management facilities may be exempted from the requirements of the Ordinance if alternative locations are not possible. However, given the previously approved site plan, staff finds that granting this modification would not serve a public purpose of greater import than this Ordinance.. RECOMMENDATION Staff is not able to find that the provisions of Section 4.2.5(b) have been met. As presented in previous sections of the Staff Report, it is possible that this location may be appropriate for a stormwater management facility in the context of a larger development plan for this area. However, without such a plan, it is impossible to make such a finding. Staff recommends denial of the critical slopes waiver. ATTACHMENTS A. Preliminary Plat B. Location/Detail Maps C. Applicant's Request and Justification D. Open Space Map Legend Nate: Same items on map MY not appear In legend) 32- 1 32- 19CI 32- 6A 32- 9C Sp/ 6 32- 22CS 32 -9131 tirz 3 -9D CIG 32- 9E 32- 22 3- 2-1762 10 3A- 01 0 32- 10+ 32A- A, I \ 32- 18 \32A- 01-0) 60 2- 17E3 32 I U 32- 20C'--- 32- 17E4. S 171 ljo7E2 12MIAX32 , 32A/ 01-6 -96 32 -17E35 II _/ v 32A- 01- A- 14-*2 32- 10+ 32- i z 17EI -324- 01- QA- 12A OA- 7 32- j . 7A1 't 32 f A- 01 32 17C IAL ""32 -OA- 1 lj 32A- Ul-05 l 01 /< GeograI phic Data SerServices0 32- ISA' GIS- Web albemarle org 32; 20C ( 434 296- 5832 649 32A- 01-OA 32C O :32C- 1 C ri A Jilw It 1, 32, a s If-- 91 - 2- A101- CA- 11 9, r A?Pi z I - W2- 49AI 3 2- C- - 0 V 0 pit),C, C- 1 32A- 01-OB 4 10 , 2 A - 0 1 Cj A - Skv [31W32A- 01R32- 41E;'il- !0' 1 • 32C- 02 ,401 4 32- 9 3 -OB-` 0' 32-41'32- 2pF 32- 49 Ptt t3 2C -0 27- 4102 - OB- 3t U tC* 32C-02 I 0 32 M4' 32- A- 01- I W- 11 I . oil a 32C- Q2- OC- 4 2 32-A - -22 /.49H I Ar- 3*') 13' 1-- 5 32 - -3 - SAAk 14232C- 02 0 ' 1 *-41P -40 /32C- 03'-- i SS,:, / /, 4 32- 41+ j32C 32 4 49G - 4: L 6 <, _ , 29 e Ns3 ' 2- 4n32-, I- H 6r- ri -- I P- 0/ 23 432SIB i326- A 3, 3321 2 1 32; 4111 i z 3- 2-, L Da an, b. r 4 2007 32- 49 32C7- 03--3 3 C- 03--B 32- 4,93 a- Map rs for dtsplay purposes only - Aerial 1— gery 2002 c -1 V119, 11a BLACKWELL ENGINEERING, PLC 566 E. MARKET ST. • HARRISONBURG, VIRGINIA _2901 • ( 540) 432 - • FAX (540) 434 -7604 November 14, 2007 David Pennock, Principal Planner Albemarle County Community Development 401 McIntyre Road Charlottesville, VA 22902 Subject: Critical Slope Waiver Request for Regional Detention Pond on TM 32 -17 and 32 -17E3 (WPO -2007- 00027) BE #1853 Dear David, In accordance with review comment C.5 by Jonathan Sharp dated 23 October 23 2007, please process this request for a critical slope waiver described in Chapter 18, Section 4.2.6c of the Albemarle County Code. The temporary stormwater management facility installed immediately downslope of the LDS Church project on TM 32 -17 was required to proceed with the building of the church. It was never proposed to remain in that location as it occupies valuable developable land that does not have steep slopes. No reasonable alternative location exists for a permanent stormwater management facility further upslope from the permanent location proposed in the detention pond plans. Description of critical slope area and proposed disturbance — The proposed location of the regional detention pond is in a drainage ravine or Swale with spotty, non- contiguous areas of critical slopes, i.e., 4:1 (25 %) and greater. It is good engineering practice for regional detention facilities to be located as far downslope as possible to intercept the greatest tributary area and reduce the overall number of ponds and their associated land disturbance. The proposed location of this facility will intercept stormwater runoff from portions of five parcels of land: the LDS Church (32- 17A1), parcel 32 -17, and three parcels on Dobleann Drive (32 -17E1 through E3). The proposed facility will use 2.5:1 (40 %) slopes on the outside of the embankment and 2:1 (50%) slopes on the water -side of the impoundment. The use of these slopes is consistent with standard engineering practice and disturbs the least amount of land. A single release pipe is proposed to discharge the detained stormwater into the same ravine where the existing un- detained runoff currently flows. CIVIL ENGINEERS SPFCIALIZING IN LAND DEVELOPNIFNT, ENVIRONMENTAL. NEEDS CONSTRUCTION MANAGFMENT SERVING COMMERCIAL, INDUSTRIAL AND MUNICIPAL ATTACHMENT C David Pennock November 14, 2007 Page 2 Area Tabulation Areas Acres TM 32 -17 28.53 TM 32 -17E3 2.77 Total Area 31.30 Critical slopes 1 2.60, 8.30 of total area Critical slopes disturbed 0.12, 4.6% of critical slopes Compliance with Zoning Ordinance 18 -4.2 1. Movement of soil and rock - Proper slope construction, control of drainage, and vegetative stabilization will prevent movement of soil and rock. 2. Excessive stormwater runoff - the regional detention pond has been designed to accommodate the tributary area with up to 80/0 of the surface eventually becoming impervious with buildings and pavement. Stormwater runoff from the proposed pond serving a fully developed drainage area will reduce runoff to an amount that is less than the area now produces. See calculations dated and submitted September 18, 2007. 3. Siltation of natural and man -made bodies of water - inspection and bonding by the County will ensure siltation control during construction. Proper stabilization and maintenance will ensure long term stability. 4. Loss of aesthetic resource - The proposed permanent detention facility is located as far from view from buildings and roadways as possible and will be further screened by the existing trees in the area. 5. Septic system failure - no septic systems are proposed for these two properties. Please call me if you have any questions or require additional information to process this waiver request. Cordially, T. Basil Finnegan Senior Designer Cc: John Griffin - Zobrist Law Group, Wendell Wood - Gold Leaf Land Trust No. 3 HOW!V `' ` / l' r • t 1 • s 634 . • • s '_ ' Jj sr f E t r ler tr f Park w 11 - - •.. 1 ftft Wo Ch f•" is q9. 1 ' fF4 ! J ' fi ; ., 4 c 4na n ri 0000 Il r / fr t,• t 'fi Hol- 1 mead 111 - . ` '" •. ; . -' • 8 •r r f JJ — • . • •- BetheeNl Trailer %r •.gip.. • Park - ..:::. ,.