Project: Flow Porsche [SDP200700012, WPO2007000041
Plan preparer: Collins Engineering [fax 245 -0300]
Owner or rep.: Flow Automotive [fax (336) 760 -7005]
Plan received date: 06 Feb 2007
Date of comments: 09 Feb 2007
Reviewer: Jonathan Sharp
A. Final Site & Drainage Plans (SDP200600127)
This site refers to the Flow Automotive site (SDP200600127) as existing, when this site plan has not even
been approved (nor has the SP associated with it been approved). The submitted plans for Flow Porsche do
not appear to be approvable until the prior site is approved and built. Engineering recommends combining
the plans and phasing them, in order to be able to approve both plans at the same time.
1. Please provide a professional signed and dated seal. [18-32.6. 11
2 Please show the layout of the entire site (parking, travelways. dumpsters, etc.)
3. 1 cannot tell the difference between the proposed grading for the proposed project compared to the
proposed grading for the adjacent project. Several of the proposed grading lines intersect or
branch.
4. The existing topography appears to be incorrect. Grade lines intersect and branch off.
5. Sidewalk directly adjacent to parking must be 6' in width or parking spaces must have bumper
blocks.
6. Travelways adjacent to 9'x 18' spaces must maintain a 24' width.
7. Please provide pipe profiles, calculations, and a drainage summary table.
8. Travelway grades must not exceed 10 %, parking cannot exceed 51 and the first 40 feet of the
entrance must not exceed 4 %.
9. The dumpster pads must extend 8 feet in front of the dumpster.
10. VDOT approval is required.
11. More comments may be necessary upon resubmittal.
B. Stormwater Management Plan (WP0200600089)
Please provide a Stormwater Management Plan and application for the water quality structures. Stormwater detention
can be provided by the adjacent property. however, since it does not yet exist, the plans cannot be approved until the
adjacent property is in place. Please provide a stormwater maintenance agreement. Also, the Filterra units should be
arranged so that the they capture an equivalent area compared to the amount of impervious area added during
SDP200600127 and SDP200400027. The Filterra units will need approval from Filterra. Additional comments will
be provided once a Stormwater Management application has been completed.
C. Erosion Control Plan (WPO200600089)
Same as the minor amendment and stormwater management plan, the current E &S plan would not be able to be
approved until the adjacent property actually exists as shown.
1. The site is not protected, as more than I acre will flow to inlet protection.
2. Show the limits of disturbance.
3. Please provide drainage area maps.
4. Show dust control, temporary seeding, and permanent seeding.
5. Provide perimeter controls.
6. More comments may be necessary upon resubmittal.
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902 -4596
Phone(434)296 -5832 Fax (434) 972 -4126
Project: Flow Automotive [SDP200600127]
Plan preparer: Collins Engineering [fat 245 -03001
Owner or rep.: Flow Automotive [fax (663) 760 -7005]
Plan received date: 17 May 2007
Date of comments: 24 May 2007
Reviewer: Jonathan Sharp
The following review comments replace the earlier review comments for Flow Automotive (dated
22 Jan 2007) and Flow Porsche (09 Feb 2007).
As you are combining Flow Porsche with Flow Automotive, do you want to have SDP200700012
and WP0200700004 withdrawn?
A. Final Site & Drainage Plans (SDP200600127)
1. There is a concern with the proposed layout of the Flow Auto building in regards to the
deep hole, existing drop inlet structure 4, and the retaining wall and building footer which
is up to over 20 feet high. Will the building have a basement? If the drop inlet fails (as it is
currently now clogged), it could flood the building. Please provide more information in
regards to the proposed building. Engineering recommends filling the area and getting rid
of the giant hole. This could decrease the height of the building footer or retaining wall up
to 10 feet. [DSM505G6]
2. Please provide more information about the covered roof area. Where will the columns
holding up the roof be located?
3. VDOT approval is required for the entrance improvements affecting VDOT right-of-way.
DSM902B]
4. Please provide easements for all off -site work. [DSM 1 102]
5. "There is concern with the 2:1 or greater slopes near the northwest corner of the site.
DSM902A5]
6. Otfsite proposed drainage easements will need to be platted and signed by adjacent
owners.
7. Curb and gutter is required in all newly proposed parking areas. (everywhere except for
the parallel parking spaces running along the east side of the site) [I 8.4.12.15g]
8. Several of the parking spaces are unprotected. They will need to be protected by parking
islands. [DSM902A5, 18- 32.7.2, 18- 4.12.15t]
9. Parking grade cannot exceed 5% in any direction. [18- 4.12.15e]
10. The dumpster located on the Flow Auto /Porsche Parcel is not accessible. [ 18- 4.12.15e]
H. Several of the parking and aisle dimensions do not meet County Code. [ 18- 4.12.16a,c,
DSM602.1 ]
12. Access aisle grade cannot exceed 10 %. [18- 4.12.17a]
13. Access aisles without adjacent parking must maintain a minimum 20 width. [18-
4.12.17c1]
14. Proposed elevation contour 424 is mislabeled as 423.
Albemarle County Community Development
Engineering Review Comments
Page - of 2
15. The bottom of wall elevation of 400 at the northwest corner of the proposed Flow Auto
building appears to be incorrect.
16. The sidewalkAvall area where elevations 413, 414, and 415 converge at the proposed Flow
Porsche building appears to have very steep grades.
17. The dumpster pad waiver has been granted by Zoning.
18. The parking space extending over property line will not be an issue as there is a proposed
access easement.
19. Several of the drainage areas for inlets are incorrect.
20. Safety slabs are needed for manholes greater than 12" deep. [DSM505E9]
21. Additional comments may be necessary upon resubmittal.
B. Stormwater Management Plan (WPO200600089)
1. Several of the Filterra units are configured in a manner in which they capture little to no runoff.
How does runoff drain from the roof of the proposed Flow Auto building? Will it make it into the
Filterra unit? (This is to make sure roof drains will not tie directly into the pipe system and bypass
water quality.)