• : Cen a' d Open Space Map — Composite Map 9 RGINI ALBEMARLE COUNTY PLANNING STAFF REPORT SUMMARY Project Name: SDP 2007 -104 Church of Staff: David E. Pennock, AICP; Jonathan Jesus Christ Latter -Day Saints Sharp Planning Commission Public Hearing:Board of Supervisors Hearing: December 11, 2007 Not applicable Owners: Church of Jesus Christ Latter -Day Applicant: John Griffin Saints Acreage: 5.14 Acres Rezone from: Not applicable Special Use Permit for: Not applicable TMP: Tax Map 32, Parcels 17 and 17E3 By -right use: RA, Rural Areas and EC, Location: approximately 0.75 miles from the Entrance Corridor intersection of Seminole Trail [Rte. 29N] and Airport Road [Rte. 649] Magisterial District: Rivanna Proffers /Conditions: Yes Requested # of Dwelling Lots: n/a DA — X RA — Proposal: Request for approval of a waiver to Comp. Plan Designation: The allow disturbance of critical slopes related to Comprehensive Plan designates this property the construction of a regional stormwater as Industrial Service in the Hollymead detention pond that will serve adjacent Community development. Character of Property: The property is Use of Surrounding Properties: The currently being developed as a previously Charlottesville Albemarle Regional Airport is approved church building with associated located roughly one mile to the northwest. parking.The general area also contains the Airport Center Subdivision, which is light industrial, and undeveloped land, much of which is part of the University of Virginia Research Park. Factors Favorable: (see report)Factors Unfavorable: (see report) RECOMMENDATION Staff recommends denial of the critical slopes waiver. STAFF PERSON PLANNING COMMISSION AGENDA TITLE: David E. Pennock, AICP; Jonathan Sharp December 11, 2007 SDP 2007 -104 Church of Jesus Christ Latter -Day Saints APPLICANT John Griffin PROPERTY OWNER(S) Church of Jesus Christ Latter -Day Saints APPLICANT'S PROPOSAL Request for approval of a waiver to allow disturbance of critical slopes related to the construction of a regional stormwater detention pond that will serve adjacent development. This property is described as Tax Map 32, Parcels 17 and 17E3, and is zoned RA, Rural Areas and EC, Entrance Corridor. The property is located in the Rio Magisterial District. Access to this property is approximately 0.75 miles from the intersection of Seminole Trail [Rte. 29N] and Airport Road [Rte. 649]. COMPREHENSIVE PLAN: The Comprehensive Plan designates this area as Industrial Service in the Hollymead Community. Attachment D) PLANNING AND ZONING HISTORY SP 04 -057: A Special Use Permit was approved allowing the construction of a church consisting of a 24,000 square foot building with 270 parking spaces on this property. SDP 05 -060 and SDP 06 -086: The preliminary and final site plans for the church approved by the SP listed above were approved with final site plan approval in March, 2007. WPO 06 -055: (currently under review) In October, 2007, a revised stormater management plan was submitted for the church, which proposed relocating the previously approved stormwater management facility to different areas off -site of the church property. Comments made during the review of the WPO plan included the need for a critical slopes waiver, which is the subject of the current request. REASON FOR PLANNING COMMISSION REVIEW The applicant submitted a Water Protection Ordinance (WPO) application proposing two regional stormwater management facilities on the above referenced parcels. Stormwater management facilities are typically exempted from critical slopes protection ordinances, provided that the applicant demonstrates that no reasonable alternative location exists. However, in this case, a previously approved location for a stormwater management facility was part of the site plan for this church. Thus, a reasonable alternative exists for at least one of the proposed facilities, and this proposed facility is not deemed to be exempt. As such, the Planning Commission must review the proposed disturbance of critical slopes in accordance with the criteria specified in Section 4.2.5 of the Zoning Ordinance. CRITICAL SLOPES WAIVER The request for a modification has been reviewed for both the Engineering and Planning aspects of the critical slopes regulations. Section 4.2.3.2 of the Zoning Ordinance restricts earth - disturbing activity on critical slopes, while Section 4.2.5(b) allows the Planning Commission to waive this restriction. The applicant has submitted a request and justification for the waiver (Attachment C), and staff has analyzed this request to address the provisions of the Ordinance. Critical slopes cover approximately 2.6 acres, or 8.3 percent, of the 31 acres included in the parcels subject to this request. This request is to disturb 0.12 acres, or 4.6 percent, of these critical slopes. The critical slopes in the area of this request do not appear to be man -made. Staff has reviewed this waiver request with consideration for the concerns that are set forth in Section 4.2 of the Zoning Ordinance, entitled "Critical Slopes." These concerns have been addressed directly through the analysis provided herein, which is presented in two parts, based on the Section of the Ordinance each pertains to. Section 4.2.5(a) Review of the request by Current Development Engineering staff: The critical slope waiver request has been reviewed. The engineering analysis of the request follows: Description of critical slope area and proposed disturbance: The critical slope area, within Tax Map 32, Parcels 17 and 17E3, appears to be natural slopes. The critical slope disturbance is in the form of a proposed stormwater management facility. This proposed facility is intended to serve roughly 8 acres of future development on portions of parcels 17, 17E 1, 17E2, and 17E3. The proposed facility will also serve the LDS Church on parcel 17A1 (roughly 4 acres), which is currently under construction. Areas Acres Total site 31.3 acres approximately Critical slopes 2.6 8.3% of site Critical slopes disturbed 0.12 4.6% of critical slopes Below, each of the concerns of Zoning Ordinance section 18 -4.2 is discussed: Compliance with Zoning Ordinance 18 -4.2: movement o f soil and rock " Proper slope construction, control of drainage, and vegetative stabilization will prevent any movement of soil. excessive stormwater runoff" Stormwater runoff will not increase, as the proposed stormwater facility will provide adequate stormwater detention. siltation " Inspection and bonding by the County will ensure siltation control during construction. Proper stabilization and maintenance will ensure long term stability. loss of aesthetic resource " The proposed disturbance will be partially visible by neighboring properties. The plans show clearing of an additional 3 acres of wooded area will be necessary in order to install the proposed facility. septic effluent " The LDS church is served by public sewer. Exemptions to critical slopes waivers for driveways, roads and utilities without reasonable alternative locations: As discussed above, the proposed critical slope disturbances associated with this plan are not exempt. The previously approved plans for the LDS Church (WPO 2006 -055) show a proposed bioretention basin in the location of the sediment basin currently on site (after final stabilization, the sediment basin will be retrofitted to a bioretention basin). This approved plan presents a reasonable alternative location for a stormwater management facility. 3 The proposed facility will serve parcels in addition to that on which the church is being constructed. However, at this point, no plans have been submitted showing the future development that the proposed stormwater facility will serve. If a preliminary plan were submitted showing the future development, the location might be demonstrated to be a reasonable location in order to serve future development, and thus a critical slopes waiver might not be necessary. However, without any plans of the proposed development, engineering staff cannot support the proposed facility. Based on the above review, engineering recommends denial to the critical slope waiver. Review of the request by Current Development Planning staff: Summary of review of modification of Section 4.2: Section 4.2.5 establishes the review process and criteria for granting a waiver of Section 4.2.3. The preceding comments by staff address the provisions of Section 4.2.5(a). Staff has included the provisions of Section 4.2.5(b) here, along with staff comment on the various provisions. The commission may modify or waive any requirement of section 4.2 in a particular case upon finding that: Strict application of the requirements of section 4.2 would not forward the purposes of this chapter or otherwise serve the public health, safety or welfare, or that alternatives proposed by the developer would satisfy the purposes of section 4.2 to at least an equivalent degree; or Added 11- 15 -89) The Open Space Plan is the primary tool used by staff to identify aesthetic resources. The maps in the Open Space Plan include inventory maps which show all resources. The composite map indicates those resources that are of the highest significance or are part of a system forming a significant resource, such as a stream valley or mountain range. The Open Space Plan shows slopes > 25 %" on this property on the "Inventory Map I". However, they are not reflected on the "Composite Map ". Based on the content of the Open Space Plan, staff opinion is that the critical slopes on this site do not represent a significant resource. The developer has proposed alternatives to the proposed layout. However, as discussed above, one such alternative — the approved site plan for the church — is deemed to satisfy the intent of the Ordinance to a greater degree than the proposed alternative. As indicated in the applicant's request letter, the primary reasons for the relocation of the approved facility are to serve future development that has not been reviewed by the County and to move the facility off of the more valuable developable portion of the property. Staff finds that a strict application of the requirements set forth in Section 4.2 would forward the purposes of this chapter and otherwise serve the public health, safety or welfare. 2. Due to its unusual size, topography, shape of the property, location of the property or other unusual conditions, excluding the proprietary interest of the developer, the requirements of section 4.2 would effectively prohibit or unreasonably restrict the use of the property or would result in significant degradation of the site or adjacent properties. Such modification or waiver shall not be detrimental to the public health, safety or welfare, to the orderly development of the area, or to adjacent properties, or be contrary to sound engineering practices; or (Added 11 -15- 89) Denial of this waiver would not prohibit or restrict the use of the property. A site plan was previously approved that allows the development of the church to the full extent that was allowed by the Special Use Permit. 3. Granting such modification or waiver would serve a public purpose of greater import than would be served by strict application of section 4.2. (Added 11- 15 -89) This property is in the Development Areas, and the resources on the site have not been indicated as significant resources in the Open Space Plan. Stormwater management facilities may be exempted from the requirements of the Ordinance if alternative locations are not possible. However, given the previously approved site plan, staff finds that granting this modification would not serve a public purpose of greater import than this Ordinance.. RECOMMENDATION Staff is not able to find that the provisions of Section 4.2.5(b) have been met. As presented in previous sections of the Staff Report, it is possible that this location may be appropriate for a stormwater management facility in the context of a larger development plan for this area. However, without such a plan, it is impossible to make such a finding. Staff recommends denial of the critical slopes waiver. ATTACHMENTS A. Preliminary Plat B. Location/Detail Maps C. Applicant's Request and Justification D. Open Space Map Legend NS R m map may not appear In legend) } a.. o, 0o's IW 32 u 6 A o AL OP 3 1 1 7 a 2 3.! A 01- 05- 0 A, 606 32A- 01- 0A- 16Alq- v 2- 17E 41 0A 14 uj - z A; L! 1 N VrR- 32A iot /A, IP Ao IA. 0 0 C albemarle org 2 Czl!% If 7 E 4 32AWIGA I- E ( 434 29658326A - ' - I _ —, me Data Services 32C- 01-' - 649 z -11A A t' 2 A 011 A P, 1 lr wwoob I W, I d Mo_ 1" A"01 low 32- 41L - 12 41L LOP 2C 0- 2-0 , UPz1ve I ... 11- 1 1 4141 32- 41D2 32- 2UD W 4Z /32 C 32 0 /31838A 32- 49G N 2 1 -C 5732C- J--Al RZ' H et -. 