2. There is not enough information provided for the detention system to adequately construct it or
verify if detention is adequate. Site specific details are necessary; the provided details are too
generic and are very confusing. Please provide cross section details of the detention system and
plan view section details. Please provide details of the outlet structure. Please indicate the location
of cleanout /inspection points, vents, etc.
3. A letter of approval is required from Filterra.
4. Please provide a stormwater maintenance agreement. Agreements will be needed for TMP 78-
14D, TMP 78 -15D, and TMP 78 -15E.
5. Additional comments may be necessary upon resubmittal.
6. A stormwater bond will be computed once the plans are approved.
C. Erosion Control Plan (WPO200600089)
1. Please provide copies of the needed construction easements. [DSM1 102]
2. There is work shown outside the limits of disturbance in all phases. [VESCH ch. 6 pgs. 13 -141
3. Please show the tree protection and tree protection details on the E &S plans. [VESCH 3.38]
4. In Phase 11, please use inlet protection rather than culvert inlet protection for the 0.2 drainage area
draining to structure 13. [VESCH 3.07]
5. Please address when existing structures 3 and 4 will be connected with the E &S plan. It may be
better to do this during the initial phase (phase 0). Also please address cleaning out the covered up
existing drop inlet (structure 4) in the narrative.
6. Please show permanent stabilization (PS) on the plans. [VESCH 3.32]
7. An E &S bond will be computed once the plans are approved.
Application #: SP200700045' iShort Review Cormnen s
Project Namea Fl Automotive New Special Use Permit
Date Completed: 10/31/2007
Reviewer: Gary Whelan ACSA
Review Status: Requested Changes
r - -Reviews Comments: This property was previously a water and sewer customer. The water service is shown on earlier
plans but not the sewer service. We would like for the old sewer service to be shown and noted if it is
cut and capped.
Date Completed 01/02/2008
Reviewer: Gary Whelan ACSA
Review Status: No Objection
Reviews Comments: IThe ACSA doesn't have any comments on the SP, but we will for the site plan.
Date Completed: 01/07/2008
Reviewer: Glenn Brooks Engineer Z &CD
Review Status: Pending
Reviews Comments: I have no comments on the display use. Please see previous comments regarding the plan.
Date Completed: 10/25/2007
Reviewer: Glenn Brooks Engineer Z &CD
Review Status: Requested Changes
Reviews Comments: It is recommended that stormwater management be provided for this site and a portion of the
upstream existing site. An analysis of the downstream system will be required with final plans, as it
may not be adequate.
Permission from off -site owners for work should be provided prior to approval of the SP
Public drainage easements will be required for drainage from the right -of -way. Private easements will
be required for increased drainage through downstream sites.
Parking rows must be protected with curbed islands in the service area.
Page: 1.00 County of Albemarle Printed On. Monday, March 31, 2008
The turn lane should have a taper.
Date Completed:11/09/2007
Reviewer:Joel DeNunzio VDOT
Review Status:Requested Changes
Reviews Comments:1. No comments on the width of the spaces or the parking turnarounds.
1:2. The internal flow of the site should accommodate truck traffic being able to maneuver within the
site to flow in and out without stopping or backing onto route 250.
3. The improvements shown on route 250 were included with a previous site plan. The road and
drainaye plan need to also be included when this site is submitted for a site plan.
Date Completed:11/02/2007
Reviewer:Margaret Maliszewski ARB
Review Status:Requested Changes
Page: 1.00 County of Albemarle Printed On. Monday, March 31, 2008
Reviews Comments: ,This proposal is eduled for ARB review on November 5, 2C ,omments will be provided after
that meeting.
Date Completed: 10/30/2007
Reviewer: Tamara Ambler Planning
Review Status: No Objection
Reviews Comments: I No water resources are located on the parcels associated with this project. The parcels are within
2,000 feet of two open DEQ leaking underground storage tank cases. However, given that the
parcels are served by public water no impac is anticipat II
Page: 2.00 County of Albemarle Printed On: Monday, March 31, 2008
Iflll"
IL
County of Albemarle
Department of Community Development
Memorandum
To: Gerald Gatobu, Current Development planning review
From: Jonathan Sharp, Current Development engineering review
Date: I I Oct 2007
Subject: Flow Automotive - Major (SDP200700099)
Before Engineering can recommend preliminary and final approval to the major amendment, the following
comments must be addressed:
1. One hundred feet on -site sight distance must be maintained by use of curbed islands a minimum 6'
off building corners or other obstructions.
2. Curbing required on all proposed parking areas and travelways with VDOT designation (CG -2,
CG,6)
3. All parking rows must be protected by curbed islands (for both the parallel and perpendicular
spaces). The parallel spaces must be also be protected by curbed islands on the back side (side
adjacent to the canopy. Curb islands must be a minimum 3" in width.
4. Will the existing perpendicular parking area directly adjacent to the guardrail and trees be removed
or relocated?
5. Proposed parking areas cannot exceed 5% grade in any direction.
6. Please provide pavement design /details for proposed paving.
7. Please provide an adequate sidewalk detail: minimum 4" stone base and 4 " of concrete of 3000 psi
at 28 days, or stronger.
8. Please provide Albemarle County general construction notes per Design Manual.
9. The tree protection is shown in the pavement. There doesn't appear to be any work near the trees.
Tree protection is probably not needed.
s F AL
GIM
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, North Wing
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832
November 15, 2007
Sheeran Architects
c/o Peter Sheeran
226 East High Street
Charlottesville, Va 22902
RE: ARB2007 -00098 Flow Auto - Display Parking Addition
Tax Map 78, Parcels 15D, 15E
Dear Mr. Sheeran:
Fax (434) 972 -4012
The Albemarle County Architectural Review Board, at its meeting on November 5, 2007, completed a
preliminary review of the above -noted request. The Board took the following actions.