29 5 B 0 32- 491L 1 2 B 4' 4-49 December 4, 2007 Map,,, display purposes -[y. Aenal Imagery 2002 Commonwealth .fV,, g,m- Ad "Ih BLACKWELL ENGINEERING, PLC uhf, F. %IARKI:T ST • IIARRI SON L31 7R(i, VIR6INIA _'_ • (i40) 432.QCS5 • FAX (i40) 434- 7(,114 November 14, 2007 David Pennock, Principal Planner Albemarle County Community Development 401 McIntyre Road Charlottesville, VA 22902 Subject: Critical Slope Waiver Request for Regional Detention Pond on TM 32 -17 and 32 -17E3 (WPO -2007 -00027) BE #1853 Dear David, In accordance with review comment C.5 by Jonathan Sharp dated 23 October 23 2007, please process this request for a critical slope waiver described in Chapter 18, Section 4.2.6c of the Albemarle County Code. The temporary stormwater management facility installed immediately downslope of the LDS Church project on TM 32 -17 was required to proceed with the building of the church. It was never proposed to remain in that location as it occupies valuable developable land that does not have steep slopes. No reasonable alternative location exists for a permanent stormwater management facility further upslope from the permanent location proposed in the detention pond plans. Description of critical slope area and proposed disturbance — The proposed location of the regional detention pond is in a drainage ravine or swale with spotty, non- contiguous areas of critical slopes, i.e., 4:1 (25 %) and greater. It is good engineering practice for regional detention facilities to be located as far downslope as possible to intercept the greatest tributary area and reduce the overall number of ponds and their associated land disturbance. The proposed location of this facility will intercept stormwater runoff from portions of five parcels of land: the LDS Church (32- 17A1), parcel 32 -17, and three parcels on Dobleann Drive (32 -17E1 through E3). The proposed facility will use 2.5:1 (40 %) slopes on the outside of the embankment and 2:1 (50 %) slopes on the water -side of the impoundment. The use of these slopes is consistent with standard engineering practice and disturbs the least amount of land. A single release pipe is proposed to discharge the detained stormwater into the same ravine where the existing un- detained runoff currently flows. C I\ IL LN(,1NI+IZS SPLC'L\I 171 \6 IN LAND DI_ \TI,O1 ,IL -Vf, EN\ IRO\ \ILL' I AI Nt.PUS CONSTRLC'FION MAN WI-\It NT SLR\'I\(i ('lt: \t \1LRCI: \I . INIH sFRIAL AND Mt NI('IPAL ATTACHMENT C David Pennock November 14, 2007 Page 2 Area Tabulation Areas Acres TM 32 -17 28.53 TM 32 -17E3 2.77 Total Area 31.30 Critical slopes 2.60, 8.3% of total area Critical slopes disturbed 0.12, 4.6% of critical slopes Compliance with Zoning Ordinance 18 -4.2 1. Movement of soil and rock — Proper slope construction, control of drainage, and vegetative stabilization will prevent movement of soil and rock. 2. Excessive stormwater runoff — the regional detention pond has been designed to accommodate the tributary area with up to 80% of the surface eventually becoming impervious with buildings and pavement. Stormwater runoff from the proposed pond serving a fully developed drainage area will reduce runoff to an amount that is less than the area now produces. See calculations dated and submitted September 18, 2007. 3. Siltation of natural and man -made bodies of water — inspection and bonding by the County will ensure siltation control during construction. Proper stabilization and maintenance will ensure long term stability. 4. Loss of aesthetic resource — The proposed permanent detention facility is located as far from view from buildings and roadways as possible and will be further screened by the existing trees in the area. 5. Septic system failure — no septic systems are proposed for these two properties. Please call me if you have any questions or require additional information to process this waiver request. Cordially, T. Basil Finnegan Senior Designer Cc: John Griffin — Zobrist Law Group, Wendell Wood — Gold Leaf Land Trust No Hm is r 634 ' 1 , \ f F -•'' ' t r ler ` a j4i. + • j • fI ) Park ; + • ) A4s le ll vrs• Ch kz l I r ti ? .• -. 49 ` / ` + t f- t _ •may I 'ti l ie N "abna t a H ofl rye ,! / F' `F /} r Holl mead 59. E S ,I ii /: • •••' ' •.. :' ., • • • ` ! i.,_. ,• v i. , G railor n - Park i+ , Cen H V Open Space Map — Composite Map 1- a jRGIN ALBEMARLE COUNTY PLANNING STAFF REPORT SUMMARY Project Name: SDP 07 -078: NGIC Staff: David Pennock, Jonathan Sharp Expansion — Preliminary Site Plan Planning Commission Public Hearing:Board of Supervisors Hearing: November 13, 2007 Not appli cable Owners: Next Generation, LLC Applicant: United Land Corporation Acreage: 15 acres within the 116 acre parcel Rezone from: Not applicable Special Use Permit for: Not applicable TMP: Tax Map 33, Parcel 1 D (in part) and 1 F By -right use: CO, Commercial Office zoning in part)with Special Use permits to allow Research Location: East of Seminole Trail [Route 29N]and Development Laboratories and at the end of Boulders Road [Private] Residential uses Magisterial District: Rivanna Proffers /Conditions: Yes Requested # of Dwelling Lots: n/a DA— X RA — Proposal: Request for preliminary site plan Comp. Plan Designation: Industrial Service approval for construction of two four -story in the Community of Piney Mountain in the office buildings totaling 178,800 square feet Development Area and site preparation work related to a future project for a 120 -unit residential building. Character of Property: This property is Use of Surrounding Properties: Adjacent to currently partially wooded, with some meadow the existing National Ground Intelligence areas, unimproved roadways, and drainage Center (NGIC) and to low density swales.residential /rural uses Factors Favorable: (see report)Factors Unfavorable: (see report) RECOMMENDATION: Staff has reviewed this request for compliance with the provisions of the Zoning Ordinance and recommends approval of the preliminary site plan subject to the conditions presented in the staff report. STAFF PERSON David E. Pennock, Jonathan Sharp PLANNING COMMISSION November 13, 2007 SITE PLAN SDP 07 -078: NGIC Expansion — Preliminary Site Plan PROPERTY OWNER Next Generation, LLC APPLICANT United Land Corporation APPLICANT'S PROPOSAL Request for preliminary site plan approval for construction of two four -story office buildings totaling 178,800 square feet and site preparation work related to a future project for a 120 -unit residential building. This project was called up for review by the Planning Commission. CHARACTER OF AREA This project is within an area east of Route 29N at the end of the previously constructed portion of Boulders Road, which currently serves the National Ground Intelligence Center (NGIC). Camelot and Briarwood subdivisions are on the west side of Route 29N at this location, and General Electric has a facility nearby. The North Fork of the Rivanna River flows adjacent to portions of the NGIC site. The surrounding properties include mostly low - density rural residential uses, the majority of which are also owned by this applicant. PLANNING AND ZONING HISTORY ZMA 07 -003 NGIC Expansion: This property was rezoned to Commercial Office in August, 2007, with proffers and a proffered application plan showing the construction of two office buildings and a residential building, as well as the extension of Boulders Road and some associated improvements to Route 29. SP 07 -031 Special Use Permit- Residential Units: A special use permit was approved with conditions in August, 2007 in order to allow Research and Development Laboratories. SP 07 -032 Special Use Permit - Research & Development; Labs: A special use permit was approved with conditions in August, 2007 to allow residential uses on this property. ZMA 99 -002 Value America: A rezoning was submitted in 1999 for Light Industrial on a portion of TMP 33 -1 D, but was eventually withdrawn. SP 99 -033 NGIC Access Road: A special use permit was granted in August, 1999 to allow fill in the floodplain for the construction of the access road (now known as Boulders Road). COMPREHENSIVE PLAN: The Comprehensive Plan designates this property as Industrial Service in the Community of Piney Mountain in the Development Area. REASON FOR PLANNING COMMISSION REVIEW: Request for review of a preliminary site plan by the Planning Commission in accordance with Section 32.4.2.6; this application has been requested for review by a member of the Planning Commission Attachment Q. At its meeting on October 9, 2007, the Planning Commission accepted the applicant's request for deferral of decision regarding this application. At that time, the proposal was reviewed by staff and found to be out of compliance with the application plan approved with the rezoning and would have required a variation as set forth in section 8.5.5.3. The proposal has been revised by the applicant 2 and re- reviewed by staff. STAFF COMMENT: This project was reviewed for compliance with the Zoning Ordinance, as well as the Application Plan and proffers approved with the ZMA for this project. One change has been proposed since approval of the Application Plan. A storm water management facility is proposed with Phase 1 of the construction. The location of this stormwater facility is within the footprint of the residential building that is proposed with a future phase. The Zoning Administrator has determined that this change is in general accord with the application plan with the condition that the construction of this facility must not impact the required 20 -foot buffer adjacent to the Rural Areas zoned properties on three sides. In addition, the facility must conform to the Application Plan in all other ways. The applicant has worked with other members of the Site Review Committee to resolve issues presented during the initial review of the site plan. This project has been reviewed by the Site Review Committee with additional comments presented below as conditions. RECOMMENDED ACTION Staff has reviewed this request for compliance with the provisions of the Zoning Ordinance and recommends approval of the preliminary site plan subject to the following conditions: The final site plan shall also be subject to these conditions: 1. The Current Development Division shall not accept submittal of the final site plan for signature until tentative final approvals for the following conditions have been obtained. The final site plan shall not be signed until the following conditions have been met: a. Current Development Planner approval to include: i. Approval of Lighting Plan, including specification sheets and photometric layouts for proposed new lights, in accordance with Section 4.17. ii. Approval of Landscaping Plan, including required screening, in accordance with Section 32.7.9. iii. Approval of Conservation Plan, in accordance with the approved Application Plan. iv. Conditions of both Special Use Permits must be included on the site plan. b. Current Development Engineer approval to include review of all applicable items as specified in the Design Standards Manual, as well as: i. Erosion and Sediment Control Plan. ii. Stormwater Management Plan. iii. Please provide all needed easements (or at a minimum for preliminary approval, a letter of intent) from the United States of America for grading, drainage easements, use of the pond, etc. A drainage easement will be needed from both proposed outfalls of the NGIC expansion. Drainage easements should be shown correctly over ditches and drainage structures. iv. Parking areas cannot exceed 5% grade in any direction. v. Grading errors shown on the proposed plan must be corrected. c. Albemarle County Building Official approval. d. Fire and Rescue Division approval to include: i. Verify adequate fire flow is available. e. Albemarle County Service Authority approval to include: i. Dedication of offsite water and sewer is required prior to final approval. ii. Approval of final water and sewer construction drawings. f. Virginia Department of Transportation approval to include: i. Approval of plans for all State maintained portions of the property and entrances into the site. 3 ii. Road and drainage plans need to be provided for the extension of Boulders Road. iii. The plan needs to address the need for a right turn lane into the site. iv. The plan needs to show the proffered improvements to route 29. v. The entrance to the site at Boulders Road needs to be designed in accordance with the Minimum Standards of Entrances to State Highways and VDOT ' s Road Design Manual. ATTACHMENTS: A. Vicinity Map B. Preliminary Site Plan C. Approved Application Plan D. Letter requesting Planning Commission Review E L. 9MdSDP07- 078: NGIC Expansion (Note: Sane items on map may not appear in legand) 1": Q d UJ 600 I xr Z' 1z'o0 4 U2 E: l 29 NU 6 47,) ef s ERShr 23 , 6-', 2 U A"' V 33 - GIS- Web 0 G.= Data ServicesaLmarleorg f d (434 296- 5832 P2 ! 