Regarding the Special Use Permit /Rezoning the Board by a vote of 5:0, forwarded the following
recommendation to the Planning Commission:
The ARB expresses no objection to the special use permit, subject to the following conditions:
1. Vehicles shall not be elevated anywhere on site.
2. Vehicles shall be displayed only in areas indicated for display shown on the plan entitled "Flow
Automotives" prepared by Collins Engineering and dated 9/17/07. Display parking shall be only in
designated striped parking spaces, as identified on this plan.
3. Final site plan approval is subject to ARB approval of the lighting plan (submitted with the site plan).
Maximum light levels on site shall not exceed 30 footcandles.
4. Final site plan approval is subject to ARB approval of the landscape plan (submitted with the site
plan). Landscaping shown on the plan will be required to be in excess of the minimum requirements of
ARB guidelines and /or the Zoning Ordinance to compensate for the negative visual impact of the
proposed use, including but not limited to the use of larger caliper trees, additional evergreen shrubs
and continuous interior planting islands.
Regarding the Preliminary Site Plan the Board made the following comments and suggestions for the benefit
of the applicant's next submittal.
1. Coordinate parking totals and labeled spaces on sheet S -1.
2. Revise the two long internal planting islands to continuous planting islands. Eliminate the gaps in
both islands.
3. Revise the landscape plan to include 3 large shade trees and evergreen shrubs in the long planting
islands located at the interior of the display parking area.
4. In the planting areas that front the EC replace the Inkberry holly with an alternate species and indicate
the plant size as 36" minimum at planting on both parcels.
5. In the planting island the fronts the EC, revise the row of holly to a staggered row on both parcels.
6. Extend the evergreen shrub row that fronts the EC into the end islands that frame the entrance to the
site.
7. Space the large shade trees at 35' on center along the EC on both parcels.
8. Add interspersed ornamental trees along the EC, on both parcels.
9. Revise the existing conditions plan to include the existing plants on the east side of parcel 15.
10. Replace the White pine with an evergreen tree that provides more consistent long term screening and
one that is better suited to the available space.
11. Replace the Hemlock with a more disease resistant tree.
12. Include the VT plant in the plant list or eliminate it from the plan.
13. Provide shade trees on parcels 15 and l 5E at 40' on center along the shared property line. Stagger
these trees.
14. Continue the mixed planting along the full length of the area between parcels 15 and 15E. Do not stop
short of the southern property line.
15. Add Schip laurel to the planting area between parcels 15 and 15E.
16. Provide 2 large shade trees and evergreen shrubs in each end island along the travelway shared
between parcels 15D and 15E.
17. Coordinate the appearance of the three end islands located along the travelway that is shared between
parcel 15D and 15E.
18. Replace the Redbuds with Serviceberry.
19. Coordinate all landscaping with existing and proposed utilities and easements.
20. Include the following note on the landscape plan: "All site plantings of trees and shrubs shall be
allowed to reach, and be maintained at, mature height; the topping of trees is prohibited. Shrubs and
trees shall be pruned minimally and only to support the overall health of the plant."
21. Revise the photometric plan as follows:
a. Use 1.0 as the maintenance factor (LLF).
b. Limit light levels to no greater than 30 footcandles.
c. Show lighting levels out to the property line.
d. Limit spillover at the property line along Route 250 to less than .5 footcandles.
e. Clearly indicate the proposed color for the fixtures on the plan. Bronze is recommended.
22. Resolve the grading issues on the west and south sides of the site regarding retaining walls, level
planting area, filteras, etc. Include proposed grading on the landscape plan.
23. Provide revised architectural elevations for the addition to the existing building. Coordinate the size of
the building illustrated in the elevations with the size of the building illustrated on the plan. Maintain
the window at the south end of the west elevation in the revised design.
24. Add an understory of evergreen shrubs in the island between the Entrance Corridor and the
maintenance building to the south.
25. The shade trees shall be a minimum of 3 '/" caliper. Ornamental trees and other understory trees shall
be a minimum of 8' in height. Shrubs shall be a minimum of 3' in height.
You may submit your application for continued ARB review at your earliest convenience. Application forms
checklists and schedules are available on -line at www.albemarle.ora /nlannina.
Revised drawings addressing the comments listed above are required. Include updated ARB revision dates on
each drawing. Please provide a memo including detailed responses indicating how each comment has been
addressed. If changes other than those requested have been made, identify those changes in the memo also.
Highlighting the changes in the drawing with "clouding" or by other means will facilitate review and approval.
If you have any questions concerning any of the above, please feel free to call me.
Sincerely,
Margaret Maliszewski
Principal Planner
Cc: Don Speight 1425 Plaza Drive Winston - Salem, N.C. 27103
Linkous, Janice S 2205 Shepherds Ridge Rd Charlottesville Va 22901
AL
O 9
IRGII
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
April 2, 2008
Mr. Scott Collins
Collins Engineering
800 East Jefferson Street
Charlottesville, Virginia 22902
RE: SDP - 2008 -038- Flow Automotive- Final Site Plan
Mr. Collins:
The Site Review Committee has reviewed the development proposal referenced above. Preliminary
comments for the following divisions of the Department of Community Development and other agencies,
as applicable, are attached:
Albemarle County Division of Zoning & Current Development (Engineer)
Albemarle County Division of Zoning & Current Development (Planner)
Albemarle County Division of Planning (E91 1)
Albemarle County Division of Zoning Inspections
Albemarle County Division of Planning (Architectural Review Board)
Albemarle County Department of Fire Rescue
Albemarle County Service Authority
Virginia Department of Transportation
Comments reflect information available at the time the development proposal was reviewed, and should
not be considered final. However, the Site Review Committee has attempted to identify all issues that
could affect approval of the proposed project.