4 " 1 11 3, , -'. x,2 E 29% No" 2KI 0 , "869 Feet OMb. r2,201 NGIC EXPANSION PROJECT SHEET INDEX APPLICATION PLAN for ZONING MAP AMENDMENT ZMA- 2007-003 TO REZONE APPROXIMATELY 15. 0± ACRES FROM RA TO CO j SCALE: 1" = 400' TMP 33- 1D (portion) & 33- 1F (portion) RIVANNA DISTRICT ALBEMARLE COUNTY, VIRGINIA NEXT GENERATION LLC PC BOX 5548 CHARLOTTESVILLE, VA 22QOS E-• GINEER SCCT COLLINS, P. E. COLLINS ENGINEERING 800 E. JEFFERSON ST., SUITE 300 CHARLOTTESVILLE, VA 22902 Attachment C COLLINS EN GINE EFRlNG EXHISIT i - COVER SHEET 1 21, F, w Irl I LAW easTato CIOSTM COLLINS ENGINEERING EXHIBIT 2 - EXISTIrIG COM) ITICNS N -N E, 5 N.3 •2 a sA 51 R 42 4.1 F, w Irl I LAW easTato CIOSTM COLLINS ENGINEERING EXHIBIT 2 - EXISTIrIG COM) ITICNS t' Zr,;.NED i TPAr + {7 1 " l MNED PA Jti.' cp cry =S G= A' +tRCA 'iFZT aEMEPR; CN L .,C 16 6ei AC NF? T GENER;, T ()t4 t 4,1 A,' 77 r „ >•. n iv aVvt Y& A ' --, ' t r ', , + — ` - A _ - __,- -__ r j ! ' w -- _ .. , ; ,,,.'f!° may. t { t ^ l I f ry T . y ~} y .. I r`"' v . J, ! , :1SS' `. fir. - • . rte ` ' ,.,- , .•.gL ; *; -` - %` W- X TMP V-' F KA ZONEIL PA i NE C COLLINS PPI 'CATIG% CO LLINS ENGINEERING 17 D. A ' 53. 82 AC w l jj EXHIBIT , 4 OVERALL STORMWATER INIANAGEMENT PLANCO LLINS ENGINEERING D. A ' 53. 82 AC w l jj EXHIBIT , 4 OVERALL STORMWATER INIANAGEMENT PLAN I' '. 11 1 1A i f G M V 4 Aat Mf i4 9 f— l 10 : ( ZONED lu NEXT 3MRAP00%, Ar Nw s 1'1 C'CT Vi' I IE -- A EXHIBIT OF ZONING k A EX' A'4ERA WEP' F03 FW. EEI S ARM I EN,: D' S T 1 E C''91- Ile t'-T -1 c API E 51 A, 1 COLLINS ENC- INEEPING 1A i f G M V 4 Aat Mf i4 9 f— l 10 : ( ZONED lu NEXT 3MRAP00%, Ar Nw s 1'1 C'CT Vi' I IE -- A EXHIBIT OF ZONING S i J to __ -.._ __ ." -_. _ - - °''.. _ T...•,K.. _ a' _ ''tr'' ham.. Y - ., ._ V `-ir sE1 i t n r z^ 4 COLLINS ENGINEEPING Y I IT 4 ''" CYJ r'1= i._ TZ: J''• a ,rj Page 1 of I From: Marcia Joseph [marcia48I @earthlink.net] Sent: Monday, August 20, 2007 6:54 PM To: David E. Pennock Subject: NGIC Follow Up Flag: Follow up Flag Status: Yellow David, I'd like to call this up for planning commission review. Item Number: SDP2007 -00078 Project Lead Reviewer: David Pennock Project Name: NGIC Expansion Request for preliminary site plan approval for construction of two four -story office buildings totaling 178,800 square feet and site preparation work related to a future project on approximately 15 acres zoned CO - Commercial Office and EC - Entrance Corridor. The property, described as portions of Tax Map 33, Parcels 1 D and 1F, is located in the Rivanna Magisterial District east of Seminole Trail [Route 29N] at the end of Boulders Road [Private]. The Comprehensive Plan designates this property as Industrial Service in the Community of Piney Mountain in the Development Area. Thanks, Marcia Marcia Joseph, ASLA, AlCP At Large Representative Albemarle County Planning Commission Joseph Associates LLC 481 Clarks Tract Keswick, Virginia 22947 Phone 434 - 984 -4199 Fax 434 - 984 -3098 Attachment D tile: / /C: \DPennockDocs \Reviews \Site Plans \2007 \NGIC \Request for PC Review.htm 10/2/2007 qWW vIN1P ALBEMARLE COUNTY PLANNING STAFF REPORT SUMMARY Project Name: SDP 07 -078: NGIC Staff: David Pennock, Jonathan Sharp Expansion — Preliminary Site Plan Planning Commission Public Hearing:Board of Supervisors Hearing: October 9, 2007 Not applicable Owners: Next Generation, LLC Applicant: United Land Corporation Acreage: 15 acres within the 116 acre parcel Rezone from: Not applicable Special Use Permit for: Not applicable TMP: Tax Map 33, Parcel 1 D (in part) and 1 F By -right use: CO, Commercial Office zoning in part)with Special Use permits to allow Research and Development Laboratories andLocation: East of Seminole Trail [Route 29N]Residential uses at the end of Boulders Road [Private] Magisterial District: Rivanna Proffers /Conditions: Yes Requested # of Dwelling Lots: n/a DA— X RA— Proposal: Request for preliminary site plan Comp. Plan Designation: Industrial Service approval for construction of two four -story in the Community of Piney Mountain in the office buildings totaling 178,800 square feet Development Area and site preparation work related to a future project for a 120 -unit residential building. Character of Property: This property is Use of Surrounding Properties: Adjacent to currently partially wooded, with some meadow the existing National Ground Intelligence areas, unimproved roadways, and drainage Center (NGIC) and to low density swales.residential /rural uses Factors Favorable: (see report)Factors Unfavorable: (see report) RECOMMENDATION The preliminary site plan cannot be approved as submitted Ig1oI_sU PC. t n i 'lrt UST - AMEND eW so TL TAT kV pAW i 5 IN V rr44 L t f bij f P6K Muir S V I1 Q (N A`t lr/RS EN1'Fp y(ONi(,t {T PLAN 1 EfF_W To 6&111 190,SUILE bft STAFF PERSON PLANNING COMMISSION SITE PLAN PROPERTY OWNER APPLICANT David E. Pennock, Jonathan Sharp October 9, 2007 SDP 07 -078: NGIC Expansion — Preliminary Site Plan Next Generation, LLC United Land Corporation APPLICANT'S PROPOSAL Request for preliminary site plan approval for construction of two four -story office buildings totaling 178,800 square feet and site preparation work related to a future project for a 120 -unit residential building. This project was called up for review by the Planning Commission. CHARACTER OF AREA This project ise within an area east of Route 29N at the end of the previously constructed portion of Boulders Road, which currently serves the National Ground Intelligence Center (NGIC). Camelot and Briarwood subdivisions are on the west side of Route 29N at this location, and General Electric has a facility nearby. The North Fork of the Rivanna River flows adjacent to portions of the NGIC site. The surrounding properties include mostly low - density rural residential uses, the majority of which are also owned by this applicant. PLANNING AND ZONING HISTORY ZMA 07 -003 NGIC Expansion: This property was rezoned to Commercial Office in August, 2007, with proffers and a proffered application plan showing the construction of two office buildings and a residential building, as well as the extension of Boulders Road and some associated improvements to Route 29. SP 07 -031 Special Use Permit - Residential Units: A special use permit was approved with conditions in August, 2007 in order to allow Research and Development Laboratories. SP 07 -032 Special Use Permit- Research & Development; Labs: A special use permit was approved with conditions in August, 2007 to allow residential uses on this property. ZMA 99 -002 Value America: A rezoning was submitted in 1999 for Light Industrial on a portion of TMP 33 -ID, but was eventually withdrawn. SP 99 -033 NGIC Access Road: A special use permit was granted in August, 1999 to allow fill in the floodplain for the construction of the access road (now known as Boulders Road). COMPREHENSIVE PLAN: The Comprehensive Plan designates this property as Industrial Service in the Community of Piney Mountain in the Development Area. REASON FOR PLANNING COMMISSION REVIEW: Request for review of a preliminary site plan by the Planning Commission in accordance with Section 32.4.2.6. This application has been requested for review by a member of the Planning Commission Attachment Q. 2 STAFF COMMENT: This project was reviewed for compliance with the Zoning Ordinance, as well as the Application Plan and proffers approved with the ZMA for this project. Based on recent changes to the design, the plan is no longer in compliance with the approved application plan. A stormwater management facility is proposed along the southwest line of the office buildings. This facility requires substantial grading that will extend from the edge of these buildings through the 20 -foot buffer and in to the adjacent parcel. As such, two waivers are necessary for the plan to proceed as submitted. First, the application plan must be amended through approval of a "Minor Variation to the Approved Plan ", in accordance with proffer #4 of ZMA 07- 003. Assuming approval of such a variation, the applicant must also pursue a waiver in order to disturb the required 20 -foot buffer that abuts all residential and rural areas districts. This waiver requires the approval of the variation referenced above, as well as approval by the Planning Commission, in accordance with Section 21.7.3 of the Zoning Ordinance. Neither of these waivers has been requested at this time. The applicant has worked with other members of the Site Review Committee to resolve issues presented during the initial review of the site plan. This project has been reviewed by the Site Review Committee with additional comments presented below as conditions. RECOMMENDED ACTION Based on the non - conformity with the approved Application Plan, as well as the lack of a necessary waiver for buffer disturbance, the preliminary site plan cannot be approved as submitted. These modifications must be approved prior to preliminary approval of the site plan. The final site plan shall also be subject to these conditions: 1. The Current Development Division shall not accept submittal of the final site plan for signature until tentative final approvals for the following conditions have been obtained. The final site plan shall not be signed until the following conditions have been met: a. Current Development Planner approval to include: i. Approval of Lighting Plan, including specification sheets and photometric layouts for proposed new lights, in accordance with Section 4.17. ii. Approval of Landscaping Plan, including required screening, in accordance with Section 32.7.9. iii. Approval of Conservation Plan, in accordance with the approved Application Plan. iv. Conditions of both Special Use Permits must be included on the site plan. b. Current Development Engineer approval to include review of all applicable items as specified in the Design Standards Manual, as well as: i. Erosion and Sediment Control Plan. ii. Stormwater Management Plan. iii. Please provide all needed easements (or at a minimum for preliminary approval, a letter of intent) from the United States of America for grading, drainage easements, use of the pond, etc. A drainage easement will be needed from both proposed outfalls of the NGIC expansion. Drainage easements should be shown correctly over ditches and drainage structures. iv. Parking areas cannot exceed 5% grade in any direction. v. Grading errors shown on the proposed plan must be corrected. c. Albemarle County Building Official approval. d. Fire and Rescue Division approval to include: i. Verify adequate fire flow is available. e. Albemarle County Service Authority approval to include: i. Dedication of offsite water and sewer is required prior to final approval. ii. Approval of final water and sewer construction drawings. f. Virginia Department of Transportation approval to include: i. Approval of plans for all State maintained portions of the property and entrances into the site. ii. Road and drainage plans need to be provided for the extension of Boulders Road. iii. The plan needs to address the need for a right turn lane into the site. iv. The plan needs to show the proffered improvements to route 29. v. The entrance to the site at Boulders Road needs to be designed in accordance with the Minimum Standards of Entrances to State Highways and VDOT ' s Road Design Manual. ATTACHMENTS: A. Vicinity Map B. Preliminary Site Plan C. Approved Application Plan D. Letter requesting Planning Commission Review 11 24) - , j- 93- 32G- G7 -- 52i G -,IN32A CKEV oe 2 2G- 07= 0 192 32G- 07--," 32G- 1 32& CiY= 32E - W - - 33 3 E; 2E- 03--3 32- SC 3 32- SC3 ,' 33- IF 32E-- UB 1 32- SCI 32E "° 6 - 2 # "h721E21 E 9 C -' 04 Jcolt 32- 5 32C.- 1 ii- ` "** 32E- 06-23 ;2E -- _1I 3UtF t 33- 14 33 32E 32- 5C4 Wc 27SP- Note: Some Iii on map may not appear in legend) 0 A- ISA2 32G- C 32- 6A 32- 5A 29 3: 3 5 32- 22KI 0 22K I3 6A 1.- 13 60 O/ 33- 6 ....... 7 4, 2143 5 f , 7C 33- 4 - 33- 7 3 kp 3- 4'A 1--, 6) 33!:-:,! B A 3- 9 3 3 -,4 C J 33- 10 33- 33- 12 for display purposes only • Aerial Imagery 2002 Commonwealth of Virginia October 2, 2007 GIS- Web Geographn: Data Services www aIbemarle org 434) 296- 5832 33- 13 hF 3: 3-12E 33- 126 Feet869Flk for display purposes only • Aerial Imagery 2002 Commonwealth of Virginia October 2, 2007 NGIC EXPANSION PROJECT APPLICATION PLAN for ZONING MAP AMENDMENT ZMA- 2007-003 TO REZONE APPROXIMATELY 15. 