Please make the revisions that have been identified as necessary for preliminary approval by the Site
Review Committee. If you choose not to make the requested revisions, please submit in writing
justification for not incorporating such revisions. Submit eight (8) full size copies and one (1) 11" x 17"
copy to the Department of Community Development including responses to each of the attached
comments of the Site Review Committee by April 14, 2007. Failure to submit this information by this
date will result in suspension of the review schedule. Review will resume when revisions are submitted
along with a reinstatement fee of $65.
Please contact me at your earliest convenience if you have questions or require additional information.
Sincerely,
Megan Yaniglos
Planner
Zoning & Current Development
t '
VIRGINIA
DEPARTMENT OF TRANSPORTATION
1601 Orange Road
Culpeper, Virginia 22701
David S. Ekern, P.E.
VirginiaDOT.org
COMMISSIONER
April 3rd , ? 008
Mr. Glenn Brooks
Department of Engineering and Development
401 McIntire Rd.
Charlottesville, VA 22902
Subject: Site Review Meeting Cornments April 3' d , 2008 site review meeting
Dear Mr. Brooks:
Below are VDOT's comments on the Site Plans for the April 3 2007 Site Review Committee
Meeting:
SDP - 2008 -00038 Flow Automotive -Final (Megan Yaniglos)
Adjacent property TMP -78 -15 has a site plan to continue the right turn lane. Effort
should be made to coordinate the construction of these sites to minimize traffic
interruption and construction costs.
The radius of 13 feet at the east end of the property should be 25 feet and CG -6 should be
used.
The flow line at the eastern entrance should be adjusted to allow for future extension of
the right turn lane. Sight distance towards the east needs to be shown at this entrance.
The drainage areas need to be checked on the road sections. It appears that the centerline
of the road is the divide and this section of road is in a full super section. Structure EX5
needs to be relocated instead of removed and because the spread on EX -4 is greater than
the allowable spread.
SDP - 2008 -00039 Durkin Property / Verizon Wireless Final (Gerald Gatobu)
No comments
SDP - 2008 -00040 Final Touch — Prel. (Summer Frederick)
The sight distance at the existing entrance needs to be shown.
Show the proposed ROW lines.
The final plan will need road and drainage plans.
Any work within the VDOT ROW will need a Land Use Permit.
00YEARSOF
TRANSPORTATION EXCELLENCE
916 200 6
SDP - 2008 -00041 North Pointe - Northwest Residential -prel. (Gerald Gatobu)
Proffered items under phase III road construction are supposed to be complete prior to
this site plan approval.
Proffer V- 5.3.1 -ci is missing from the proffers at the beginning of the plan.
The ingress to the site off route 29 should either be a yield condition or accommodate a
proper merge according to AASHTO standard merge lengths.
The egress onto route 29 needs to have a lane configuration and lengths to accommodate
the queue from the traffic study queue analysis.
The lane shifts on route 29 need to be a minimum of 720 feet in length. The lane shift on
Northwest Passage needs to be in accordance with the design speed of the road.
The CG -6 on the north side of the entrance needs to have a minimum 12 foot offset and
an appropriate taper to tie back into the pavement on route 29.
Road and drainage plans will be needed with the final site plan.
A Land Use Permit will be needed for any work within the VDOT ROW.
SDP - 2008 -00042 Buck Mountain Episcopal Church / Verizon (Melzan Yanit!los)
Sight distance needs to be shown for the connection to Earlysville Road.
SUB - 2008 -00076 Old Trail- Ballard Field Townhomes -Phase III (Summer Frederick)
No comments
Please request the applicants provide a written description of revisions with re- submissions. If you
have any questions or comments, please contact me prior to sharing these comments with the
applicants.
Sincerely,
Joel DeNunzio, P.E.
Residency Program Manager
VDOT Charlottesville Residency
434 -293 -0011
cc Bill Fritz, David Benish, Juan Wade, Elaine Echols, Joan McDowell, Judith Wiegand,
Margaret Maliszewski, David Pennock, Francis McCall, Jon Sharp, Summer Frederick, Patrick
Lawrence, and John Giometti
I W P
County of Albemarle
Department of Community Development
Memorandum
To:Scott Collins (scott @collins- engineering.com)
From:Megan Yaniglos- Senior Planner
Division:Zoning & Current Development
Date:April 2, 2008
Subject:SDP -2008 -038- Flow Automotive- Final Site Plan
The Planner for the Zoning & Current Development Division of the Albemarle County
Department Community Development will recommend approve the plan referred to above when
the following items have been satisfactorily addressed. (The following comments are those that
have been identified at this time. Additional comments or conditions may be added or eliminated
based on further review.) [Each comment is preceded by the applicable reference to the
Albemarle County Code.]
1. There are trees shown over where a drainage easement is required on TMP 78 -15. Show
the drainage easement and revise so that the trees are outside of the drainage easement.
Trees are not permitted in drainage easements.
2. [32.7.9.8] Some of the landscaping proposed are over pipes, move all proposed trees off
of the pipes.
3. [32.7.9.8] Proposed Red Cedars located in the adjacent property, TMP 78 -15 are on the
existing curb, move off of the curb and into the landscape area.
4. [32.7.9.8] There is proposed landscaping shown over existing landscaping. Indicate if the
existing landscaping is to be removed, or move the proposed landscaping off of the
existing.
5. [4.17.4] On the lighting plan, indicate that the proposed fixtures are `Flat Lens' as to
insure full cut -off.
6. [Special Use Permit Condition 451 Final site plan approval is subject to the recordation of
easements for ingress /egress and for the installation, maintenance and use of planter
islands and landscaping on adjacent parcels (Tax Map 78, Parcels 15, 15D and 15E).
Provide easements and deeds of easements for the above mentioned off site
improvements.
Please contact Megan Yaniglos at the Department of Community Development 296 -5832 ext.
3004 for further information.
OF Ale /
r
r
RGINN
County of Albemarle
Department of Community Development
Memorandum
To:Scott Collins (scott @collins - engineering.com)
From:Megan Yaniglos- Senior Planner
Division:Zoning & Current Development
Date:April 2, 2008
Subject:SDP- 2008 -038- Flow Automotive- Final Site Plan
The Planner for the Zoning & Current Development Division of the Albemarle County
Department Community Development will recommend approve the plan referred to above when
the following items have been satisfactorily addressed. (The following comments are those that
have been identified at this time. Additional comments or conditions may be added or eliminated
based on further review.) [Each comment is preceded by the applicable reference to the
Albemarle County Code.]
di --, There are trees shown over where a drainage easement is required on TMP 78 -15. Show
the drainage easement and revise so that the trees are outside of the drainage easement.
X - Yrees are not permitted in drainage easements.
32.7.9.8] Some of the landscaping proposed are over pipes, move all proposed trees off
of the pipes.ll • [32.7.9.8] Proposed Red Cedars located in the adjacent property, TMP 78 -15 are on the
xisting curb, move off of the curb and into the landscape area.
6h. Cv' 32.7.9.8] There is proposed landscaping shown over existing landscaping. Indicate if the
L . existing landscaping is to be removed, or move the proposed landscaping off of the
existing.
17.4] On the lighting plan, indicate that the proposed fixtures are `Flat Lens' as to
insure full cut -off.
6. [Special Use Permit Condition #5] Final site plan approval is subject to the recordation of
easements for ingress /egress and for the installation, maintenance and use of planter
islands and landscaping on adjacent parcels (Tax Map 78, Parcels 15, 15D and 15E).
Provide easements and deeds of easements for the above mentioned off site
improvements.
Please contact Megan Yaniglos at the Department of Community Development 296 -5832 ext.
3004 for further information.
Stij F.J
County of Albemarle
Department of Community Development
Memorandum
To: Scott Collins (scott @collins - engineering.com)
From: Megan Yaniglos- Senior Planner
Division: Zoning & Current Development
Date: April 2, 2008
Subject: SDP - 2008 -038- Flow Automotive- Final Si Plan
The Planner for the Zoning & Current Development Division of the Albemarle County
Department Community Development will recommend approve the plan referred to above when
the following items have been satisfactorily addressed. (The following comments are those that
have been identified at this time. Additional comments or conditions may be added or eliminated
based on further review.) [Each comment is preceded by the applicable reference to the
Albemarle County Code.]
4Yhere are trees shown over where a drainage easement is required on TMP 78 -15. Show
the drainage easement and revise so that the trees are outside of the drainage easement.
Trees are not permitted in drainage easements.
32.7.9.8] Some of the landscaping proposed are over pipes, move all proposed trees off
the pipes.
32.7.9.8] Proposed Red Cedars located in the adjacent property, TMP 78 -15 are on the
Xexisting curb, move off of the curb and into the landscape area.
r[32.7.9.8] There is proposed landscaping shown over existing landscaping. Indicate if the
existing landscaping is to be removed, or move the proposed landscaping off of the
d - existing.
IX.. [4.17.4] On the lighting plan, indicate that the proposed fixtures are 'Flat Lens' as to
insure full cut -off.
Special Use Permit Condition #5] Final site plan approval is subject to the recordation of
easements for ingress /egress and for the installation, maintenance and use of planter
islands and landscaping on adjacent parcels (Tax Map 78, Parcels 15, 15D and 15E).
Provide easements and deeds of easements for the above mentioned off site
improvements.
Please contact Megan Yaniglos at the Department of Community Development 296 -5832 ext.
3004 for further information.
y A :tr
3' y-
County of Albemarle
Department of Community Development
Memorandum
To: Megan Yaniglos, Current Development Project Planner
From: Amy Pflaum, Current Development Engineering Review
Date: 31 March 2008
Subject: Flow Automotive (SDP -2008- 00038)
The final site plan for Flow Automotive has been reviewed. Before engineering can recommend approval
the following items must be addressed:
1. It does not appear that the fill in the southwest corner of the site (near existing STM manhole 5)
can tie to existing grading without exceeding a 2:1 slope. [18- 32.6.6]
2. The disturbance of existing areas of critical slope will require a waiver by the Planning
Commission. [18 -42, 14 -304]
3. One hundred feet on -site sight distance must be maintained by use of curbed islands a minimum 6'
off building corners or other obstructions. Please provide curbed islands (minimum 3'x6') at the
northeast and southeast corners of the existing portion of the building.
4. All parking rows must be protected by curbed islands. The proposed parallel parking along the
eastern property line of the site must be flanked by curbed islands. [18 -4.12]
5, Curbing is required on all parking areas, please show curbing along the proposed parallel parking
on the eastern property line of the site.
6. Proposed parking areas may not exceed 5% grade in any direction. All new parking spaces must
meet this criteria, including those proposed on existing pavement.
7. Proposed sidewalks must be a minimum of 5' wide, exclusive of the curb. Those shown around
the proposed showroom appear to scale less than this. As this is a very "tight" site, please verify
the dimension.
8. Please revise the Sight Distance Exhibit to state proper scale, show lane lines on Route 250, and
shade the site triangles. Please see VDOT Road Design Manual Appendix B, Page B -1 1.
9. Please revise the Easement Exhibit to include information pertaining to the parties easements will
be dedicated to and from.
10. An easement is not required on the portion of the 4" sanitary sewer service lateral that is on the
parcel under review. Where the lateral leaves this parcel and enters another, an easement is
required there. [18- 32.7.4]
11. Please label the two round symbols found in the center of TMP 78 -15E on the Site Plan, they do
not show up on the Existing Conditions Plan.
Current Development
Engineering Review Comments
Page 2 of 2
12. There is an existing retaining wall shown on TMP 78 -15 in the area of proposed grading. Is this
wall to be removed?