0±- ACRES FROM RA TO CO SHEET INDEX SCALE': I" = 400' TMP 33- 1D ( portion) & 33- 1F (portion) RIVANNA DISTRICT ALBEMARLE COUNTY, VIRGINIA COLLINS ENGINEFERING i , ` , .,EXHIBIT COVER SHpF--' OWNER: NEXT GENERATION LLC PC BOX 5548 CHARLOTTESVILLE, VA 22905 ENGINEER: SCOTT COLLINS, P. E. COLLINS ENGINEERING 800 E. JEFFERSON ST., SUITE 300 CHARLOTTESVILLE, VA 22902 Attachment C AJ' %: ; 7 7 7 SCALE': I" = 400' TMP 33- 1D (portion) & 33- 1F (portion) RIVANNA DISTRICT ALBEMARLE COUNTY, VIRGINIA COLLINS ENGINEFERING i , ` , .,EXHIBIT COVER SHpF--' OWNER: NEXT GENERATION LLC PC BOX 5548 CHARLOTTESVILLE, VA 22905 ENGINEER: SCOTT COLLINS, P. E. COLLINS ENGINEERING 800 E. JEFFERSON ST., SUITE 300 CHARLOTTESVILLE, VA 22902 Attachment C om RA VART ESTA Ac 4 10 YEAH 4,STO ZI: 4 LN fW FLOCS -LAIN OF r TlW 32-6C FxIS7149 4 NEX- 3PNEFU'j 'ON. L't C $ Ex' s WEU - WGF- TK L — nw212, AC C 6 Ec ZAMFLUI AATeRUNE aw k 24 T, j"! TEQ SlArES 0 WERv 4W-3 IA i_ , ° \, •tea -"Y `fir'. _ -- +''_ - s - ein A ._' 1, YEW, -W Pogo mp 33-zc-= OF T N EKE A - F 4 EIS C 0 RN E UM r TNE = ,yR Z: E REZGN RC jLD 5-.- E ACCESS' . a, PAR,:'-L c,- BE 5'_k8_: ;Q NC 7 Ef, Uv,LCPEZSM I- B PARCP AN INZ! , ST 0-REC N;7jl -- ?LFFEP fKSTSAL0I7, , 1 iT BE PAR ;E SEC CA, ICT6E SEENF*1- COLLINS ENGINEEPiNG ' 2 -,-') 7 EXHIBIT 2 - EXISTING CONDITICNS Ad -v e vY AtEelijll$ n COLLINS ENGINEEPiNG ' 2 -,-') 7 EXHIBIT 2 - EXISTING CONDITICNS ZONED PRD Nlzll 75 7z, r J v P TMP 3-k- 14 ZONED RA NEXT GENERAT; 01. LLC 15.212 AC 4 0 , 40 ZONED Li ED STATES OF AMERI;_ A 28 880 AC EXiSTINC PPOPERT PAP 32- 5Cd TMP 3331 F ZONED RA ZONED RA UNITED STATES OF AMERICA NEXT GENEFIkT] ON, L.LC .. 46 671 AC 16 0 AC L "'RIP GENERATION ESTM', TES COLLI N 5 ENGINEERING I 1 .1 -N PLL.' NiEXHIBIT3APPLICATIO Q1i4SE ii TMP 32- 5 u ZONED L7 _ UNITE,'; STATES Os- AM RICA " 2E 83C rC -- ' i TNIP 32 5L: 4 TMP 33 -'F ZONED RA7ONECFA NEXT GENERAT; ON L LCuMT =G STATES OF NkTR1CA P, 86? Ay45. 671 A, C O Lr L. I h 5 j EXHIBI T 3 4PP! T CATION Fi_% -, V - -- — MP 33-10 4'} "NEXT GENE. P TON, L. L.0 v ; . nom. ! ,• W x wF _ ... i - '•. /. • "; J' 75 dau t b . c -,15: r. •/", / .. J•: .r, > t.. c "x r;' i .c , K.._.u< _ • _, .: -,, r: H,_ w _ ,., _,, ,.5 ... ,. , _.. .. " . .. - - u _. •.r i = A.rtM'+' j . fv^' er. . - :.F lx,.wc s a.. t tr ^ •': ..5cj 9i .: ^r_Rt RCr._ y• i; -'' . 8n.:sc: .. ..- ,>t+ .¢y,¢.- ,aMrE - _ _ : -'- _-- •. -- -___ - -- _- __ - _•._ - -_'__ l " 'C_ —EXi _'•s; 1'..}' :f "_ -. - II ^ -_ a, - -.r'+n ,.v and e'M .0 r.cr.. l• l.vb 1 ` I /. ! \_- •S._/ \ ..r `. / /.+ - - ' i ARr• :r_>. -w- GY4. r :r. -N . _ . G\ / / ! Y - +I-- axsw. •z eJ Pecs ,_ , C:. = , c..r ! . u. - _ f , } - /, - - _ - s. :. 2•+.. Y ». '. 4... aa ..P a..,.•.. _ ..rte. .a,r - r. tia - eif JJ ",y / l/ y n. - -- - - j c» w .a-rm _ * .a +..:.• r n «w- . • >/ :' - , fi' I y .c••v _. -.a: es•.a.t -.,F St R: J. in ` " • P fR / __lam e'•_ ae'gr' ^•w' S +r.z sr > ! -:' _' tC sr n "f' ! S _ \ _ __ _ 5 ` 8- ' - _ www.'.•+:f :Y' nr .fa_ ,p- M( m ti )rq- x f . t. ; \ \ 9lure. Y >'- : " 6 'i[ K3Crnd• r;tn.. .'w. .w >nv' 1 J 1 ' , \' ara .e.- n1 S.:'." • ['TCw nFv .. . t , d I • / I ., / ,_ Y ' `" `.' • +/ - ru,,. rw ra^. m,. A a• .-a Sr..._ a .. -a. +,. u,.0 . . S 1 % •> ^--` r. <-. Al i. , mss: L• r. ,... r 'n,...„i:. .: .«r'.a - r / tP TMP 3 S •alx5 J R J •}as !w v »Yana Yt.'MY w..., - r ,w . I ir i t .:, - _> J'`', {¢ /'Ay<. . re .r.,..,• re w s' i :.F ,,.' r:.. u. c Ef ..: - -, : r f j % 7 ',_'+ -` :t' t i' S {r'' ! j ZONE:. RA NEXT GENE-RA'iON LL C T W-- Lt4 MAK— — K I Tm W A.Df-. At mA, wlf Afi lfY4. THE fPeCV1 Zl"L Y1 COLLIN5 ENGINEERING I EXHIBIT 4- OVERALL STORMWATER MANAGEMENT PLAN LIM ofI j.i{AX7C P KN 7oc A =53, 82 AC POND lo 0 COLLIN5 ENGINEERING I EXHIBIT 4- OVERALL STORMWATER MANAGEMENT PLAN 4f7,_ EIERF l L COLLIN5 ENGINEERING : C ALE 6- EXHIBIT 5 - LIlMITS 0 ZONING Tw kl 8 d 1F3 fjc tla,— 1- h 50'. d,—i— f '4 d N S0A —1 Mu Jf 2L I fi CANN=! t ZL "acD RA FR, ASe P. 322 DOYER ROA: 1 C' RARLCT LE. VA --%- MARTN ROVAd fG !:S 0 2' 'hccce -.str -xj s 3 3721 W ROA 7 2 ' OA'4 I " W, . d MAr of " 0 47 If 77 1 &C%, 11 1taG co to F .—f. NfXTGE4ERATK— t Lf of 172 9? f— ih— -l-= g . ft 33' 41' 14 .— . FIC !k) X .5s5 C 1 flV. dw— of '4- f—, NEXT Gk:SERAI'0, C i-- $745*42 po Sox 5549 iux G2 NEX7 ^Gt- JERAMt 4 L,L C F-D 90A S&O a* 3 0 t;,— - Cli. J;V 0TES LLE, VA dh a , ,N W 04 feet. 'h.— —tivai" i NEXT GEYERATk' h, LAC h FID Sox 6948 4 w TSC < d.-- ^l 32 tor: :,, Poec:) >: ii< g;: :ag ChARLCT !4 22 93 41" IMP 5-1 0 OON SW Cw VA 1, X E- R UWTFO STATES Cc AME- C*o JS AWr E. G , l47 A-N PE DIL. E-M FRONT STR= EET NL*VFC" VA 235' 9 UNMED STA- ES fF AW° Cl GK) US ARMY ENG :)!ST AT; RE 50 FRONT ! K VA235 NjxT -IENERATON, L C— k a rEs.kLE. •A t tdE1T.; Eyc_RAT uN t .LL be 511t COLLIN5 ENGINEERING : C ALE 6- EXHIBIT 5 - LIlMITS 0 ZONING 0' 4' i—L a Ei.—W 41"S 98 f— Ml- 8 d 1F3 fjc tla,— 1- h 50'. d,—i— f '4 d N S0A —1 Mu Jf 2L t ZL "acD RA FR, ASe P. 0 2' 'hccce -.str -xj s 3 7 2 ' OA'4 I " W, . d MAr of " 0 47 If 77 1 &C%, 11 1taG co to F .—f. of 172 9? f— ih— -l-= g .ft 33' 41' 14 .— . C 1 flV. dw— of '4- f—, i-- $745*42 iux G2 a* 3 0 t;,— - dh a , ,N W 04 feet. 'h.— —tivai" i h 4 w TSC < d.-- ^l 32 tor: :,, Poec:) >: ii< g;: :ag 93 41" COLLIN5 ENGINEERING : C ALE 6- EXHIBIT 5 - LIlMITS 0 ZONING t ZL "acD RA U,- AC IMP 5-1 1, X E- R T 21 -13 ZONEDLU W- Xr G& r C 12- W AC COLLIN5 ENGINEERING : C ALE 6- EXHIBIT 5 - LIlMITS 0 ZONING I Ei; Sit - fz c r r i nn s a I COLLINS ENGINEERING EXHIBIT 6 SIT= CROSS -SEC -, 1ONS Page 1 of 1 From: Marcia Joseph [marcia481 @earthlink.net] Sent: Monday, August 20, 2007 6:54 PM To: David E. Pennock Subject: NGIC Follow Up Flag: Follow up Flag Status: Yellow David, I'd like to call this up for planning commission review. Item Number: SDP2007 -00078 Project Lead Reviewer: David Pennock Project Name: NGIC Expansion Request for preliminary site plan approval for construction of two four -story office buildings totaling 178,800 square feet and site preparation work related to a future project on approximately 15 acres zoned CO - Commercial Office and EC - Entrance Corridor. The property, described as portions of Tax Map 33, Parcels 1 D and 1 F, is located in the Rivanna Magisterial District east of Seminole Trail [Route 29N] at the end of Boulders Road [Private]. The Comprehensive Plan designates this property as Industrial Service in the Community of Piney Mountain in the Development Area. Thanks, Marcia Marcia Joseph, ASLA, AICP At Large Representative Albemarle County Planning Commission Joseph Associates LLC 481 Clarks Tract Keswick, Virginia 22947 Phone 434 - 984 -4199 Fax 434 - 984 -3098 Attachment D file: / /C: \DPennockDocs \Reviews \Site Plans \2007 \NGIC \Request for PC_Review.htm 10/2/2007