13. The labeling of the storm sewer system is confusing. For example, the existing STM manhole
near the southwest corner of the site is labeled as both "EX 1 " and "5 ". On the Profile sheet it is
labeled as "EX STR 1" in one profile and "EX STR 5" in another. Please clarify this labeling. It
is also unclear which portions of the storm sewer pipes are to be abandoned and which are to
remain. Please clarify by shading the existing pipes and labeling the proposed pipes with sizes and
lengths.
14. On the border of the two sheets pertaining to erosion & sediment control, "erosion" is spelled
incorrectly in the title block.
15. Comments on the Drainage Areas and Computations, Stormwater Management Plan, and Erosion
Sediment Control Plan will be forthcoming with the review of the previously submitted WPO
application (WP0200800020).
16. VDOT approval is required for any work affecting the public right -of -way.
17. More comments may be necessary upon resubmittal.
Application #: SDP2O Short Review COmmen s
Project Name: Flow Automotive - Final Final — Non - residential — Administrati
Date Completed: 03/31/2008
Reviewer: Amy Pflaum Engineer Z &CD
Review Status: Requested Changes
Reviews Comments:
Date Completed:
Reviewer:
Review Status:
Reviews Comments:
Date Completed:
Reviewer:
Review Status:
Reviews Comments:
Site Review Meeting 4/3/08, comments due in cityview 3/31/08
03/28/2008
Jay Schlothauer Inspections
Requested Changes
3ased on plans revised December 28, 2007.
3earrange the barrier -free parking spaces so that at least one of them is van - accessible.
03/20/2008
Margaret Maliszewski ARB
Requested Changes
Fhe ARB reviewed this proposal on November 5, 2007. The Board's action, attached, indicates that
mother ARB submittal /review is required.
Page: 1.00 County of Albemarle Printed On: Wednesday, April 02, 2008
Albemarle County
Service Authority
Serving 6 Conserving
TO: Megan Yaniglos
FROM: Gary Whelan, Civil Engineer
DATE: March 28, 2008
RE: Site Plan Technical Review for:Flow Automotive -Final
SDP200800038
TM 78 -15E
The below checked items apply to this site.
X 1. This site plan is within the Authority's jurisdictional area for:
X A. Water and sewer
B. Water only
C. Water only to existing structure
D. Limited service
X 2.A 4 inch water line is located approximately 10' distant.
3.Fire flow from, nearest public hydrant, located distant from this site plan, is
Gpm + at 20 psi residual.
X 4.An 8 inch sewer line is located approximately 10' distant.
5.An Industrial Waste Ordinance survey form must be completed.
X 6.No improvements or obstructions shall be placed within existing or future
easements.
7.and plans are currently under review.
8.and plans have been received and approved.
X 9.No plans are required.
10.Final and plans are required for our review and approval prior to
granting tentative approval.
11.Final site plan may /may not be signed.
12.RWSA approval for water and /or sewer connections.
13.City of Charlottesville approval for sewer.
Comments: Provide plumbing fixture count to size the meter. Backflow prevention
is required. Show water meter location.
The site plan does not show or incorrectly shows:
meter locations water line size
waterline locations sewer line size
sewer line locations expected wastewater flows
easements expected water demands
168 Spotnap Road • Charlottesville • VA 22911 • Tel (434977 -4511 • Fax (434)979 -0698
www.serviceauthoriy.org
l_
County of Albemarle
Department of Community Development
Memorandum
To: Megan Yaniglos, Current Development Project Planner
From: Amy Pflaum, Current Development Engineering Review
Date: 31 March 2008
Subject: Flow Automotive (SDP - 2008 - 00038)
The final site plan for Flow Automotive has been reviewed. Before engineering can recommend approval
the following items must be addressed:
I . It does not appear that the fill in the southwest corner of the site (near existing STM manhole 5)
can tie to existing grading without exceeding a 2:1 slope. [18- 32.6.6]
2. The disturbance of existing reas of critical slope will require a waiver b the Planninggpqyf ';C7
Commission. [18-4.2, 14 -304] v
3. One hundred feet on -site sight distance must be maintained by use of curbed islands a minimum 6'
off building corners or other obstructions. Please provide curbed islands (minimum 3'x6') at the
northeast and southeast corners of the existing portion of the building.
4. All parking rows must be protected by curbed islands. The proposed parallel parking along the
eastern property line of the site must be flanked by curbed islands. [18 -4.12]
5. Curbing is required on all parking areas, please show curbing along the proposed parallel parking
on the eastern property line of the site.
6. Proposed parking areas may not exceed 5% grade in any direction. All new parking spaces must
meet this criteria, including those proposed on existing pavement.
7. Proposed sidewalks must be a minimum of 5' wide, exclusive of the curb. Those shown around
the proposed showroom appear to scale less than this. As this is a very "tight" site, please verify
the dimension.
8. Please revise the Sight Distance Exhibit to state proper scale, show lane lines on Route 250, and
shade the site triangles. Please see VDOT Road Design Manual Appendix B. Page B -1 1.
9. Please revise the Easement Exhibit to include information pertaining to the parties easements will
be dedicated to and from.
10. An easement is not required on the portion of the 4" sanitary sewer service lateral that is on the
parcel under review. Where the lateral leaves this parcel and enters another, an easement is
required there. [18- 32.7.4]
11. Please label the two round symbols found in the center of TMP 78 -15E on the Site Plan. they do
not show up on the Existing Conditions Plan.
Current Development
Engineering Review Comments
Page 2 of 3
12. There is an existing retaining wall shown on TMP 78 -15 in the area of proposed grading. Is this
wall to be removed.'
13. The labeling of the storm sewer system is contusing. For example, the existing STM manhole
near the southwest corner of the site is labeled as both " EX I" and "5 ". On the Profile sheet it is
labeled as "EX STR 1 in one profile and "EX STR 5" in another. Please clarify this labeling. It
is also unclear which portions of the storm sewer pipes are to be abandoned and which are to
remain. Please clarify by shading the existing pipes and labeling the proposed pipes with sizes and
lengths.
14. On the border of the two sheets pertaining to erosion & sediment control, "erosion " is spelled
incorrectly in the title block.
15. Comments on the Drainage Areas and Computations, Stormwater Management Plan, and Erosion
Sediment Control Plan will be forthcoming with the review of the previously submitted WPO
application (WPO200800020).
16. VDOT approval is required for any work affecting the public right -of -way.
17. More comments may be necessary upon resubmittal.
rt 71y
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
To: Megan Yaniglos, Senior Planner
From: Amy Pflaum, Engineer
Subject: SDP - 2008 - 00038, Flow Automotive, Final Site Plan, Critical Slope Waiver
Request
Date received: 15 April 2008
Date of Comment: 23 April 2008
The request for a waiver to develop on areas of critical slope for grading incorporated with the new
construction proposed on TMP's 78 -15D and 78 -15E was received on 15 April 2008. The existing critical
slopes and proposed grading are shown on the Final Site Plan dated February 20, 2008.
The engineering analysis of the request follows:
Description of critical slope area and proposed disturbance:
The critical slope areas within TMP's 78 -15D and 78 -15E appear to contain both natural and man -made
slopes. The apparent man -made slopes appear to have been embankments created when asphalt and gravel
parking and travelways were constructed on the Flow Automotive site. The presumably natural critical
slopes are wooded low spots on TMP 78 -15E.
The critical slope disturbances are in the form of commercial construction including parking spaces,
landscaped curb islands, underground detention and stormwater facilities.
Areas Acres
Total site area 1.95
Area of critical slopes
man -made & natural)
Man -made = 0.09
Natural = 0.07
4.6% of development
3.6% of development
Total critical slopes area 0.16 8.2% of development
Total critical slopes disturbed 0.16 100% of critical slopes
Below, each of the concerns of Zoning Ordinance section 18 -4.2 is addressed:
rapid and /car large scale movement nfsoil and reek ": The areas of existing critical slopes
on this site are small and scattered. In most cases, the slopes are being tilled over rather than
cut into. Large scale movement of soil and rock is not anticipated to occur as a result of this
construction.
2. "evicessihe storrr7tirater run- nff "': The applicant has submitted a Storm water Management
Plan which is being reviewed for County compliance. Stormwater facilities are being
Albemarle County Community Development
Engineering Review comments
Page 2 of 2
proposed to control the drainage generated by this site through underground detention and
proper conveyance systems. Excessive stormwater runoff is not expected as a result of
disturbance of these critical slopes.
3. "siltation of'zurtrncrl crncl nurzz -Horde hoclies nf'lruter ": The applicant has submitted an
Erosion and Sediment Control Plan which is being reviewed for County compliance. The
submitted Plan consists of two phases — the first providing E &S control measures during
earth - moving activities such as dust control, silt fence and temporary seeding, and the second
proposing storm sewer inlet protection and permanent seeding on exposed ground during the
final stages of construction. These measures are anticipated to reduce sediment -laden runoff
from leaving the site. Inspection and bonding by the County will ensure siltation control
during construction. Proper stabilization and maintenance will ensure long tern stability.
4. "lass crf aesthetic r•esotwce ": The disturbance of the existing critical slopes with this
development does involve the removal of existing trees. The applicant has submitted a
detailed landscaping plan which includes the addition of several trees and shrubs
anticipated to screen and enhance the proposed parking area. This site is located within
the highly visible Entrance Corridor along Route 250, and is therefore subject to approval by
the ARB.
5. "septic effluent ": No septic systems or drainfields are proposed in this project. This site is
accessible to the public sanitary sewer system.
This site does drain into a waterway that is a public drinking water supply for Albemarle County. No
portion of this site plan is located inside the 100 -year flood plain area according to FEMA Maps, dated 04
February 2005.
Based on the above review, there are no engineering concerns which prohibit the disturbance of the critical
slopes as shown on the plans.
Copy: SDP -2008- 00038, Flow Automotive Final Site Plan
File: El_csw_ADP_sdp200800038
ALg }
IRGIN
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, North Wing
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4012
May 15, 2008
Collins Engineering - Scott Collins
800 E Jefferson Street
Charlottesville, VA 22902
RE: SDP200800038 Flow Automotive — Final
Tax Map 78, Parcel 151), Tax Map 78, and Parcel 15E
Dear Mr. Collins:
The Albemarle County Planning Commission, at its meeting on, May 6, 2008 approved the above -noted
petition, Critical Slopes Waiver, Section 4.2, by a vote of 6:0,
If you should have any questions or comments regarding the above noted action, please do not hesitate to
contact me at (434) 296 -5832.
Sincerely,
I c
Megan Yani' I99
Planner
Zoning and Current Development Division
MY /SM
Cc: Flow Companies
1425 Plaza Drive
Winston -Salem NC 27103
i >krnti'r
County of Albemarle
Department of Community Development
Memorandum
To: Patrick Lawrence, Planner
From: Amy Pflaum, Engineering Review
Division: Current Development
Date: June 11, 2008
Subject: SUB200800105, 106, 107 Flow Automotive (SDP200800038, WP0200800020)
The easements for Flow Automotive, TM 78, Parcels 14D, 15D and 15E, received on 24 April 2008, has been
reviewed. The engineering review for current development can not recommend approval of the easements until
the following items are adequately addressed:
A. SUB200800105:
1. Because the proposed 24 -inch storm sewer pipe between inlets EX 1 and EX4 will be approximately 20-
feet deep, a standard 20 -foot easement will not be adequate. Although it is understood that a portion of
this easement will be on the neighboring property (TMP 78 -15), it appears that the portion on TMP 78-
15E will need to be increased. Please see the Albemarle County Design Standards Manual for the
required width.
2. Drainage easements must be labeled as "dedicated to public use ".
B. SUB200800106:
The 14 -foot wide strip along the Route 250 right -of -way is shown differently on the site plan
SDP200800038). On the site plan, at the eastern end, the strip is only 8 -feet wide. Please revise the
plans to match.
C. SUB200800107:
4. Because the proposed 24 -inch storm sewer pipe between inlets EX 1 and EX4 will be approximately 20-
feet deep, a standard 20 -foot easement will not be adequate. Although it is understood that a portion of
this easement will be on the neighboring property (TMP 78 -15E), it appears that the portion on TMP 78-
15 will need to be increased. Please see the Albemarle County Design Standards Manual for the required
width.
Drainage easements must be labeled as "dedicated to public use ".
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832
Project:
Plan preparer:
Plan received date
Date of comments:
Reviewer:
Fax (434) 972 - 4126
Flow Automotive - Final [SDP200800038]
Collins Engineering [email: ,cottiei colliiis- enLIiieet_in.colliI
1 I Mar 2008
16 Apr 2008 (Rev I)
19 May 2008 (Rev2)
31 Mar 2008
24 Apr 2008 (Rev I )
03 .July 2008 (Rev2)
Amy Pt7aum, Jonathan Sharp (Rev], Rev2)
The final site plan for Flow Automotive has been reviewed. Before engineering can recommend approval
the following items must be addressed:
A. Final Site Plan comments
6. Proposed parking areas may not exceed 5% grade in any direction. All new parking spaces must
meet this criteria, including those proposed on existing pavement.
Revl: An administrative waiver request, for this item is being reviewed by Engineering and Zoning
stuff
Rev?: ?
Current Development
Engineering Review Comments
Page 2 of 5
9. Please revise the Easement Esbibit to include information pertaining to the parties easements will
be dedicated to and from.
Reel: All offsitc drainage easements and anY necessary construction easements urill need to he
recorded prior to inal .site plan approval.
Rev2: Easement comments are attached at the end of the comment letter. Any drainage
easentents dedicated to public nse ttntst be accompanied by a deed approved by the County
Attorney.
16. VDOT approval is required for any work affecting the public right -of -way.
Rev 1. ,4 copy of the plans has heen fcurirarded to VDOT for review.
Rev2: We have not} , et received any continents front VDOT. The latest copy of the plans should
have been forwarded to VDOT for review.
17.
Additional comments:
Current Development
Engineering Review Comments
Page 3 of 5
26. Please include the following on the pipe profiles:
a. A VDOT designation for each structure
b. A throat length or grate type for each inlet.
c. Inlet shaping (IS - I) in all structures
d. Safety slabs (SL -1) in any structures taller than 12 feet.
Rev2: comments not addresser.
29. All spreads must be less than 10 feet.
Rev2: No inlet calculations have been provided with tWs submittal.
B. Stormwater Management comments
30. Please provide a Stormwater Maintenance Agreement signed by the land owners of TMP 78 -14D,
15D, and 15E. Please include the appropriate $17 fee. Please send to Pam Shifflett.
Rev2: comments not addressed.
33. Please label the elevations of the orifice and weir, and label the weir length and location in the
manhole (is it centered in the manhole ?).
Rev2: The proposed pipe configuration out letting from the raintanks is inadequate. The pipe
inverts are too close together and are overlapping.
Current Development
Engineering Review Comments
Page 4 of 5
42. A SWM bond will be computed by the County once the plans have been approved.
C. Erosion Control Plans
47. Please clearly show details of how the TSD will tie into a manhole. Safety is a concern. The
manhole will be upwards of 15 feet deep and is very close to pedestrian areas.
Rev2: Will the manhole be large enough for the TSD to fit inside it? A standard VDOT
manhole only has a 20.5" opening.
49. Please provide calculations to show that the downstream drainage system is adequate. [MS -19]
Rev2: An analysis should be providedfrom the site clown to the Rivanna River (floodplain).
50. An ESC bond will be computed by the County once the plans have been approved.
t
j
Current Development
Engineering Review Comments
Page 5 of 5
katA
County of Albemarle
Department of Community Development
Memorandum
To: Patrick Lawrence, Planner
From: Amy Pflaum, Engineering Review
Division: Current Development
Date: June 11, 2008
Subject: SUB200800105, 106, 107 Flow Automotive (SDP200800038, WP0200800020)
The easements for Flow Automotive, TM 78, Parcels 14D, 15D and 15E, received on 24 April 2008, has
been reviewed. The engineering review for current development can not recommend approval of the
easements until the following items are adequately addressed:
A. SUB200800105:
1. Because the proposed 24 -inch storm sewer pipe between inlets EX I and EX4 will be
approximately 20 -feet deep, a standard 20 -foot easement will not be adequate. Although it is
understood that a portion of this easement will be on the neighboring property (TMP 78 -15), it
appears that the portion on TMP 78 -15F will need to be increased. Please see the Albemarle
County Design Standards Manual for the required width.
2. Drainage easements must be labeled as "dedicated to public use
B. SUB200800106:
3. The 14 -foot wide strip along the Route 250 right -of -way is shown differently on the site plan
SDP200800038). On the site plan, at the eastern end, the strip is only 8 -feet wide. Please revise
the plans to match.
C. SUB200800107:
4. Because the proposed 24 -inch storm sewer pipe between inlets EX and EX4 will be
approximately 20 -feet deep, a standard 20 -foot easement will not be adequate. Although it is
understood that a portion of this easement will be on the neighboring property (TMP 78 -15E), it
appears that the portion on TMP 78 -15 will need to be increased. Please see the Albemarle
County Design Standards Manual for the required width.
5. Drainage easements must be labeled as "dedicated to public use ".